The Delhi-Dehradun Motorway will reduce commute time by half
23 May 2024
2 Min Read
CW Team
The Delhi-Dehradun expressway's fourth segment, which would improve connectivity, is expected to open by May 2025. Saharanpur will be used in this project to connect two roads. Instead of five hours, a two-hour journey time is what is expected. This motorway will save fuel, lessen traffic, enhance connectivity between the two cities, and save time. It is projected that the project will cost Rs. 130 billion.
On the motorway, light cars are permitted to go up to 100 kmph. After NH44, the longest highway spanning from north to south, this will be the second motorway, including a wildlife protection corridor.
Connectivity
Saharanpur, Baghpat, Muzaffarnagar, Shamli, and Delhi will all be connected by this motorway. Phases 1, 2, 3, and 4 of the 210-km Delhi-Dehradun road have six lanes each, whereas Phase 1 has twelve lanes. This motorway will link the three states of Uttar Pradesh, Delhi, and Uttrakhand.
Issues
One of the biggest challenges is the removal of trees. Because this motorway passes through Rajaji National Park, wildlife is seriously at risk. To halt the tree-cutting, some groups have filed lawsuits. The first segment of the Delhi-Dehradun motorway is anticipated to be operational by the end of June 2024. The project's first phase is 90?95% complete, although expansion joints, signs, and other infrastructure still need to be installed.
Timeline of the construction
The government grants approval for the NHAI project by February 2020. The land acquisition and tender allocation for the first two stages were completed in January 2021. The national government has set aside Rs 20 billion by November of that year to build six additional highways connecting Haridwar. By January 2022, tenders were open for the second phase of this expressway's construction. The environmentally sensitive Delhi-Dehradun motorway segment was completed by August.
The Delhi-Dehradun expressway's fourth segment, which would improve connectivity, is expected to open by May 2025. Saharanpur will be used in this project to connect two roads. Instead of five hours, a two-hour journey time is what is expected. This motorway will save fuel, lessen traffic, enhance connectivity between the two cities, and save time. It is projected that the project will cost Rs. 130 billion.
On the motorway, light cars are permitted to go up to 100 kmph. After NH44, the longest highway spanning from north to south, this will be the second motorway, including a wildlife protection corridor.
Connectivity
Saharanpur, Baghpat, Muzaffarnagar, Shamli, and Delhi will all be connected by this motorway. Phases 1, 2, 3, and 4 of the 210-km Delhi-Dehradun road have six lanes each, whereas Phase 1 has twelve lanes. This motorway will link the three states of Uttar Pradesh, Delhi, and Uttrakhand.
Issues
One of the biggest challenges is the removal of trees. Because this motorway passes through Rajaji National Park, wildlife is seriously at risk. To halt the tree-cutting, some groups have filed lawsuits. The first segment of the Delhi-Dehradun motorway is anticipated to be operational by the end of June 2024. The project's first phase is 90?95% complete, although expansion joints, signs, and other infrastructure still need to be installed.
Timeline of the construction
The government grants approval for the NHAI project by February 2020. The land acquisition and tender allocation for the first two stages were completed in January 2021. The national government has set aside Rs 20 billion by November of that year to build six additional highways connecting Haridwar. By January 2022, tenders were open for the second phase of this expressway's construction. The environmentally sensitive Delhi-Dehradun motorway segment was completed by August.
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..