On 21 March Coal India Limited revealed its decision to adopt an Engineering, Procurement, and Construction (EPC) model for coal gasification projects, aiming to enhance project viability by mitigating risks for plant operators. This strategic shift ensures that the entire equity required for project capital expenditure will be provided by special purpose vehicles rather than the plant operator appointed to manage these sophisticated units for coal-to-chemical and coal gasification processes.
The EPC model, also known as turnkey construction contracts, is commonly utilised for intricate infrastructure initiatives.
"We have chosen the EPC contract model to make the execution of gasification projects more attractive, reducing risks for operators. This approach will facilitate expedited project implementation," stated B Veera Reddy, Director (Technical) of Coal India, on the sidelines of the 17th Indian Coal Markets Conference organised by mjunction.
Coal India has unveiled plans to establish coal gasification plants to achieve the target of gasifying 100 MT of coal by 2030. The company has already entered into MoUs with Public Sector Undertakings (PSUs) for joint ventures (JVs) in this domain.
A JV agreement was inked with GAIL for establishing a Coal-to-SNG Project at the Sonepur Bazari Area of Eastern Coalfields Limited (ECL) in West Bengal, with an estimated project cost of Rs 1,305.281 billion. Additionally, MoUs have been signed with BHEL for setting up a Coal-to-Ammonium Nitrate Project at the Lakhanpur Area of Mahanadi Coalfields Limited (MCL) in Odisha, with an estimated project cost of Rs 1,178.2 billion.
Coal India has secured cabinet approval for equity investment in these projects.
Regarding coal production, Reddy disclosed that the company has produced 735 million tonnes and aims to reach the target of 780 million tonnes. However, production may be limited to 770 million tonnes due to issues in South Eastern Coalfields Ltd. Nonetheless, Reddy expressed confidence in achieving the one billion production target by 2028-26, asserting that all necessary plans are in place.
He also highlighted the company's focus on underground mining as part of its sustainability action plan.
Meanwhile, a provision of Rs 40.5 billion has been allocated exclusively for government PSUs, where up to three projects will receive support through a lump-sum grant of Rs 13.5 billion each or 15% of the capital expenditure, whichever is lower, as viability gap funding. This allocation forms part of the total Rs 85 billion viability gap funding provision for coal gasification projects.
On 21 March Coal India Limited revealed its decision to adopt an Engineering, Procurement, and Construction (EPC) model for coal gasification projects, aiming to enhance project viability by mitigating risks for plant operators. This strategic shift ensures that the entire equity required for project capital expenditure will be provided by special purpose vehicles rather than the plant operator appointed to manage these sophisticated units for coal-to-chemical and coal gasification processes.
The EPC model, also known as turnkey construction contracts, is commonly utilised for intricate infrastructure initiatives.
We have chosen the EPC contract model to make the execution of gasification projects more attractive, reducing risks for operators. This approach will facilitate expedited project implementation, stated B Veera Reddy, Director (Technical) of Coal India, on the sidelines of the 17th Indian Coal Markets Conference organised by mjunction.
Coal India has unveiled plans to establish coal gasification plants to achieve the target of gasifying 100 MT of coal by 2030. The company has already entered into MoUs with Public Sector Undertakings (PSUs) for joint ventures (JVs) in this domain.
A JV agreement was inked with GAIL for establishing a Coal-to-SNG Project at the Sonepur Bazari Area of Eastern Coalfields Limited (ECL) in West Bengal, with an estimated project cost of Rs 1,305.281 billion. Additionally, MoUs have been signed with BHEL for setting up a Coal-to-Ammonium Nitrate Project at the Lakhanpur Area of Mahanadi Coalfields Limited (MCL) in Odisha, with an estimated project cost of Rs 1,178.2 billion.
Coal India has secured cabinet approval for equity investment in these projects.
Regarding coal production, Reddy disclosed that the company has produced 735 million tonnes and aims to reach the target of 780 million tonnes. However, production may be limited to 770 million tonnes due to issues in South Eastern Coalfields Ltd. Nonetheless, Reddy expressed confidence in achieving the one billion production target by 2028-26, asserting that all necessary plans are in place.
He also highlighted the company's focus on underground mining as part of its sustainability action plan.
Meanwhile, a provision of Rs 40.5 billion has been allocated exclusively for government PSUs, where up to three projects will receive support through a lump-sum grant of Rs 13.5 billion each or 15% of the capital expenditure, whichever is lower, as viability gap funding. This allocation forms part of the total Rs 85 billion viability gap funding provision for coal gasification projects.
Next Story
Govt Launches Massive Tribal Outreach Across 100,000 Villages
In a landmark move towards inclusive governance and tribal empowerment, the Government of India has launched the Dharti Aaba Janbhagidari Abhiyan, a large-scale nationwide benefit saturation campaign. The initiative aims to ensure that critical government schemes and entitlements reach every eligible tribal household across the country.Union Minister of Tribal Affairs, Shri Jual Oram, hailed the Abhiyan as a historic stride towards realising Prime Minister Narendra Modi鈥檚 Antyodaya vision 鈥� empowering the last person in the queue. He emphasised that this campaign is not just about deliveri..
Next Story
Top PMO Official Reviews Dholera, Lothal Mega Projects
Dr P. K. Mishra, Principal Secretary to the Prime Minister, conducted an extensive review of major infrastructure and heritage projects in Dholera and Lothal, Gujarat, reinforcing the government鈥檚 push for industrial and economic transformation aligned with Prime Minister Narendra Modi鈥檚 vision.Dr Mishra visited the Ahmedabad鈥揇holera Greenfield Expressway, currently under construction by the National Highways Authority of India (NHAI). He underlined the importance of the expressway in reducing travel time between Ahmedabad and Dholera to just 45 minutes and urged adherence to global cons..
Next Story
India, Cyprus Agree on Strategic Road Map, Security Ties
Prime Minister Narendra Modi held formal talks with the President of the Republic of Cyprus, Nikos Christodoulides, at the Presidential Palace in Nicosia. President Christodoulides personally welcomed Prime Minister Modi at the airport a day earlier, highlighting the deep mutual respect and enduring friendship between the two nations.During the meeting, the leaders reaffirmed their shared democratic values and mutual respect for sovereignty and territorial integrity. Prime Minister Modi expressed gratitude to Cyprus for its strong condemnation of the April 2025 terrorist attack in Pahalgam and..