L&T Bags Rs. 2447 Crore Contract for Kolkata Metro Purple Line
26 Jun 2023
2 Min Read
CW Team
Larsen & Toubro was declared the low bidder for the 5.05 km UG1 underground civil works contract between Mominpur and Esplanade on the Kolkata Metro Purple Line.
This northern and final part of the 15.215 km Line-3 (Joka to Esplanade / BBD Bagh) will be made up of twin tunnels that will connect four subterranean stations: Kidderpore, Victoria, Park Street, and Esplanade. L&T will be needed to install two new tunnel boring machines (TBMs) with one TBM on standby if and when awarded.
RVNL had requested bids for this contract in July 2022, with an estimated value of Rs. 2571.28 crore. In February, technical bids were opened, revealing three bidders.
L&T's offer of Rs. 2447 was 4.82% lower than RVNL's estimate.
Financial bid values:
Firm | Bid values ( in Rs. Crore) |
Larsen & Toubro | 2447 |
ITD cementation | 2473 |
Afcons infrastructure | 2486 |
About:
The Kolkata Metro Purple Line is a 15.08-kilometer (9.37 mi) long rapid transit line in Kolkata, West Bengal, India. The line is currently under construction, with the first section from Joka to Taratala having been inaugurated on 30 December 2022. The line will eventually connect Joka in the south to Esplanade in the north, via Majerhat.
The Purple Line is being built by the Kolkata Metro Rail Corporation (KMRCL). The line will be elevated for most of its length, with a short underground section between Majerhat and Esplanade. The line will have six stations: Joka, Thakurpukur, Sakherbazar, Behala Chowrasta, Behala Bazar, and Taratala.
Larsen & Toubro was declared the low bidder for the 5.05 km UG1 underground civil works contract between Mominpur and Esplanade on the Kolkata Metro Purple Line.
This northern and final part of the 15.215 km Line-3 (Joka to Esplanade / BBD Bagh) will be made up of twin tunnels that will connect four subterranean stations: Kidderpore, Victoria, Park Street, and Esplanade. L&T will be needed to install two new tunnel boring machines (TBMs) with one TBM on standby if and when awarded.
RVNL had requested bids for this contract in July 2022, with an estimated value of Rs. 2571.28 crore. In February, technical bids were opened, revealing three bidders.
L&T's offer of Rs. 2447 was 4.82% lower than RVNL's estimate.Financial bid values: Firm Bid values ( in Rs. Crore) Larsen & Toubro 2447ITD cementation 2473Afcons infrastructure 2486
About:
The Kolkata Metro Purple Line is a 15.08-kilometer (9.37 mi) long rapid transit line in Kolkata, West Bengal, India. The line is currently under construction, with the first section from Joka to Taratala having been inaugurated on 30 December 2022. The line will eventually connect Joka in the south to Esplanade in the north, via Majerhat.
The Purple Line is being built by the Kolkata Metro Rail Corporation (KMRCL). The line will be elevated for most of its length, with a short underground section between Majerhat and Esplanade. The line will have six stations: Joka, Thakurpukur, Sakherbazar, Behala Chowrasta, Behala Bazar, and Taratala.
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..