ÑDz©ÌåÓý¹ÙÍøÊ×Ò³

449 infra projects sees cost overruns of Rs 5.1 trillion
ECONOMY & POLICY

449 infra projects sees cost overruns of Rs 5.1 trillion

According to the Ministry of Statistics and Programme Implementation (MoSPI) report, nearly 449 infrastructure projects out of 1,873 projects, each with an investment of Rs 1.5 billion and above, were hit by a cost overrun of more than Rs 5.01 trillion in March 2024. It also indicated that 779 projects were delayed. The expense on these projects until March 2024 is Rs 17.11 trillion., which is 53.68% of the anticipated cost of the projects. However, the number of delayed projects decreased to 567 if the delay was calculated on the basis of the latest schedule of completion. It further said that 393 projects have neither the tentative gestation duration nor the year of commissioning disclosed. Of the 779 projects that have been postponed, 202 have been delayed for a total of 1 to 12 months, 181 for 13 to 24 months, 277 for 25 to 60 months, and 119 for longer than 60 months. 36.04 months is the average time overrun for these 779 delayed projects. Various project implementing agencies have indicated that delays in land acquisition, gaining approvals related to the environment and forests, and a lack of infrastructural support and connectivity are among the reasons for schedule overruns. Among other things, delays in securing project funding, completion of technical engineering, scope changes, tendering, ordering, and equipment delivery, and issues with law and order The 1,873 projects' total estimated completion cost is expected to be Rs 31.88 trillion, reflecting an overall cost overrun of Rs 5.01 trillion (18% of the original cost). The 1,873 projects' total initial cost of execution was Rs 26.87 trillion. The study also attributed the delay in these projects' completion to state-level lockdowns brought on by COVID-19, which were implemented in 2020 and 2021. Additionally, it has been noted that many project execution agencies are failing to provide updated cost estimates and commissioning timelines, which raises the possibility that time and cost overrun statistics are being underreported.

According to the Ministry of Statistics and Programme Implementation (MoSPI) report, nearly 449 infrastructure projects out of 1,873 projects, each with an investment of Rs 1.5 billion and above, were hit by a cost overrun of more than Rs 5.01 trillion in March 2024. It also indicated that 779 projects were delayed. The expense on these projects until March 2024 is Rs 17.11 trillion., which is 53.68% of the anticipated cost of the projects. However, the number of delayed projects decreased to 567 if the delay was calculated on the basis of the latest schedule of completion. It further said that 393 projects have neither the tentative gestation duration nor the year of commissioning disclosed. Of the 779 projects that have been postponed, 202 have been delayed for a total of 1 to 12 months, 181 for 13 to 24 months, 277 for 25 to 60 months, and 119 for longer than 60 months. 36.04 months is the average time overrun for these 779 delayed projects. Various project implementing agencies have indicated that delays in land acquisition, gaining approvals related to the environment and forests, and a lack of infrastructural support and connectivity are among the reasons for schedule overruns. Among other things, delays in securing project funding, completion of technical engineering, scope changes, tendering, ordering, and equipment delivery, and issues with law and order The 1,873 projects' total estimated completion cost is expected to be Rs 31.88 trillion, reflecting an overall cost overrun of Rs 5.01 trillion (18% of the original cost). The 1,873 projects' total initial cost of execution was Rs 26.87 trillion. The study also attributed the delay in these projects' completion to state-level lockdowns brought on by COVID-19, which were implemented in 2020 and 2021. Additionally, it has been noted that many project execution agencies are failing to provide updated cost estimates and commissioning timelines, which raises the possibility that time and cost overrun statistics are being underreported.

Next Story
Infrastructure Transport

Dassault To Build Falcon Jets In India With Reliance

Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..

Next Story
Infrastructure Urban

INDEA Lays Foundation for India’s First Auto Design School

The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..

Next Story
Infrastructure Transport

Karnataka Launches Global Innovation Hub at Airport City

The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement