Mumbai Coastal Road Project to Be Completed by End of 2023
ROADS & HIGHWAYS

Mumbai Coastal Road Project to Be Completed by End of 2023

The enormous Mumbai Coastal Road project will now be completed by the end of 2023, having missed its original timetable. The BMC has told RTI activist Anil Galgali that a punishment of Rs 31 crore has been imposed on the project contractors, who have suffered a cost overrun of Rs 226 crores. Despite this, the contractors have already received 65 percent of their dues. Galgali had requested project details from the BMC. The BMC informed him that the project's work is separated into three sections.

Part 1 cost escalation

M/s Larsen & Toubro has been awarded the work from Priyadarshini Park to Baroda Palace under Part 1, and the original cost has increased by Rs 99.79 crores. The initial investment was estimated to be Rs 3,505 crores. The contractor had received roughly Rs 2,286 crore as of June 20, 2023. So far, a fine of Rs 8.57 crores has been issued for this job. The work was scheduled to be completed on October 12, 2022, however the deadline has been pushed back to September 10, 2023.

Part 2 cost escalation

M/s HCC HDC has been awarded the work from Baroda Palace to the southern end of the Bandra Worli Sea Link under Part 2, with an increase in the initial cost of Rs 62.25 crores. The initial investment was estimated to be Rs 2,126 crores. The contractor had received roughly Rs 1193 crore as of June 20, 2023. This work has resulted in a fine of Rs 15.37 crores. This section was supposed to be finished on October 15, 2022. The deadline, however, has been extended, and the project will now be completed by October 7, 2023.

Part 3 cost escalation

Part 3 work has been given to M/s Larsen & Toubro, and the initial cost has increased by Rs 63.83 crores. The initial cost was projected to be Rs 2,798 crores. The contractor had been paid around Rs 2,160 crore as of June 20, 2023. For this work, a punishment of Rs 7.25 crores was imposed. The planned completion date was October 12, 2022, but the deadline has been pushed out to November 26, 2023.

According to Galgali, the penalty imposed is relatively minor given the cost rise. Contractors work hard to secure such ambitious projects, but once they do, they fail to finish them on time. As a result, the cost rises, and the higher spending is covered by monies raised by taxpayers, he explained.

See also:
Mumbai to build Bowstring Bridge to connect coastal road
BMC completes Mumbai's final undersea tunnel for Coastal Road Project


The enormous Mumbai Coastal Road project will now be completed by the end of 2023, having missed its original timetable. The BMC has told RTI activist Anil Galgali that a punishment of Rs 31 crore has been imposed on the project contractors, who have suffered a cost overrun of Rs 226 crores. Despite this, the contractors have already received 65 percent of their dues. Galgali had requested project details from the BMC. The BMC informed him that the project's work is separated into three sections. Part 1 cost escalation M/s Larsen & Toubro has been awarded the work from Priyadarshini Park to Baroda Palace under Part 1, and the original cost has increased by Rs 99.79 crores. The initial investment was estimated to be Rs 3,505 crores. The contractor had received roughly Rs 2,286 crore as of June 20, 2023. So far, a fine of Rs 8.57 crores has been issued for this job. The work was scheduled to be completed on October 12, 2022, however the deadline has been pushed back to September 10, 2023. Part 2 cost escalation M/s HCC HDC has been awarded the work from Baroda Palace to the southern end of the Bandra Worli Sea Link under Part 2, with an increase in the initial cost of Rs 62.25 crores. The initial investment was estimated to be Rs 2,126 crores. The contractor had received roughly Rs 1193 crore as of June 20, 2023. This work has resulted in a fine of Rs 15.37 crores. This section was supposed to be finished on October 15, 2022. The deadline, however, has been extended, and the project will now be completed by October 7, 2023. Part 3 cost escalation Part 3 work has been given to M/s Larsen & Toubro, and the initial cost has increased by Rs 63.83 crores. The initial cost was projected to be Rs 2,798 crores. The contractor had been paid around Rs 2,160 crore as of June 20, 2023. For this work, a punishment of Rs 7.25 crores was imposed. The planned completion date was October 12, 2022, but the deadline has been pushed out to November 26, 2023. According to Galgali, the penalty imposed is relatively minor given the cost rise. Contractors work hard to secure such ambitious projects, but once they do, they fail to finish them on time. As a result, the cost rises, and the higher spending is covered by monies raised by taxpayers, he explained. See also: Mumbai to build Bowstring Bridge to connect coastal road BMC completes Mumbai's final undersea tunnel for Coastal Road Project

Next Story
Infrastructure Transport

Dassault To Build Falcon Jets In India With Reliance

Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..

Next Story
Infrastructure Urban

INDEA Lays Foundation for India’s First Auto Design School

The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..

Next Story
Infrastructure Transport

Karnataka Launches Global Innovation Hub at Airport City

The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement