Bengaluru-Mysuru expressway set to open in Feb 2022
ROADS & HIGHWAYS

Bengaluru-Mysuru expressway set to open in Feb 2022

The Karnataka government has announced over 55% of the work on the Mysuru-Bengaluru Economic Corridor (Bengaluru-Mysuru expressway) has been completed and is set to be open in February 2022.

The economic corridor project between Bengaluru and Mysuru is being executed under Bharatmala Pariyojana phase-1 and is estimated to cost Rs 7,400 crore.

The expressway is being constructed under two packages 鈥� the first one runs from Bengaluru to Nidaghatta in Maddur taluk, which costs around Rs 3,000 crore, and the second package connects Nidaghatta to Myusuru and costs Rs 3,500 crore.

Dilip Buildcon, a Bhopal-based contractor, was awarded the contract for construction of both the packages 鈥� 56 km from Bengaluru to Nidagatta and 61 km from Nidagatta to Mysore.

More than 67.5% of the work has been completed in the first package, and 50.5% of the work has been completed in the second package, the state government informed.

Once the project is completed, the government said the expressway would reduce travel time from three hours to 90 minutes between the two cities.

The scope of the work also includes the construction of nine major bridges, 44 minor bridges and four road-over bridges and road-under bridges.

Three elevated corridors are being built, including a 5 km section in the outskirts of Bengaluru, a 3 km section in Maddur, and a third one in Srirangapatna.

The 10-lane highway also includes two service roads on either side and wherever the works have been completed, vehicles are being allowed to travel.


Also read: Nitin Gadkari: Bengaluru Ring Road to push economic activities

Also read: Chennai-B'luru expressway downgraded to four lanes

The Karnataka government has announced over 55% of the work on the Mysuru-Bengaluru Economic Corridor (Bengaluru-Mysuru expressway) has been completed and is set to be open in February 2022. The economic corridor project between Bengaluru and Mysuru is being executed under Bharatmala Pariyojana phase-1 and is estimated to cost Rs 7,400 crore. The expressway is being constructed under two packages 鈥� the first one runs from Bengaluru to Nidaghatta in Maddur taluk, which costs around Rs 3,000 crore, and the second package connects Nidaghatta to Myusuru and costs Rs 3,500 crore. Dilip Buildcon, a Bhopal-based contractor, was awarded the contract for construction of both the packages 鈥� 56 km from Bengaluru to Nidagatta and 61 km from Nidagatta to Mysore. More than 67.5% of the work has been completed in the first package, and 50.5% of the work has been completed in the second package, the state government informed. Once the project is completed, the government said the expressway would reduce travel time from three hours to 90 minutes between the two cities. The scope of the work also includes the construction of nine major bridges, 44 minor bridges and four road-over bridges and road-under bridges. Three elevated corridors are being built, including a 5 km section in the outskirts of Bengaluru, a 3 km section in Maddur, and a third one in Srirangapatna. The 10-lane highway also includes two service roads on either side and wherever the works have been completed, vehicles are being allowed to travel. Image Source Also read: Nitin Gadkari: Bengaluru Ring Road to push economic activities Also read: Chennai-B'luru expressway downgraded to four lanes

Next Story
Infrastructure Urban

Reliance, Diehl Advance Pact for Precision-Guided Munitions

Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..

Next Story
Infrastructure Urban

Modis Navnirman to Migrate to Main Board, Merge Subsidiary

Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..

Next Story
Infrastructure Urban

Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025

The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement