Pamban Bridge: India's sea lift bridge in Rameswaram faces 'curve' test
ROADS & HIGHWAYS

Pamban Bridge: India's sea lift bridge in Rameswaram faces 'curve' test

The RVNL official stated that a significant challenge has emerged in the construction of the Pamban railway bridge, India's inaugural vertical-lift bridge linking the mainland with Rameswaram island, owing to a sharp curve. This curve, in addition to the mechanical complexities and turbulent sea conditions, has posed an additional obstacle for the Railways. The RVNL, tasked with erecting this 2.08-km-long bridge, is encountering substantial difficulty in transporting a lift span measuring 72.5 metres in length, 16 meters in width, and weighing 550 tonnes, from the Rameshwaram end to a distance of 450 metres into the sea to affix it to the bridge.

We commenced the transportation of this lift span on March 10th, and thus far, we have managed to shift the 550-tonne lift span 80 metres towards the centre of the bridge. The primary challenge lies in the 2.65-degree curved alignment of the bridge. If it were straight, progress would have been swifter, explained a senior RVNL official, noting that the curved configuration was necessitated by various alignment adjustments.

The RVNL aims to conclude the movement of the lift span to its ultimate fixing position by the end of May, requiring an additional 370 metres of transportation.

Once we surpass the curved section, we can accelerate its movement. We've exercised great caution while maneuvering it in the sea due to its size and weight, necessitating precise execution at every stage, the official remarked.

With a deadline set for June 30 to operationalise the bridge, RVNL officials affirm their utmost efforts to meet the target.

Once the lift span is affixed, the remaining tasks are manageable, expressed another RVNL official.

Furthermore, he elaborated, This lift span can be automatically raised to a height of up to 17 meters to allow passage for ships. The ascending and descending process takes approximately 5 minutes each and will be scheduled to minimize disruptions to train services.

The RVNL commissioned the design of this lift span from the Spanish firm TYPSA, with manufacturing undertaken at Sattirakkudi Railway Station, located 20 kilometres from the coastline.

We transported it in various segments and assembled it here at the coast because transporting such a massive structure from the manufacturing site was impractical, clarified the RVNL official.

The RVNL official stated that a significant challenge has emerged in the construction of the Pamban railway bridge, India's inaugural vertical-lift bridge linking the mainland with Rameswaram island, owing to a sharp curve. This curve, in addition to the mechanical complexities and turbulent sea conditions, has posed an additional obstacle for the Railways. The RVNL, tasked with erecting this 2.08-km-long bridge, is encountering substantial difficulty in transporting a lift span measuring 72.5 metres in length, 16 meters in width, and weighing 550 tonnes, from the Rameshwaram end to a distance of 450 metres into the sea to affix it to the bridge. We commenced the transportation of this lift span on March 10th, and thus far, we have managed to shift the 550-tonne lift span 80 metres towards the centre of the bridge. The primary challenge lies in the 2.65-degree curved alignment of the bridge. If it were straight, progress would have been swifter, explained a senior RVNL official, noting that the curved configuration was necessitated by various alignment adjustments. The RVNL aims to conclude the movement of the lift span to its ultimate fixing position by the end of May, requiring an additional 370 metres of transportation. Once we surpass the curved section, we can accelerate its movement. We've exercised great caution while maneuvering it in the sea due to its size and weight, necessitating precise execution at every stage, the official remarked. With a deadline set for June 30 to operationalise the bridge, RVNL officials affirm their utmost efforts to meet the target. Once the lift span is affixed, the remaining tasks are manageable, expressed another RVNL official. Furthermore, he elaborated, This lift span can be automatically raised to a height of up to 17 meters to allow passage for ships. The ascending and descending process takes approximately 5 minutes each and will be scheduled to minimize disruptions to train services. The RVNL commissioned the design of this lift span from the Spanish firm TYPSA, with manufacturing undertaken at Sattirakkudi Railway Station, located 20 kilometres from the coastline. We transported it in various segments and assembled it here at the coast because transporting such a massive structure from the manufacturing site was impractical, clarified the RVNL official.

Next Story
Infrastructure Urban

Reliance, Diehl Advance Pact for Precision-Guided Munitions

Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..

Next Story
Infrastructure Urban

Modis Navnirman to Migrate to Main Board, Merge Subsidiary

Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..

Next Story
Infrastructure Urban

Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025

The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement