CAG Audit exposes discrepancies in BBP-1 implementation
ROADS & HIGHWAYS

CAG Audit exposes discrepancies in BBP-1 implementation

The audit report by the Comptroller and Auditor General of India (CAG) regarding the 'Implementation of Phase-I of Bharatmala Pariyojana (BPP-1)' has brought to light significant revelations. The report highlights that the National Highway Authority of India (NHAI) Board sanctioned the Dwarka Expressway at a civil cost of Rs 72.87 billion, equating to Rs 2.50 billion per kilometre. This stands in stark contrast to the per kilometre civil cost of Rs 182 million that had been approved by the Cabinet Committee on Economic Affairs (CCEA).

In addition, the report uncovers that the Delhi-Vadodara Expressway, with an estimated civil cost of approximately Rs 328.39 billion, was endorsed by the NHAI Board even though it had not been included in the list of BPP-I projects approved by the CCEA.

The report sheds light on the fact that NHAI was responsible for the development of 70,950 km out of the designated 76,999 km of national highways for BPP-I. The NHAI was granted the authority to determine the construction approach for its projects. However, the audit discerned that NHAI was making decisions about construction methods without proper documented justifications.

According to the CAG report, "The audit also noticed that the evaluation and approval framework initially proposed to the CCEA failed to establish clear definitions for the terms 'project' and 'package'. As a result, the determination of whether construction packages within a single project should be regarded as individual projects or combined as one comprehensive project lacked clarity."

The CAG report further expounds that the appraisal and endorsement framework stipulated by the CCEA for BPP-I was not being adhered to by the entities responsible for project execution.

"The analysis encompassed a sample of 50 NHAI projects, and among these, eight projects had not undergone appraisal by the Project Appraisal and Technical Scrutiny Committee. This omission occurred due to the projects either being evaluated under the previous NHDP program or classified as balance works or one-time improvement initiatives," the report elucidated.

The audit report by the Comptroller and Auditor General of India (CAG) regarding the 'Implementation of Phase-I of Bharatmala Pariyojana (BPP-1)' has brought to light significant revelations. The report highlights that the National Highway Authority of India (NHAI) Board sanctioned the Dwarka Expressway at a civil cost of Rs 72.87 billion, equating to Rs 2.50 billion per kilometre. This stands in stark contrast to the per kilometre civil cost of Rs 182 million that had been approved by the Cabinet Committee on Economic Affairs (CCEA).In addition, the report uncovers that the Delhi-Vadodara Expressway, with an estimated civil cost of approximately Rs 328.39 billion, was endorsed by the NHAI Board even though it had not been included in the list of BPP-I projects approved by the CCEA.The report sheds light on the fact that NHAI was responsible for the development of 70,950 km out of the designated 76,999 km of national highways for BPP-I. The NHAI was granted the authority to determine the construction approach for its projects. However, the audit discerned that NHAI was making decisions about construction methods without proper documented justifications.According to the CAG report, The audit also noticed that the evaluation and approval framework initially proposed to the CCEA failed to establish clear definitions for the terms 'project' and 'package'. As a result, the determination of whether construction packages within a single project should be regarded as individual projects or combined as one comprehensive project lacked clarity.The CAG report further expounds that the appraisal and endorsement framework stipulated by the CCEA for BPP-I was not being adhered to by the entities responsible for project execution.The analysis encompassed a sample of 50 NHAI projects, and among these, eight projects had not undergone appraisal by the Project Appraisal and Technical Scrutiny Committee. This omission occurred due to the projects either being evaluated under the previous NHDP program or classified as balance works or one-time improvement initiatives, the report elucidated.

Next Story
Infrastructure Transport

Dassault To Build Falcon Jets In India With Reliance

Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..

Next Story
Infrastructure Urban

INDEA Lays Foundation for India’s First Auto Design School

The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..

Next Story
Infrastructure Transport

Karnataka Launches Global Innovation Hub at Airport City

The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement