PMRDA Inner Ring Road: First Phase Land Acquisition to Finish in 3-4 Months
ROADS & HIGHWAYS

PMRDA Inner Ring Road: First Phase Land Acquisition to Finish in 3-4 Months

The Pune district administration is expected to complete the land acquisition for the first phase of the Pune Metropolitan Region Development Authority (PMRDA) inner ring road project in the next three to four months. The first phase, spanning 4.7 km from Solu to Vadgaon Shinde, is part of a broader plan to reduce traffic congestion by redirecting heavy vehicles from city roads.

The acquisition process had been delayed last year due to the state assembly elections, but it has now resumed, with joint measurements and valuation underway. The PMRDA has set aside Rs 1.13 billion for the land acquisition, with approximately 30 per cent already deposited for compensation in the first phase. Officials are optimistic that the land acquisition for this stretch will be completed within the specified timeframe.

The total cost for the entire 83.12 km inner ring road project is estimated at Rs 142 billion. The district collector's office has completed the joint survey for the first phase and will now proceed with the valuation process. The landowners from the affected villages have agreed to provide the required land for the project.

The inner ring road is designed to enhance traffic flow by providing direct connections to highways, thereby bypassing the city鈥檚 congested roads. To expedite the project, the state government relaxed certain planning regulations last year.

The first phase will require 28 hectares of land from the villages of Solu, Wadgaon Shinde, and Nirgudi. A total of 743.41 hectares will be needed for the full 83.12 km ring road, which will pass through 44 villages in Khed, Haveli, Mulshi, and Maval talukas. The project will also include 42 connecting roads, 17 bridges, and 10 tunnels, with a 5-meter section allocated for Metro tracks.

News source: Pune Mirror

The Pune district administration is expected to complete the land acquisition for the first phase of the Pune Metropolitan Region Development Authority (PMRDA) inner ring road project in the next three to four months. The first phase, spanning 4.7 km from Solu to Vadgaon Shinde, is part of a broader plan to reduce traffic congestion by redirecting heavy vehicles from city roads. The acquisition process had been delayed last year due to the state assembly elections, but it has now resumed, with joint measurements and valuation underway. The PMRDA has set aside Rs 1.13 billion for the land acquisition, with approximately 30 per cent already deposited for compensation in the first phase. Officials are optimistic that the land acquisition for this stretch will be completed within the specified timeframe. The total cost for the entire 83.12 km inner ring road project is estimated at Rs 142 billion. The district collector's office has completed the joint survey for the first phase and will now proceed with the valuation process. The landowners from the affected villages have agreed to provide the required land for the project. The inner ring road is designed to enhance traffic flow by providing direct connections to highways, thereby bypassing the city鈥檚 congested roads. To expedite the project, the state government relaxed certain planning regulations last year. The first phase will require 28 hectares of land from the villages of Solu, Wadgaon Shinde, and Nirgudi. A total of 743.41 hectares will be needed for the full 83.12 km ring road, which will pass through 44 villages in Khed, Haveli, Mulshi, and Maval talukas. The project will also include 42 connecting roads, 17 bridges, and 10 tunnels, with a 5-meter section allocated for Metro tracks. News source: Pune Mirror

Next Story
Infrastructure Transport

Lack of Bidders Stalls VOC Port鈥檚 Rs 70.56 Bn Harbour Project Again

The VOC Port Authority鈥檚 Rs 70.56 billion outer harbour project has once again faced a setback, with the latest tender process cancelled due to the absence of qualified bidders. This marks the second failed attempt to secure participation for the mega infrastructure initiative.The tender has reportedly been withdrawn from the active list of bids, and the authority is now expected to re-evaluate and possibly restructure the project to enhance its appeal to potential developers.The port authority had initially floated the Request for Proposal (RFP) in December 2024, following the cancellation ..

Next Story
Infrastructure Transport

Sea Lord Containers Opens Cryogenic LPG Terminal in Mangalore

Sea Lord Containers (SCL), a wholly-owned subsidiary of Aegis Logistics, has commissioned a new cryogenic Liquified Petroleum Gas (LPG) terminal in Mangalore. The facility, which became operational on 12 June 2025, offers a static storage capacity of 82,000 metric tons (MT), significantly strengthening the region鈥檚 LPG logistics infrastructure.The terminal was developed by SCL on behalf of Aegis Vopak Terminals, an associate company of Aegis Logistics. The asset is expected to be transferred to Aegis Vopak Terminals Limited at a later date, with formal updates to be shared separately with st..

Next Story
Infrastructure Urban

Cochin Port and Oil India Partner for Offshore Exploration Support

The Cochin Port Authority (CoPA) has signed a Memorandum of Understanding (MoU) with Oil India (OIL) to establish a shore base facility supporting offshore oil exploration in the Kerala-Konkan Basin. The agreement was formalised at a ceremony held at CoPA, Willingdon Island, on 12 June 2025, in the presence of senior officials from both organisations.Under the partnership, Cochin Port will provide critical logistics infrastructure for OIL鈥檚 offshore drilling operations, expected to begin later in 2025. The planned shore base will include a dedicated warehouse, dry bulk handling plant, and an..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement