Mumbai suburban rail's longest tunnel completes on Panvel-Karjat line
11 Jun 2024
2 Min Read
CW Team
The Mumbai Railway Vikas Corporation (MRVC) announced a significant achievement with the breakthrough of the 2,625m Wavarle tunnel, marking it as the longest tunnel in the Mumbai suburban railway network. This tunnel forms part of the Panvel-Karjat railway project, which is under the Mumbai Urban Transport Project-3 (MUTP-3). Construction on this project commenced on February 22 of the previous year.
According to Sunil Udasi, the chief public relations officer of MRVC, the Panvel-Karjat railway project entails the construction of three tunnels totaling 3,164m. Breakthroughs for the Nadhamuni (219m) and Kirawali (320m) tunnels were also achieved. MRVC has completed 50% of the Rs 27.82-billion project and aims to open it by December 2025.
The Wavarle tunnel, constructed using the new Austrian tunnelling method, involves cyclic excavation followed by primary support and delayed secondary lining. The tunnel includes features such as a ballastless track, public refuge areas, a tunnel control system, lighting, firefighting, and ventilation systems meeting international standards. It measures 7.32m tall and 13.28m wide.
Excavation encountered significant challenges, including fractured rock masses with water seepage and minimal cover as low as 12m. Two water streams cross the tunnel alignment at the low cover zone. Despite these difficulties, an average excavation output of 175m per month was achieved through careful planning and daytime blasting, as night blasting is prohibited.
The new double-line corridor is expected to enhance connectivity by enabling local trains to operate between Mumbai and Karjat via Panvel, supplementing the existing line primarily used for goods trains and a few long-distance passenger services. It will also connect Navi Mumbai with Raigad district and serve as a catalyst for the development of Panvel, Karjat, and the proposed Navi Mumbai Airport Influence Notified Area.
The Mumbai Railway Vikas Corporation (MRVC) announced a significant achievement with the breakthrough of the 2,625m Wavarle tunnel, marking it as the longest tunnel in the Mumbai suburban railway network. This tunnel forms part of the Panvel-Karjat railway project, which is under the Mumbai Urban Transport Project-3 (MUTP-3). Construction on this project commenced on February 22 of the previous year.
According to Sunil Udasi, the chief public relations officer of MRVC, the Panvel-Karjat railway project entails the construction of three tunnels totaling 3,164m. Breakthroughs for the Nadhamuni (219m) and Kirawali (320m) tunnels were also achieved. MRVC has completed 50% of the Rs 27.82-billion project and aims to open it by December 2025.
The Wavarle tunnel, constructed using the new Austrian tunnelling method, involves cyclic excavation followed by primary support and delayed secondary lining. The tunnel includes features such as a ballastless track, public refuge areas, a tunnel control system, lighting, firefighting, and ventilation systems meeting international standards. It measures 7.32m tall and 13.28m wide.
Excavation encountered significant challenges, including fractured rock masses with water seepage and minimal cover as low as 12m. Two water streams cross the tunnel alignment at the low cover zone. Despite these difficulties, an average excavation output of 175m per month was achieved through careful planning and daytime blasting, as night blasting is prohibited.
The new double-line corridor is expected to enhance connectivity by enabling local trains to operate between Mumbai and Karjat via Panvel, supplementing the existing line primarily used for goods trains and a few long-distance passenger services. It will also connect Navi Mumbai with Raigad district and serve as a catalyst for the development of Panvel, Karjat, and the proposed Navi Mumbai Airport Influence Notified Area.
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..