Kolkata East-West metro project: Railways completes tunnelling work
17 May 2021
2 Min Read
CW Team
The tunnelling work in Kolkata鈥檚 East-West Metro Corridor by Tunnel Boring Machine (TBM) with the breakthrough of 鈥淯rvi鈥� at Bowbazar, Kolkata on May 15.
With this breakthrough, the Kolkata East-West Metro Project's TBM tunnelling is complete. Because of the century-old buildings, the stretch was difficult for tunnelling work.
This difficult 800m tunnel drive was completed successfully amid a pandemic situation using the Covid-19 protocol.
The Tunnel Boring Machine 鈥楿rvi,' which had previously completed the East Bound tunnel from Esplanade to Sealdah in October 2020, was relaunched from Sealdah in January 2021 after necessary refurbishment and inspection to complete the remaining 800 m tunnelling work in the West Bound tunnel from Sealdah to Bowbazar.
This tunnelling drive has been completed, and the tunnel boring machine broke through at the Retrieval Shaft in Bowbazar yesterday, on May 15, 2021.
This TBM (Urvi) passed beneath the Sealdah Flyover, which was closed to vehicular traffic for three days for safety reasons.
After this TBM drive is completed, the tunnel boring machine 鈥楿rvi', as well as the other stalled TBM 鈥楥handi,' will be retrieved from this retrieval shaft at Bowbazar.
Excavation of the shaft after ensuring the water-tightness of the shaft and the affected tunnel, as well as retrieval of the TBMs, are intricate activities that must be completed safely and thus take time.
After the excavation is completed, both TBMs will be extracted from the shaft in pieces. Following that, the RCC flooring and roofing for the shaft area will be finished, and the shaft top will be backfilled to prepare the ground for above-ground construction.
Also read:
Also read: Chennai Metro floats tender for tough tunnelling
The tunnelling work in Kolkata鈥檚 East-West Metro Corridor by Tunnel Boring Machine (TBM) with the breakthrough of 鈥淯rvi鈥� at Bowbazar, Kolkata on May 15.
With this breakthrough, the Kolkata East-West Metro Project's TBM tunnelling is complete. Because of the century-old buildings, the stretch was difficult for tunnelling work.
This difficult 800m tunnel drive was completed successfully amid a pandemic situation using the Covid-19 protocol.
The Tunnel Boring Machine 鈥楿rvi,' which had previously completed the East Bound tunnel from Esplanade to Sealdah in October 2020, was relaunched from Sealdah in January 2021 after necessary refurbishment and inspection to complete the remaining 800 m tunnelling work in the West Bound tunnel from Sealdah to Bowbazar.
This tunnelling drive has been completed, and the tunnel boring machine broke through at the Retrieval Shaft in Bowbazar yesterday, on May 15, 2021.
This TBM (Urvi) passed beneath the Sealdah Flyover, which was closed to vehicular traffic for three days for safety reasons.
After this TBM drive is completed, the tunnel boring machine 鈥楿rvi', as well as the other stalled TBM 鈥楥handi,' will be retrieved from this retrieval shaft at Bowbazar.
Excavation of the shaft after ensuring the water-tightness of the shaft and the affected tunnel, as well as retrieval of the TBMs, are intricate activities that must be completed safely and thus take time.
After the excavation is completed, both TBMs will be extracted from the shaft in pieces. Following that, the RCC flooring and roofing for the shaft area will be finished, and the shaft top will be backfilled to prepare the ground for above-ground construction.
Image SourceAlso read: Kolkata Metro鈥檚 East-West Corridor project kicks off
Also read: Chennai Metro floats tender for tough tunnelling
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..