Indian Railways plans to expand network to Arunachal's Tawang
25 Mar 2023
2 Min Read
CW Team
In light of India's security strategy towards the Line of Actual Control (LAC) along the India-China border, and in order to assist the Indian army in pushing its men and equipment into the border, the Indian Railways has planned to expand its railway network to Tawang and other parts of the Northeast frontier state of Arunachal Pradesh.
According to Anshul Gupta, General Manager of Northeast Frontier Railway, the final location survey report has already been sent to higher authority.
"The Defence Ministry also held its first meeting, and they agreed on two other projects: Bame-Aalo up to Mechuka and Pasighat-Parshuram-Wakro. These three projects have already been approved and their survey has also been completed. Our target is to complete the Pasighat new line work by March 2025,� Anshul Gupta said.
The General Manager of NF Railway stated that the NF Railway is attempting to complete the work of rail connectivity to Aizawl by December of this year.
The Sikkim construction will be finished by December 2024, and the train will run to Serima in Nagaland in September of this year. We plan to finish the railway project from Serima to Kohima by March 2024.
Anshul Gupta stated, "There is an umbrella project of border and hilly area connectivity projects worth Rs 1.20 lakh crore aiming to connect some important towns and border areas of Arunachal Pradesh, Manipur, Mizoram, and Sikkim, and we are working on it with the state government, different organisations, and the Indian army."
Also Read
BCCL signs 1st MDO contract for coking coal extraction
Indian cement companies set to raise prices from next month
In light of India's security strategy towards the Line of Actual Control (LAC) along the India-China border, and in order to assist the Indian army in pushing its men and equipment into the border, the Indian Railways has planned to expand its railway network to Tawang and other parts of the Northeast frontier state of Arunachal Pradesh.
According to Anshul Gupta, General Manager of Northeast Frontier Railway, the final location survey report has already been sent to higher authority.
The Defence Ministry also held its first meeting, and they agreed on two other projects: Bame-Aalo up to Mechuka and Pasighat-Parshuram-Wakro. These three projects have already been approved and their survey has also been completed. Our target is to complete the Pasighat new line work by March 2025,� Anshul Gupta said.
The General Manager of NF Railway stated that the NF Railway is attempting to complete the work of rail connectivity to Aizawl by December of this year.
The Sikkim construction will be finished by December 2024, and the train will run to Serima in Nagaland in September of this year. We plan to finish the railway project from Serima to Kohima by March 2024.
Anshul Gupta stated, There is an umbrella project of border and hilly area connectivity projects worth Rs 1.20 lakh crore aiming to connect some important towns and border areas of Arunachal Pradesh, Manipur, Mizoram, and Sikkim, and we are working on it with the state government, different organisations, and the Indian army.
Also Read
BCCL signs 1st MDO contract for coking coal extraction
Indian cement companies set to raise prices from next month
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..