Delay in Yellow Line launch as metro coaches from China face setbacks
25 Jan 2024
2 Min Read
CW Team
The completion of the Yellow Line construction for Namma Metro is imminent; however, commuters will face a significant delay in the launch of the service, anticipated to be extended by six months.
The Bangalore Metro Rail Corporation (BMRCL) attributes the delay to the late arrival of metro coaches from China. The root cause is the requirement for engineers from the coach supply company to accompany two prototype trains, a process hindered until their recent receipt of Indian visas.
In 2019, the China Railway Rolling Stock Corporation (CRRC) secured a Rs 15.78 billion contract to deliver 216 metro coaches to BMRCL. Their failure to establish a manufacturing plant in India, as stipulated, led to an unfulfilled contract.
A senior BMRCL official explained, "Upon receiving the prototype train, a minimum of three months will be needed for BMRCL to conduct trial runs and obtain approvals for commercial operations. The prototype coaches have been dispatched from China, and engineers are scheduled to arrive in Bengaluru for testing by the end of this month."
The launch of Yellow Line operations is further hindered by the anticipated enforcement of the model code of conduct for general elections in April?May. Operations may commence in July after testing the coaches, ensuring a seamless interface between the trainset and signaling systems, and conducting oscillation trials through the Research Designs and Standards Organisation (RDSO).
Previously, BMRCL had considered encashing the Rs 3.72 billion bank guarantee from CRRC and has now engaged Kolkata-based Titagarh Wagons to supply the remaining coaches.
The 19-km elevated Yellow Line, connecting R.V. Road to Bommasandra, will alleviate traffic congestion and benefit commuters in Electronics City, the Bommasandra industrial area, HSR Layout, and Beratena Agrahara (Hosa Road).
The completion of the Yellow Line construction for Namma Metro is imminent; however, commuters will face a significant delay in the launch of the service, anticipated to be extended by six months.
The Bangalore Metro Rail Corporation (BMRCL) attributes the delay to the late arrival of metro coaches from China. The root cause is the requirement for engineers from the coach supply company to accompany two prototype trains, a process hindered until their recent receipt of Indian visas.
In 2019, the China Railway Rolling Stock Corporation (CRRC) secured a Rs 15.78 billion contract to deliver 216 metro coaches to BMRCL. Their failure to establish a manufacturing plant in India, as stipulated, led to an unfulfilled contract.
A senior BMRCL official explained, Upon receiving the prototype train, a minimum of three months will be needed for BMRCL to conduct trial runs and obtain approvals for commercial operations. The prototype coaches have been dispatched from China, and engineers are scheduled to arrive in Bengaluru for testing by the end of this month.
The launch of Yellow Line operations is further hindered by the anticipated enforcement of the model code of conduct for general elections in April?May. Operations may commence in July after testing the coaches, ensuring a seamless interface between the trainset and signaling systems, and conducting oscillation trials through the Research Designs and Standards Organisation (RDSO).
Previously, BMRCL had considered encashing the Rs 3.72 billion bank guarantee from CRRC and has now engaged Kolkata-based Titagarh Wagons to supply the remaining coaches.
The 19-km elevated Yellow Line, connecting R.V. Road to Bommasandra, will alleviate traffic congestion and benefit commuters in Electronics City, the Bommasandra industrial area, HSR Layout, and Beratena Agrahara (Hosa Road).
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..