Government Issues Bidding Guidelines for Pumped Storage Projects
POWER & RENEWABLE ENERGY

Government Issues Bidding Guidelines for Pumped Storage Projects

The Ministry of Power has released tariff-based competitive bidding guidelines for procuring stored energy from existing, under-construction, or new Pumped Storage Projects (PSP). 
According to the National Electricity Plan 2023, India will require 74 GW/411 GWh of energy storage systems (ESS) by 2031-32, including 27 GW/175 GWh from PSPs and 47 GW/236 GWh from Battery Energy Storage Systems (BESS). 

Procurement models 

Mode 1: PSPs developed on sites identified by the procurer 

鈥� The procurer selects the site, and the project is developed on a Build-Own-Operate-Transfer (BOOT) basis for 25 to 40 years. 
鈥� A Special Purpose Vehicle (SPV) will handle pre-feasibility activities, including environmental and statutory clearances. 
鈥� The SPV, initially owned by the procurer, will be transferred to the successful bidder at a pre-specified cost. 

Mode 2: PSPs identified by the bidder or already commissioned 

鈥� PSPs may be developed on self-identified sites or existing facilities on a Build-Own-Operate (BOO) basis for 15 to 40 years. 
鈥� Developers must secure environmental, forest, and land clearances before construction. 
鈥� The procurer is not responsible for clearance-related delays. 

Key bidding criteria Minimum bid capacity 

鈥� ISTS-connected projects: 50 MW 
鈥� InSTS-connected projects: 10 MW (lower capacities may be permitted in the Northeast and Special Category States). 

Eligibility requirements 
鈥� Developers must have infrastructure project experience from the last five years. 
鈥� Minimum capital expenditure thresholds will be defined in the bidding documents. 
鈥� Net worth or assets under management must be at least 20% of the estimated capital cost of the project. 

Financial obligations 
鈥� Earnest Money Deposit (EMD): 2% of the estimated project cost. 
鈥� Performance Bank Guarantee (PBG): 5% of the estimated project cost. 

Contractual and regulatory framework 
鈥� The Power Purchase Agreement (PPA) must be signed within six months of the Letter of Award (LoA), or the awarded capacity may be cancelled. 
鈥� The tariff adoption process must be completed within 60 days of application to the relevant Commission. 

Additional provisions 
鈥� Transmission connectivity: Developers must secure access to the ISTS network at their own cost. 
鈥� Force majeure: Developers must notify the procurer within 15 days of any such event. 
鈥� Financial closure: Must be completed within 12 months, with penalties for delays. 
鈥� Minimum commissioning capacity: 50% of the project capacity or 50 MW, whichever is lower. 

The government has also modified its budgetary support for hydroelectric and PSP projects, allocating Rs 124.6 billion for development. These guidelines aim to accelerate energy storage expansion and support India鈥檚 growing renewable energy sector. 
(Mercom) 

The Ministry of Power has released tariff-based competitive bidding guidelines for procuring stored energy from existing, under-construction, or new Pumped Storage Projects (PSP). According to the National Electricity Plan 2023, India will require 74 GW/411 GWh of energy storage systems (ESS) by 2031-32, including 27 GW/175 GWh from PSPs and 47 GW/236 GWh from Battery Energy Storage Systems (BESS). Procurement models Mode 1: PSPs developed on sites identified by the procurer 鈥� The procurer selects the site, and the project is developed on a Build-Own-Operate-Transfer (BOOT) basis for 25 to 40 years. 鈥� A Special Purpose Vehicle (SPV) will handle pre-feasibility activities, including environmental and statutory clearances. 鈥� The SPV, initially owned by the procurer, will be transferred to the successful bidder at a pre-specified cost. Mode 2: PSPs identified by the bidder or already commissioned 鈥� PSPs may be developed on self-identified sites or existing facilities on a Build-Own-Operate (BOO) basis for 15 to 40 years. 鈥� Developers must secure environmental, forest, and land clearances before construction. 鈥� The procurer is not responsible for clearance-related delays. Key bidding criteria Minimum bid capacity 鈥� ISTS-connected projects: 50 MW 鈥� InSTS-connected projects: 10 MW (lower capacities may be permitted in the Northeast and Special Category States). Eligibility requirements 鈥� Developers must have infrastructure project experience from the last five years. 鈥� Minimum capital expenditure thresholds will be defined in the bidding documents. 鈥� Net worth or assets under management must be at least 20% of the estimated capital cost of the project. Financial obligations 鈥� Earnest Money Deposit (EMD): 2% of the estimated project cost. 鈥� Performance Bank Guarantee (PBG): 5% of the estimated project cost. Contractual and regulatory framework 鈥� The Power Purchase Agreement (PPA) must be signed within six months of the Letter of Award (LoA), or the awarded capacity may be cancelled. 鈥� The tariff adoption process must be completed within 60 days of application to the relevant Commission. Additional provisions 鈥� Transmission connectivity: Developers must secure access to the ISTS network at their own cost. 鈥� Force majeure: Developers must notify the procurer within 15 days of any such event. 鈥� Financial closure: Must be completed within 12 months, with penalties for delays. 鈥� Minimum commissioning capacity: 50% of the project capacity or 50 MW, whichever is lower. The government has also modified its budgetary support for hydroelectric and PSP projects, allocating Rs 124.6 billion for development. These guidelines aim to accelerate energy storage expansion and support India鈥檚 growing renewable energy sector. (Mercom) 

Next Story
Infrastructure Urban

Reliance, Diehl Advance Pact for Precision-Guided Munitions

Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..

Next Story
Infrastructure Urban

Modis Navnirman to Migrate to Main Board, Merge Subsidiary

Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..

Next Story
Infrastructure Urban

Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025

The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement