Kamptee Corridor Leads as Nagpur Metro Phase 2 Construction Advances
16 Jan 2025
2 Min Read
CW Team
The contours of Nagpur Metro's Phase 2 are becoming clearer, with significant progress observed on the Kamptee corridor. The viaducts, part of the Orange Line extension, now extend beyond Khairi and are nearing Kamptee, with only the final stretch to Kanhan left. The 13 km corridor, which features 12 stations, is the most station-dense and the second-longest in the entire Phase 2 project. Metro officials confirmed that the Kamptee stretch is leading in construction efforts across the ongoing expansion.
A senior Metro official shared that construction has commenced on 14 of the 32 planned stations for Phase 2, with work progressing across all four project reaches. According to MahaMetro, tenders for most of Phase 2's components have been floated and awarded, with only a few pending finalisation. All tenders related to viaducts and stations have been finalised, while track tenders are awaiting approval, the official added.
Metro officials indicated that Rs 33.12 billion in civil tenders have been awarded so far, and tenders worth Rs 2.19 billion are in the pipeline and expected to be finalised soon. These tenders cover consultancy work, surveys, utility shifting, viaduct construction, station work, and infrastructure components such as subways, road overbridges (ROBs), and foot overbridges (FOBs).
A senior MahaMetro official mentioned that the viaduct on the Kamptee corridor has already crossed Khairi and is nearing Kamptee. He added that construction has started on all four reaches of Phase 2, with the Kamptee stretch showing the most visible progress. The official also noted that foundation-laying activities had begun on the Mihan-Butibori and Hingna corridors, marking the start of construction on those stretches.
He further stated that, in terms of land acquisition, Metro has secured 80% of the required land for Phase 2 and has received consent letters from the remaining landowners.
The Mihan-Butibori stretch, which recently began groundwork, is supported by a casting yard near Gumgaon village, inaugurated in December. This facility is expected to produce critical segments for the Metro's construction. Currently, three casting yards are operational for Phase 2, with preparatory work also underway on the Hingna and Pardi corridors. Officials expressed optimism that the entire Phase 2 network would be ready for public use by December 2027.
Phase 2 of Nagpur Metro spans 43.8 km and includes 32 stations, aiming to connect the city's peripheral areas with the core. The Rs 67.08 billion project is being funded through contributions from the European Investment Bank (EIB), the Asian Development Bank (ADB), and equity investments from the central and state governments.
The contours of Nagpur Metro's Phase 2 are becoming clearer, with significant progress observed on the Kamptee corridor. The viaducts, part of the Orange Line extension, now extend beyond Khairi and are nearing Kamptee, with only the final stretch to Kanhan left. The 13 km corridor, which features 12 stations, is the most station-dense and the second-longest in the entire Phase 2 project. Metro officials confirmed that the Kamptee stretch is leading in construction efforts across the ongoing expansion.
A senior Metro official shared that construction has commenced on 14 of the 32 planned stations for Phase 2, with work progressing across all four project reaches. According to MahaMetro, tenders for most of Phase 2's components have been floated and awarded, with only a few pending finalisation. All tenders related to viaducts and stations have been finalised, while track tenders are awaiting approval, the official added.
Metro officials indicated that Rs 33.12 billion in civil tenders have been awarded so far, and tenders worth Rs 2.19 billion are in the pipeline and expected to be finalised soon. These tenders cover consultancy work, surveys, utility shifting, viaduct construction, station work, and infrastructure components such as subways, road overbridges (ROBs), and foot overbridges (FOBs).
A senior MahaMetro official mentioned that the viaduct on the Kamptee corridor has already crossed Khairi and is nearing Kamptee. He added that construction has started on all four reaches of Phase 2, with the Kamptee stretch showing the most visible progress. The official also noted that foundation-laying activities had begun on the Mihan-Butibori and Hingna corridors, marking the start of construction on those stretches.
He further stated that, in terms of land acquisition, Metro has secured 80% of the required land for Phase 2 and has received consent letters from the remaining landowners.
The Mihan-Butibori stretch, which recently began groundwork, is supported by a casting yard near Gumgaon village, inaugurated in December. This facility is expected to produce critical segments for the Metro's construction. Currently, three casting yards are operational for Phase 2, with preparatory work also underway on the Hingna and Pardi corridors. Officials expressed optimism that the entire Phase 2 network would be ready for public use by December 2027.
Phase 2 of Nagpur Metro spans 43.8 km and includes 32 stations, aiming to connect the city's peripheral areas with the core. The Rs 67.08 billion project is being funded through contributions from the European Investment Bank (EIB), the Asian Development Bank (ADB), and equity investments from the central and state governments.
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..