NH-29 Package- III: NHIDCL receives three proposals
22 Dec 2022
2 Min Read
CW Team
The Guwahati High Court, Kohima Bench has been notified by the National Highways and
Infrastructure Development Corporation Limited (NHIDCL) that it has received three bids and a
project cost estimate for Package III of the NH 29 from M/S RAMKY-ECI (JV).
The proposals were made after the court ordered the NHIDCL authorities and RAMKY-ECI(JV) to
consider the Package-III after observing that its progress "has become a non-starter creating a lot of
annoyance to the commuters" on December 14.
Two contractors' contracts have already been terminated in relation to Package-III of the ongoing
four-lane National Highway-29 project, which roughly corresponds to the Piphema to Jotsoma length
(Design Km 152.490 to Km 166.700).
The NHIDCL authorities asked for some time to review the proposals, to further discuss them with
the contractor of Package I & II (M/S RAMKY-ECI JV), and to then decide at the highest level whether
the proposals were acceptable or not. The hearing on the ongoing sou motu public interest litigation
on the NH-29 four-lane project resumed on Monday.
In addition, the General Manager of NHIDCL, who was also present in court, stated that if the
solutions presented are rejected, more steps will be taken to propose a better solution for the
completion of Package-III.
In addition, the General Manager gave the Division Bench of Justices LS Jamir and Songkhupchung
Serto assurances that the two-lane in relation to Package-III, which is currently undergoing
maintenance, would be completely finished before March 2023 in accordance with the project
requirements.
The Bench instructed the NHIDCL and Contractor to further consider their options, reach a
conclusion by no later than January 15, 2023, and submit an affidavit in light of the submissions.
If the current offers made by the Contractor are not acceptable, the NHIDCL authorities will also
present an alternative plan for completion of Package-III in the aforementioned affidavit and submit
it by January 17, 2023, as instructed.
The Bench stated that it was pleased with the NHIDCL's affidavit submitted on December 14
detailing the actions followed by its officials following receipt of the sum of 111.19Million from the
previous contractor.
The M/S RAMKY-ECI JV was also instructed by the Bench to make sure that Packages I and II are
finished on or before January 15, 2023.
When it became known to the Court that the project that was supposed to be finished in September
2019 hadn't been finished, this PIL was brought up in 2019.
The Guwahati High Court, Kohima Bench has been notified by the National Highways and
Infrastructure Development Corporation Limited (NHIDCL) that it has received three bids and a
project cost estimate for Package III of the NH 29 from M/S RAMKY-ECI (JV).
The proposals were made after the court ordered the NHIDCL authorities and RAMKY-ECI(JV) to
consider the Package-III after observing that its progress has become a non-starter creating a lot of
annoyance to the commuters on December 14.
Two contractors' contracts have already been terminated in relation to Package-III of the ongoing
four-lane National Highway-29 project, which roughly corresponds to the Piphema to Jotsoma length
(Design Km 152.490 to Km 166.700).
The NHIDCL authorities asked for some time to review the proposals, to further discuss them with
the contractor of Package I & II (M/S RAMKY-ECI JV), and to then decide at the highest level whether
the proposals were acceptable or not. The hearing on the ongoing sou motu public interest litigation
on the NH-29 four-lane project resumed on Monday.
In addition, the General Manager of NHIDCL, who was also present in court, stated that if the
solutions presented are rejected, more steps will be taken to propose a better solution for the
completion of Package-III.
In addition, the General Manager gave the Division Bench of Justices LS Jamir and Songkhupchung
Serto assurances that the two-lane in relation to Package-III, which is currently undergoing
maintenance, would be completely finished before March 2023 in accordance with the project
requirements.
The Bench instructed the NHIDCL and Contractor to further consider their options, reach a
conclusion by no later than January 15, 2023, and submit an affidavit in light of the submissions.
If the current offers made by the Contractor are not acceptable, the NHIDCL authorities will also
present an alternative plan for completion of Package-III in the aforementioned affidavit and submit
it by January 17, 2023, as instructed.
The Bench stated that it was pleased with the NHIDCL's affidavit submitted on December 14
detailing the actions followed by its officials following receipt of the sum of 111.19Million from the
previous contractor.
The M/S RAMKY-ECI JV was also instructed by the Bench to make sure that Packages I and II are
finished on or before January 15, 2023.
When it became known to the Court that the project that was supposed to be finished in September
2019 hadn't been finished, this PIL was brought up in 2019.
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..