Stalled FNG expressway project resumes
15 Feb 2023
2 Min Read
CW Team
The union minister VK Singh recently asked the National Highways Authority of India (NHAI) to take over the remaining work on the 43-kilometer long Faridabad-Noida-Ghaziabad (FNG) expressway project, which had been stalled for years.
The lack of coordination and land disputes that plagued the stretch caused the project to drag on for more than 30 years. Under the 23 kilometers of the Noida Authority portion, a 11-kilometer section has been completed. The six-lane expressway will connect Delhi, Faridabad, Noida, Greater Noida, Meerut, and Ghaziabad in a crucial way. In 2018, the NHAI was asked to take over the project, but it turned it down. According to officials, the Noida authority has decided to construct three crucial stretches of the expressway, including two elevated stretches, for the benefit of commuters now that work has resumed.
Officials say that an elevated road above the Hindon embankment road and a 659-meter-long elevated road above Chhijarsi will be built. The Authority will also construct an underpass on the Noida-Greater Noida Expressway so that the FNG expressway can pass through it. This will mark the end of work on the FNG expressway in Noida.
The dispute between the governments of Uttar Pradesh and Haryana over the financial burden of a 600-meter-long bridge over the Yamuna near Chauprauli village in Noida that connects to Faridabad on the other side was a major obstacle in the competition for the FNG expressway. The bridge's cost will now be shared by both governments.
The FNG expressway, when it is finished, will connect Sector 168 in Noida to NH2 in Faridabad and NH9 in Ghaziabad, near Chhajarsi. The distance between the two locations would be reduced to 25 minutes. At the moment, it takes longer than an hour.
The union minister VK Singh recently asked the National Highways Authority of India (NHAI) to take over the remaining work on the 43-kilometer long Faridabad-Noida-Ghaziabad (FNG) expressway project, which had been stalled for years.
The lack of coordination and land disputes that plagued the stretch caused the project to drag on for more than 30 years. Under the 23 kilometers of the Noida Authority portion, a 11-kilometer section has been completed. The six-lane expressway will connect Delhi, Faridabad, Noida, Greater Noida, Meerut, and Ghaziabad in a crucial way. In 2018, the NHAI was asked to take over the project, but it turned it down. According to officials, the Noida authority has decided to construct three crucial stretches of the expressway, including two elevated stretches, for the benefit of commuters now that work has resumed.
Officials say that an elevated road above the Hindon embankment road and a 659-meter-long elevated road above Chhijarsi will be built. The Authority will also construct an underpass on the Noida-Greater Noida Expressway so that the FNG expressway can pass through it. This will mark the end of work on the FNG expressway in Noida.
The dispute between the governments of Uttar Pradesh and Haryana over the financial burden of a 600-meter-long bridge over the Yamuna near Chauprauli village in Noida that connects to Faridabad on the other side was a major obstacle in the competition for the FNG expressway. The bridge's cost will now be shared by both governments.
The FNG expressway, when it is finished, will connect Sector 168 in Noida to NH2 in Faridabad and NH9 in Ghaziabad, near Chhajarsi. The distance between the two locations would be reduced to 25 minutes. At the moment, it takes longer than an hour.
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..