Carnac Bridge to Reopen By 10 June After Delay
ROADS & HIGHWAYS

Carnac Bridge to Reopen By 10 June After Delay

Mumbai’s historic Carnac Bridge, a vital link connecting South Mumbai to the eastern suburbs, is now on course for completion by 10 June 2025, despite recent construction delays.

The Brihanmumbai Municipal Corporation (BMC) resumed work after a 15-day setback due to the delayed arrival of essential steel girders. The contractor responsible has been fined Rs 18 million for failing to meet the original delivery deadline of 30 April. Penalties were imposed at Rs 1 million per day from 1 to 2 May, increasing to Rs 2 million per day from 3 to 10 May. To speed up progress, BMC deployed engineers to the contractor’s plant in Daman to supervise fabrication and dispatch.

All 30 steel girders are now on-site, and installation has begun. These will support both the main bridge and its approach roads. Once fitted, work will progress to surface levelling and final road-laying. The BMC is prioritising pre-monsoon completion, citing the bridge’s role in easing traffic flow across South Mumbai.

The new four-lane structure replaces the original two-lane bridge, allowing for greater vehicle capacity and improved connectivity between P D’Mello Road and the Eastern Freeway. The original Carnac Bridge, built in 1866, was deemed unsafe and dismantled in 2022.

This reconstruction reflects BMC’s commitment to modernising the city’s infrastructure. Officials have warned that delays beyond 10 June could cause significant disruption due to the monsoon. The timely opening of the upgraded bridge is crucial for decongesting the area and reinforcing Mumbai’s east–west traffic corridors.

The BMC’s imposition of penalties and on-site monitoring highlight a focused approach to urban development and public safety.

Mumbai’s historic Carnac Bridge, a vital link connecting South Mumbai to the eastern suburbs, is now on course for completion by 10 June 2025, despite recent construction delays.The Brihanmumbai Municipal Corporation (BMC) resumed work after a 15-day setback due to the delayed arrival of essential steel girders. The contractor responsible has been fined Rs 18 million for failing to meet the original delivery deadline of 30 April. Penalties were imposed at Rs 1 million per day from 1 to 2 May, increasing to Rs 2 million per day from 3 to 10 May. To speed up progress, BMC deployed engineers to the contractor’s plant in Daman to supervise fabrication and dispatch.All 30 steel girders are now on-site, and installation has begun. These will support both the main bridge and its approach roads. Once fitted, work will progress to surface levelling and final road-laying. The BMC is prioritising pre-monsoon completion, citing the bridge’s role in easing traffic flow across South Mumbai.The new four-lane structure replaces the original two-lane bridge, allowing for greater vehicle capacity and improved connectivity between P D’Mello Road and the Eastern Freeway. The original Carnac Bridge, built in 1866, was deemed unsafe and dismantled in 2022.This reconstruction reflects BMC’s commitment to modernising the city’s infrastructure. Officials have warned that delays beyond 10 June could cause significant disruption due to the monsoon. The timely opening of the upgraded bridge is crucial for decongesting the area and reinforcing Mumbai’s east–west traffic corridors.The BMC’s imposition of penalties and on-site monitoring highlight a focused approach to urban development and public safety.

Next Story
Real Estate

Inspira Realty Plans 8-10 Redevelopment Projects in Mumbai

Inspira Realty, a leading Mumbai-based developer and a part of Inspira Global, has announced plans to undertake 8â€�10 new redevelopment projects across the city’s key western and southern corridors. With this expansion, the firm is poised to exceed its current Gross Development Value (GDV) of Rs 40 billion and drive forward its urban transformation agenda. The company has commenced the financial year with two development agreements signed in Borivali and Santacruz (W) and is actively negotiating further acquisitions. These projects, expected to span a construction area of 4 million sq ..

Next Story
Real Estate

U-Sphere Bags First Private Project with Ceenex in Thiruvananthapuram

U-Sphere, the high-tech construction arm of ULCCS, has secured its first major private sector project: the design and construction of a new training facility for Canada-based Ceenex Global Computer Private Limited in Sasthamangalam, Thiruvananthapuram. The agreement was signed by Remeshan Palery, Director, U-Sphere, and Muhammed Irfan, Director, Ceenex Global. As part of the project, U-Sphere will deliver the core structural framework and building envelope within a fast-tracked seven-month schedule. This facility will serve as a key hub for Ceenex’s initiatives across e-governance, heal..

Next Story
Equipment

Godrej Motor Solutions Targets Rs 10 billion Revenue by FY28

The Motor Solutions business of the Godrej Enterprises Group is aiming for Rs 10 billion  in revenue by FY28, with 20 per cent of this expected from exports. For FY26, the business is targeting Rs750 crore, driven by demand growth across electric vehicles (EVs), HVAC, pumps, and actuators in both domestic and international markets. Xercsis Marker, EVP & Head, Motor Solutions Business, Godrej Enterprises Group, said,  â€œWe are strengthening our manufacturing capabilities through significant R&D investments and advanced technology adoption. We continue to invest in t..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement