MRIDCL submits revised DPR for Pune-Nashik high-speed rail
08 Jun 2022
2 Min Read
CW Team
The Maharashtra Rail Infrastructure Development Corporation Limited (MRIDCL) has submitted a revised railway track alignment plan for the proposed Pune-Nashik high-speed train in the Khed tehsil.
The land acquisition in Khed tehsil for the proposed Pune-Nashik high-speed rail project was put on hold after the defence department asked the district administration to revise the railway track alignment in the original detailed project report (DPR), reasoning that it passed via an explosive destruction army facility.
Defence estates officer of the Pune circle, Vineet Nair, told the media that there was a problem regarding railway track alignment. So now, a recently revised alignment has been submitted by the MRIDC, and after going through it, it will suggest a further process.
According to an official, the railway line in the actual DPR was passing via the army鈥檚 explosive destruction facility.
As per the official, the defence department was first approached on March 7, 2022, for approval to build on land under it through the office of the defence estates officer (DEO). Upon receipt of the land requirement from MRIDCL, the first joint survey was conducted as early as March 11, 2022.
On March 16, 2022, a joint meeting with MRIDCL officials was held, in which it was conveyed to the MRIDCL officials that the demolition activities conducted on the army facility posed danger to the suggested railway alignment.
MRIDCL officials then understood the requirement for changing the suggested railway alignment. On April 19, 2022, they submitted a fresh proposal with the revised railway track alignment, after the second joint inspection was held on April 18, 2022. Now, the proposal is under process based on the revised alignment.
The Pune district collector, Rajesh Deshmukh, said the defence and the railways are operating on the revised alignment of 10 villages in Khed. The problem is not big and will be finalised soon. The project is likely to be finished on time.
The 235 km Pune-Nashik railway line will pass via the Ahmednagar, Pune, and Nashik districts.
Also read: MRIDC to construct 20 railway stations on Pune-Nashik rail line
The Maharashtra Rail Infrastructure Development Corporation Limited (MRIDCL) has submitted a revised railway track alignment plan for the proposed Pune-Nashik high-speed train in the Khed tehsil.
The land acquisition in Khed tehsil for the proposed Pune-Nashik high-speed rail project was put on hold after the defence department asked the district administration to revise the railway track alignment in the original detailed project report (DPR), reasoning that it passed via an explosive destruction army facility.
Defence estates officer of the Pune circle, Vineet Nair, told the media that there was a problem regarding railway track alignment. So now, a recently revised alignment has been submitted by the MRIDC, and after going through it, it will suggest a further process.
According to an official, the railway line in the actual DPR was passing via the army鈥檚 explosive destruction facility.
As per the official, the defence department was first approached on March 7, 2022, for approval to build on land under it through the office of the defence estates officer (DEO). Upon receipt of the land requirement from MRIDCL, the first joint survey was conducted as early as March 11, 2022.
On March 16, 2022, a joint meeting with MRIDCL officials was held, in which it was conveyed to the MRIDCL officials that the demolition activities conducted on the army facility posed danger to the suggested railway alignment.
MRIDCL officials then understood the requirement for changing the suggested railway alignment. On April 19, 2022, they submitted a fresh proposal with the revised railway track alignment, after the second joint inspection was held on April 18, 2022. Now, the proposal is under process based on the revised alignment.
The Pune district collector, Rajesh Deshmukh, said the defence and the railways are operating on the revised alignment of 10 villages in Khed. The problem is not big and will be finalised soon. The project is likely to be finished on time.
The 235 km Pune-Nashik railway line will pass via the Ahmednagar, Pune, and Nashik districts.
Image Source
Also read: MRIDC to construct 20 railway stations on Pune-Nashik rail line
Next Story
Concorde Acquires 3 Acre in Hennur for Premium High-Rise Project
In a strategic expansion move, Concorde has acquired a 3-acre land parcel in Hennur, North Bengaluru, for a premium high-rise residential development. The upcoming project will feature a saleable built-up area of approximately 4.25 lakh sq. ft., with an estimated Gross Development Value (GDV) of Rs 5 billion. Scheduled for launch in FY 2026鈥�27, the development will offer 2 and 3 BHK premium residences designed to appeal to discerning urban homebuyers seeking elevated, community-centric living in one of the city's fastest-growing corridors. 鈥淭his investment underlines our commitme..
Next Story
JP Infra Launches Monsoon Fest 2025 for 亚博体育官网首页buyers
JP Infra, one of Mumbai鈥檚 most trusted real estate developers, has announced the launch of 鈥楳onsoon Fest 2025鈥�, a limited-period campaign offering exclusive privileges across its residential projects in Mira Road, Thane, and other key locations. Running from 16th June to 31st July 2025, the Monsoon Fest presents a curated package of benefits for homebuyers. Every booking comes with an assured premium White Goods voucher from leading brands. Buyers can also choose one of three value-added offers: 50 per cent waiver on stamp duty Modular kitchen Fully furnished home&nbs..
Next Story
LANXESS Resin Removes Short-Chain PFAS From Water
Speciality chemicals company LANXESS has launched Lewatit MDS TP 108, a new ion exchange resin designed for the efficient removal of short-chain per- and polyfluoroalkyl substances (PFAS) from water. These PFAS compounds鈥攃haracterised by having three or fewer carbon atoms鈥攁re among the smallest and most challenging to eliminate through conventional water purification methods.Lewatit MDS TP 108 marks a significant advancement in the treatment of contaminated water, particularly where traditional technologies such as activated carbon adsorption fall short. The new resin offers a service life..