CE in charge of Bengaluru metro work not named in FIR
16 Jan 2023
3 Min Read
CW Team
Big fish appear to have been exempt from responsibility for the fatal subway disaster.
In defiance of the chief minister's directives, the KR's package 1 (Benniganahalli-Kempapura) chief engineer in charge of civil construction
In the FIR that the police have filed on the event, the Puram-airport metro line is not mentioned.
The in-charge chief engineer from the Bangalore Metro Rail Corporation Limited (BMRCL), according to a well-placed source in the state administration, was among those who were ordered to be punished for the terrible disaster by the chief minister.
Police have only detained joint engineer Jaffer Sadiq, executive engineer Mahesh Bandekari, and deputy chief engineer Venkatesh Shetty. The FIR does not list the chief engineer or any other higher-ranking officers.
According to police, they used a BMRCL list. Only individuals identified in the FIR have been suspended by the BMRCL.
The 38.44-km KR Puram airport line is being built in three sections: the 11.68-km Kempapura-Bagalur Cross section, the 11-km Benniganahalli-Kempapura section, and 15.01-km Doddajala-airport. One package is under the management of a chief engineer.
Package 1 contains the under-construction metro pier (number 218) that gave way and toppled, causing the fatal accident (Benniganahalli-Kempapura).
A three-person internal technical team has been assembled by the BMRCL to look into the accident's root cause. Chief engineers from the quality, safety, and work departments make up the team. In two days, the report is anticipated.
The civil engineering department at the Indian Institute of Science has also been asked to independently investigate the occurrence and provide a report.
The airport line's contractor, Nagarjuna Constructions Company (NCC) Limited, has also faced criticism. The large construction company with headquarters in Hyderabad has not yet commented on the incident or answered questions from the media.
The company's second metro contract in Bengaluru is for the airport line. The first involved designing and building viaducts for Reach 4's 3.6-km extension (Yelachenahalli-Anjanapura). 7,220 metres of precast parapets were cast and erected as part of the project.
The line is currently in use. The government source stated that despite the victims' families' requests for the corporation to be banned, such a move was improbable given the significance of the airport metro line. The tender cannot be cancelled either. The business might escape with just financial fines.
The Electronics City flyover, several TTMCs (Traffic Transit Management Centers) for the Bengaluru Metropolitan Transport Corporation (BMTC), and a two-level grade separator close to Nayandahalli were also constructed in Bengaluru by NCC Ltd. Additionally, it secured metro contracts in Nagpur, Pune, Mumbai, and Navi Mumbai.
Big fish appear to have been exempt from responsibility for the fatal subway disaster.
In defiance of the chief minister's directives, the KR's package 1 (Benniganahalli-Kempapura) chief engineer in charge of civil construction
In the FIR that the police have filed on the event, the Puram-airport metro line is not mentioned.
The in-charge chief engineer from the Bangalore Metro Rail Corporation Limited (BMRCL), according to a well-placed source in the state administration, was among those who were ordered to be punished for the terrible disaster by the chief minister.
Police have only detained joint engineer Jaffer Sadiq, executive engineer Mahesh Bandekari, and deputy chief engineer Venkatesh Shetty. The FIR does not list the chief engineer or any other higher-ranking officers.
According to police, they used a BMRCL list. Only individuals identified in the FIR have been suspended by the BMRCL.
The 38.44-km KR Puram airport line is being built in three sections: the 11.68-km Kempapura-Bagalur Cross section, the 11-km Benniganahalli-Kempapura section, and 15.01-km Doddajala-airport. One package is under the management of a chief engineer.
Package 1 contains the under-construction metro pier (number 218) that gave way and toppled, causing the fatal accident (Benniganahalli-Kempapura).
A three-person internal technical team has been assembled by the BMRCL to look into the accident's root cause. Chief engineers from the quality, safety, and work departments make up the team. In two days, the report is anticipated.
The civil engineering department at the Indian Institute of Science has also been asked to independently investigate the occurrence and provide a report.
The airport line's contractor, Nagarjuna Constructions Company (NCC) Limited, has also faced criticism. The large construction company with headquarters in Hyderabad has not yet commented on the incident or answered questions from the media.
The company's second metro contract in Bengaluru is for the airport line. The first involved designing and building viaducts for Reach 4's 3.6-km extension (Yelachenahalli-Anjanapura). 7,220 metres of precast parapets were cast and erected as part of the project.
The line is currently in use. The government source stated that despite the victims' families' requests for the corporation to be banned, such a move was improbable given the significance of the airport metro line. The tender cannot be cancelled either. The business might escape with just financial fines.
The Electronics City flyover, several TTMCs (Traffic Transit Management Centers) for the Bengaluru Metropolitan Transport Corporation (BMTC), and a two-level grade separator close to Nayandahalli were also constructed in Bengaluru by NCC Ltd. Additionally, it secured metro contracts in Nagpur, Pune, Mumbai, and Navi Mumbai.
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..