Marappalam Rail Subway Widening Project set to Begin Soon
22 Jan 2025
2 Min Read
CW Team
After a prolonged delay, the district administration is prepared to commence land acquisition for the widening of the Marappalam railway underpass in Madukkarai, situated on the Coimbatore-Palakkad main road. The project aims to transform the underpass into a four-lane stretch to improve traffic flow on this critical interstate route.
The Marappalam underpass, originally a wooden railway bridge, is located approximately two kilometers from the Kochi-Salem National Highway. It serves as the only convenient access road connecting Kerala and Coimbatore without toll plazas up to the state border.
The existing two-lane underpass, constructed during the British era, was later renovated and reduced to a single-lane subway. Currently, it accommodates only one heavy vehicle alongside a bike, causing traffic bottlenecks and long queues on both sides.
In response to public demand, the Coimbatore district administration has initiated the widening project. Explaining the plan, Collector Kranthi Kumar Pati informed *The New Indian Express* that the Marappalam Road Under Bridge (RUB) is set to be dismantled and reconstructed as a four-lane carriageway. The new structure will feature a railway box with a length of 82.70 meters and a width of 21.90 meters.
He further mentioned that the approved General Arrangement Drawing (GAD), incorporating all required modifications, had been received from the Chief Bridge Engineer of Southern Railways in Chennai on December 31, 2024. Subsequently, a request to divert traffic was submitted to the Palakkad Railway Division on January 6, 2025. Additionally, the Land Planning Schedule (LPS) for land acquisition is being prepared and will be sent to the government for approval.
Meanwhile, local residents have appealed to the district administration to renovate a nearby abandoned underpass, suggesting it could be utilized for light vehicles to further alleviate traffic congestion.
After a prolonged delay, the district administration is prepared to commence land acquisition for the widening of the Marappalam railway underpass in Madukkarai, situated on the Coimbatore-Palakkad main road. The project aims to transform the underpass into a four-lane stretch to improve traffic flow on this critical interstate route.
The Marappalam underpass, originally a wooden railway bridge, is located approximately two kilometers from the Kochi-Salem National Highway. It serves as the only convenient access road connecting Kerala and Coimbatore without toll plazas up to the state border.
The existing two-lane underpass, constructed during the British era, was later renovated and reduced to a single-lane subway. Currently, it accommodates only one heavy vehicle alongside a bike, causing traffic bottlenecks and long queues on both sides.
In response to public demand, the Coimbatore district administration has initiated the widening project. Explaining the plan, Collector Kranthi Kumar Pati informed *The New Indian Express* that the Marappalam Road Under Bridge (RUB) is set to be dismantled and reconstructed as a four-lane carriageway. The new structure will feature a railway box with a length of 82.70 meters and a width of 21.90 meters.
He further mentioned that the approved General Arrangement Drawing (GAD), incorporating all required modifications, had been received from the Chief Bridge Engineer of Southern Railways in Chennai on December 31, 2024. Subsequently, a request to divert traffic was submitted to the Palakkad Railway Division on January 6, 2025. Additionally, the Land Planning Schedule (LPS) for land acquisition is being prepared and will be sent to the government for approval.
Meanwhile, local residents have appealed to the district administration to renovate a nearby abandoned underpass, suggesting it could be utilized for light vehicles to further alleviate traffic congestion.
Next Story
Lack of Bidders Stalls VOC Port鈥檚 Rs 70.56 Bn Harbour Project Again
The VOC Port Authority鈥檚 Rs 70.56 billion outer harbour project has once again faced a setback, with the latest tender process cancelled due to the absence of qualified bidders. This marks the second failed attempt to secure participation for the mega infrastructure initiative.The tender has reportedly been withdrawn from the active list of bids, and the authority is now expected to re-evaluate and possibly restructure the project to enhance its appeal to potential developers.The port authority had initially floated the Request for Proposal (RFP) in December 2024, following the cancellation ..
Next Story
Sea Lord Containers Opens Cryogenic LPG Terminal in Mangalore
Sea Lord Containers (SCL), a wholly-owned subsidiary of Aegis Logistics, has commissioned a new cryogenic Liquified Petroleum Gas (LPG) terminal in Mangalore. The facility, which became operational on 12 June 2025, offers a static storage capacity of 82,000 metric tons (MT), significantly strengthening the region鈥檚 LPG logistics infrastructure.The terminal was developed by SCL on behalf of Aegis Vopak Terminals, an associate company of Aegis Logistics. The asset is expected to be transferred to Aegis Vopak Terminals Limited at a later date, with formal updates to be shared separately with st..
Next Story
Cochin Port and Oil India Partner for Offshore Exploration Support
The Cochin Port Authority (CoPA) has signed a Memorandum of Understanding (MoU) with Oil India (OIL) to establish a shore base facility supporting offshore oil exploration in the Kerala-Konkan Basin. The agreement was formalised at a ceremony held at CoPA, Willingdon Island, on 12 June 2025, in the presence of senior officials from both organisations.Under the partnership, Cochin Port will provide critical logistics infrastructure for OIL鈥檚 offshore drilling operations, expected to begin later in 2025. The planned shore base will include a dedicated warehouse, dry bulk handling plant, and an..