Supply chain management at Bogibeel Bridge
01 Feb 2019
2 Min Read
Editorial Team
India recently welcomed one of its biggest landmarks! The country鈥檚 longest rail-cum-road bridge鈥擝ogibeel Bridge over river Brahmaputra in Assam鈥攚as recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997.
HCC follows the Just-In-Time (JIT) inventory system where it produces or acquires materials and products as per demand. This is a key component of its supply chain. At the Bogibeel Bridge project, the team used a combination of rail and road transport to deliver 80,000 tonne of steel plates from various parts of the country to the remote project site in Assam. The orders for extra wide plates were placed in advance as per the design of the superstructure. In this way, the team avoided any possible mismatch of material and ensured qualitative and timely execution of the job.
鈥淭he steel used in the construction of the bridge is special grade, confined to E410CBC,鈥� says RVR Kishore, Project Director, HCC. Steel plates and sections were procured mainly from three sources: JSPL, Essar and SAIL. Of these 80,000 mt, about 20,000 mt (25 per cent scope) was categorised as ODC (over dimension cargo) and attracted special measures for transport to the project site from the sources in Hazira and Angul.
A procurement plan was made according to minimum order quantity required thickness-wise, also estimating future market price trends as the order lot sizes range from 3,500 mt to 10,000 mt. Also, for the construction of the bridge, Kishore adds, 鈥淧lasma cutting machines for the cutting of material, automated-box making machines, levelling machines and robotic welding machines were imported from Canada.鈥�
India recently welcomed one of its biggest landmarks! The country鈥檚 longest rail-cum-road bridge鈥擝ogibeel Bridge over river Brahmaputra in Assam鈥攚as recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997.
HCC follows the Just-In-Time (JIT) inventory system where it produces or acquires materials and products as per demand. This is a key component of its supply chain. At the Bogibeel Bridge project, the team used a combination of rail and road transport to deliver 80,000 tonne of steel plates from various parts of the country to the remote project site in Assam. The orders for extra wide plates were placed in advance as per the design of the superstructure. In this way, the team avoided any possible mismatch of material and ensured qualitative and timely execution of the job.
鈥淭he steel used in the construction of the bridge is special grade, confined to E410CBC,鈥� says RVR Kishore, Project Director, HCC. Steel plates and sections were procured mainly from three sources: JSPL, Essar and SAIL. Of these 80,000 mt, about 20,000 mt (25 per cent scope) was categorised as ODC (over dimension cargo) and attracted special measures for transport to the project site from the sources in Hazira and Angul.
A procurement plan was made according to minimum order quantity required thickness-wise, also estimating future market price trends as the order lot sizes range from 3,500 mt to 10,000 mt. Also, for the construction of the bridge, Kishore adds, 鈥淧lasma cutting machines for the cutting of material, automated-box making machines, levelling machines and robotic welding machines were imported from Canada.鈥�
Next Story
Concorde Acquires 3 Acre in Hennur for Premium High-Rise Project
In a strategic expansion move, Concorde has acquired a 3-acre land parcel in Hennur, North Bengaluru, for a premium high-rise residential development. The upcoming project will feature a saleable built-up area of approximately 4.25 lakh sq. ft., with an estimated Gross Development Value (GDV) of Rs 5 billion. Scheduled for launch in FY 2026鈥�27, the development will offer 2 and 3 BHK premium residences designed to appeal to discerning urban homebuyers seeking elevated, community-centric living in one of the city's fastest-growing corridors. 鈥淭his investment underlines our commitme..
Next Story
JP Infra Launches Monsoon Fest 2025 for 亚博体育官网首页buyers
JP Infra, one of Mumbai鈥檚 most trusted real estate developers, has announced the launch of 鈥楳onsoon Fest 2025鈥�, a limited-period campaign offering exclusive privileges across its residential projects in Mira Road, Thane, and other key locations. Running from 16th June to 31st July 2025, the Monsoon Fest presents a curated package of benefits for homebuyers. Every booking comes with an assured premium White Goods voucher from leading brands. Buyers can also choose one of three value-added offers: 50 per cent waiver on stamp duty Modular kitchen Fully furnished home&nbs..
Next Story
LANXESS Resin Removes Short-Chain PFAS From Water
Speciality chemicals company LANXESS has launched Lewatit MDS TP 108, a new ion exchange resin designed for the efficient removal of short-chain per- and polyfluoroalkyl substances (PFAS) from water. These PFAS compounds鈥攃haracterised by having three or fewer carbon atoms鈥攁re among the smallest and most challenging to eliminate through conventional water purification methods.Lewatit MDS TP 108 marks a significant advancement in the treatment of contaminated water, particularly where traditional technologies such as activated carbon adsorption fall short. The new resin offers a service life..