Acquire 80% land for Pune Ring Road Project by Feb 15
19 Jan 2024
2 Min Read
CW Team
The Pune collector Rajesh Deshmukh was instructed by the Maharashtra State Road Development Corporation (MSRDC) to complete 80% of the necessary land acquisition for the 136.8 km outer Pune ring road project by February 15. They expressed their hope to issue the letter of intent for the project before the commencement of the actual work, anticipated to begin post-monsoon.
The officer stated that due to the involvement of revenue machinery in poll-related activities, the deadline for land acquisition had been advanced. This same deadline was given to collectors of Mumbai, Raigad, for the Virar-Alibaug multi-purpose corridor, and the Jalna collector for the Jalna-Nanded Expressway.
The total cost for land acquisition of the three projects was estimated to be around Rs 180 billion. The Pune ring road required the acquisition of 1,700 hectares, the Virar-Alibaug corridor needed around 1,000 hectares, and the Jalna-Nanded project involved the acquisition of approximately 2,000 hectares.
As per the local MSRDC official, only 60% of the land had been acquired for the Pune ring road project at present. However, he expressed confidence that 80% of the required land would be acquired by February 15, and the land acquisition was expected to be completed by the end of March.
Rahul Vasaikar, the superintendent engineer at MSRDC overseeing the project, affirmed that timelines would be adhered to, and 70% of the land would be acquired by the end of January. He mentioned that a total of Rs 75 billion would be allocated from the state government for the land acquisition of the outer ring road project, with Rs 30 billion required for the western phase and Rs 45 billion for the eastern phase. The construction was divided into two parts ? eastern and western, and it would be carried out in nine phases based on fund disbursement.
Vasaikar stated that a resolution had been passed to appoint a contractor for the project once 80% of the land was acquired. The request for proposal would be floated, and the letter of award would be given to the lowest bidder, expediting the work. The entire project was projected to be completed by May 2026.
Upon completion, the outer ring road would divert traffic passing through the city towards other districts, allowing heavy vehicles to travel through highways without entering the city. The road, designed for vehicles with a speed of 120 kmph, would pass through 83 villages.
The Pune collector Rajesh Deshmukh was instructed by the Maharashtra State Road Development Corporation (MSRDC) to complete 80% of the necessary land acquisition for the 136.8 km outer Pune ring road project by February 15. They expressed their hope to issue the letter of intent for the project before the commencement of the actual work, anticipated to begin post-monsoon.
The officer stated that due to the involvement of revenue machinery in poll-related activities, the deadline for land acquisition had been advanced. This same deadline was given to collectors of Mumbai, Raigad, for the Virar-Alibaug multi-purpose corridor, and the Jalna collector for the Jalna-Nanded Expressway.
The total cost for land acquisition of the three projects was estimated to be around Rs 180 billion. The Pune ring road required the acquisition of 1,700 hectares, the Virar-Alibaug corridor needed around 1,000 hectares, and the Jalna-Nanded project involved the acquisition of approximately 2,000 hectares.
As per the local MSRDC official, only 60% of the land had been acquired for the Pune ring road project at present. However, he expressed confidence that 80% of the required land would be acquired by February 15, and the land acquisition was expected to be completed by the end of March.
Rahul Vasaikar, the superintendent engineer at MSRDC overseeing the project, affirmed that timelines would be adhered to, and 70% of the land would be acquired by the end of January. He mentioned that a total of Rs 75 billion would be allocated from the state government for the land acquisition of the outer ring road project, with Rs 30 billion required for the western phase and Rs 45 billion for the eastern phase. The construction was divided into two parts ? eastern and western, and it would be carried out in nine phases based on fund disbursement.
Vasaikar stated that a resolution had been passed to appoint a contractor for the project once 80% of the land was acquired. The request for proposal would be floated, and the letter of award would be given to the lowest bidder, expediting the work. The entire project was projected to be completed by May 2026.
Upon completion, the outer ring road would divert traffic passing through the city towards other districts, allowing heavy vehicles to travel through highways without entering the city. The road, designed for vehicles with a speed of 120 kmph, would pass through 83 villages.
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..