Alstom emerges as the only bidder for Delhi Metro signal upgradation
26 May 2021
2 Min Read
CW Team
Alstom Transport India has emerged as the only bidder for the supply and commissioning of the train control and signalling system for Delhi Metro’s red line (line-1).
The system also contains virtual signal implementation for the red line, Line-1 of Delhi metro’s red line that extends to 34.4 km from Shaheed Sthal to Rithala with 29 stations.
The invitation of bids for the work was started in March 2021 by the Delhi Metro Rail Corporation (DMRC) with a total capital of Rs 90.27 crore and time for completion as 15 months.
The reveal of Alstom as the only bidder for the contract came when the technical bids were opened.
Currently, Delhi Metro's Red Line is decked with Urbalis 200 train control and signalling solution by Alstom.
The work includes design, manufacture, supply, installation, configuration/customisation, testing and commissioning of train control and signalling system for short looping train movement along with virtual signal implementation.
They also have trains conversion from six cars to eight-car trains along with head stopping at all platforms of the Line-1 and combining the train control and signalling system with a third-party ATS system.
The process of signalling upgradation was launched in 2019 by the Delhi Metro on its Red, Yellow and Blue Lines to identify glitches and make the required changes to aid the affected trains run at 33-37 km per hour.
This will render stable train services thereby preventing overcrowding.
The bid of Rs 86.21 crore by Siemens won the contract for upgradation of Blue Line in June 2020.
The contract for Yellow Line upgradation along with the contract for the bid raised in March by the only bidder Alstom is also still pending.
Also read:
Alstom Transport India has emerged as the only bidder for the supply and commissioning of the train control and signalling system for Delhi Metro’s red line (line-1).
The system also contains virtual signal implementation for the red line, Line-1 of Delhi metro’s red line that extends to 34.4 km from Shaheed Sthal to Rithala with 29 stations.
The invitation of bids for the work was started in March 2021 by the Delhi Metro Rail Corporation (DMRC) with a total capital of Rs 90.27 crore and time for completion as 15 months.
The reveal of Alstom as the only bidder for the contract came when the technical bids were opened.
Currently, Delhi Metro's Red Line is decked with Urbalis 200 train control and signalling solution by Alstom.
The work includes design, manufacture, supply, installation, configuration/customisation, testing and commissioning of train control and signalling system for short looping train movement along with virtual signal implementation.
They also have trains conversion from six cars to eight-car trains along with head stopping at all platforms of the Line-1 and combining the train control and signalling system with a third-party ATS system.
The process of signalling upgradation was launched in 2019 by the Delhi Metro on its Red, Yellow and Blue Lines to identify glitches and make the required changes to aid the affected trains run at 33-37 km per hour.
This will render stable train services thereby preventing overcrowding.
The bid of Rs 86.21 crore by Siemens won the contract for upgradation of Blue Line in June 2020.
The contract for Yellow Line upgradation along with the contract for the bid raised in March by the only bidder Alstom is also still pending.
Image Source
Also read: DMRCL opens tender for construction of four stations, twin tunnels
Next Story
Lack of Bidders Stalls VOC Port’s Rs 70.56 Bn Harbour Project Again
The VOC Port Authority’s Rs 70.56 billion outer harbour project has once again faced a setback, with the latest tender process cancelled due to the absence of qualified bidders. This marks the second failed attempt to secure participation for the mega infrastructure initiative.The tender has reportedly been withdrawn from the active list of bids, and the authority is now expected to re-evaluate and possibly restructure the project to enhance its appeal to potential developers.The port authority had initially floated the Request for Proposal (RFP) in December 2024, following the cancellation ..
Next Story
Sea Lord Containers Opens Cryogenic LPG Terminal in Mangalore
Sea Lord Containers (SCL), a wholly-owned subsidiary of Aegis Logistics, has commissioned a new cryogenic Liquified Petroleum Gas (LPG) terminal in Mangalore. The facility, which became operational on 12 June 2025, offers a static storage capacity of 82,000 metric tons (MT), significantly strengthening the region’s LPG logistics infrastructure.The terminal was developed by SCL on behalf of Aegis Vopak Terminals, an associate company of Aegis Logistics. The asset is expected to be transferred to Aegis Vopak Terminals Limited at a later date, with formal updates to be shared separately with st..
Next Story
Cochin Port and Oil India Partner for Offshore Exploration Support
The Cochin Port Authority (CoPA) has signed a Memorandum of Understanding (MoU) with Oil India (OIL) to establish a shore base facility supporting offshore oil exploration in the Kerala-Konkan Basin. The agreement was formalised at a ceremony held at CoPA, Willingdon Island, on 12 June 2025, in the presence of senior officials from both organisations.Under the partnership, Cochin Port will provide critical logistics infrastructure for OIL’s offshore drilling operations, expected to begin later in 2025. The planned shore base will include a dedicated warehouse, dry bulk handling plant, and an..