Real estate developers fear project delays due to Covid-19: CREDAI
11 Jun 2021
2 Min Read
CW Team
As per the survey report given by the Confederation of Real Estate Developers' Associations of India (CREDAI), over 95% of real estate developers consider project delays if no urgent relief measures are introduced by the government and RBI in the sector.
These delays are due to a range of factors, with 92% of developers undergoing labor shortage at sites, 83% of developers are operating with less than half the workforce, and over 82% of developers are experiencing project approval delays.
To evaluate the impact of the second wave of Covid-19 on the real estate sector in India, CREDAI issued findings of its first-ever industry survey carried across North, East, West and South zones between May 24 and June 3, 2021. The exploratory survey, conducted with a stratified sampling method, witnessed first-of-its-kind extensive participation of 4,813 developers from 217 cities, offering critical insights on the industry view and the list of challenges faced by the real estate sector.
A staggering 98% of developers are experiencing decreased customer enquiries, and 42% of developers are experiencing a 75% drop in customer enquiries. Also, the report unveils that the second wave has induced 95% of customers to postpone their purchase decisions.
The apex developers� body also thinks that decreasing the cost of construction materials, work commencement and implementing single-window clearances for project approvals, and providing an input tax credit for all sectors will support the business.
CREDAI believes that continued and adequate policy support is crucial for the revival of the Indian economy, as the real estate sector estimates for 6-7% of GDP, is the second-largest employer, and is a business dynamo for over 270 ancillary industries in the nation.
Harsh Vardhan Patodia, President of CREDAI National, stated that the real estate sector exhibited tremendous resilience in bouncing back on a circumspect recovery path post the first wave, despite little relief measures. However, the second wave has urged them to reflect and re-evaluate the development path of the industry, and they thought it was essential to estimate the challenges faced by the customers and industry partners in light of the recent developments. The findings unveil that the second wave has had a more debilitating influence on the real estate sector than the first wave.
Also read: Rising steel, cement prices to impact real estate
Also read: Falling demand to control soaring steel prices
As per the survey report given by the Confederation of Real Estate Developers' Associations of India (CREDAI), over 95% of real estate developers consider project delays if no urgent relief measures are introduced by the government and RBI in the sector.
These delays are due to a range of factors, with 92% of developers undergoing labor shortage at sites, 83% of developers are operating with less than half the workforce, and over 82% of developers are experiencing project approval delays.
To evaluate the impact of the second wave of Covid-19 on the real estate sector in India, CREDAI issued findings of its first-ever industry survey carried across North, East, West and South zones between May 24 and June 3, 2021. The exploratory survey, conducted with a stratified sampling method, witnessed first-of-its-kind extensive participation of 4,813 developers from 217 cities, offering critical insights on the industry view and the list of challenges faced by the real estate sector.
A staggering 98% of developers are experiencing decreased customer enquiries, and 42% of developers are experiencing a 75% drop in customer enquiries. Also, the report unveils that the second wave has induced 95% of customers to postpone their purchase decisions.
The apex developers� body also thinks that decreasing the cost of construction materials, work commencement and implementing single-window clearances for project approvals, and providing an input tax credit for all sectors will support the business.
CREDAI believes that continued and adequate policy support is crucial for the revival of the Indian economy, as the real estate sector estimates for 6-7% of GDP, is the second-largest employer, and is a business dynamo for over 270 ancillary industries in the nation.
Harsh Vardhan Patodia, President of CREDAI National, stated that the real estate sector exhibited tremendous resilience in bouncing back on a circumspect recovery path post the first wave, despite little relief measures. However, the second wave has urged them to reflect and re-evaluate the development path of the industry, and they thought it was essential to estimate the challenges faced by the customers and industry partners in light of the recent developments. The findings unveil that the second wave has had a more debilitating influence on the real estate sector than the first wave.
Image Source
Also read: Rising steel, cement prices to impact real estate
Also read: Falling demand to control soaring steel prices
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..