Murkongselek-Pasighat Rail Project Hits 45% Completion
RAILWAYS & METRO RAIL

Murkongselek-Pasighat Rail Project Hits 45% Completion

The Murkongselek鈥揚asighat new railway line, a flagship project under Northeast Frontier Railway (NFR), has reached 45 per cent physical progress as of March 31, 2025, with work valued at approximately Rs 12.52 billion. Designed to enhance rail connectivity between Assam and Arunachal Pradesh, the 26.15-kilometre line is being executed in two distinct phases.

Phase I, covering the Murkongselek鈥揝ille segment (15.6 km), is close to completing its earthwork, with 1.375 million cubic meters finished out of the targeted 1.416 million. Construction is also well underway on 18 major and 35 minor bridges, while ballast supply and track laying are set to begin soon. The Murkongselek station building is nearing completion.

In Phase II (Sille鈥揚asighat, 10.55 km), 0.355 million cubic meters of earthwork has been completed out of the planned 0.685 million, with bridge building and casting ongoing. Land acquisition for a road overbridge at Pasighat Yard is being fast-tracked with local support.

The project has continued steadily despite challenges like prolonged monsoon conditions and local disruptions. During a recent site visit, the NFR General Manager (Construction) directed officials to maintain progress and ensure high construction standards.

Once operational, the new line is expected to spur economic development, promote tourism, and strengthen national integration by connecting remote border areas. The NFR reaffirmed its commitment to completing the project despite logistical and environmental challenges.


The Murkongselek鈥揚asighat new railway line, a flagship project under Northeast Frontier Railway (NFR), has reached 45 per cent physical progress as of March 31, 2025, with work valued at approximately Rs 12.52 billion. Designed to enhance rail connectivity between Assam and Arunachal Pradesh, the 26.15-kilometre line is being executed in two distinct phases.Phase I, covering the Murkongselek鈥揝ille segment (15.6 km), is close to completing its earthwork, with 1.375 million cubic meters finished out of the targeted 1.416 million. Construction is also well underway on 18 major and 35 minor bridges, while ballast supply and track laying are set to begin soon. The Murkongselek station building is nearing completion.In Phase II (Sille鈥揚asighat, 10.55 km), 0.355 million cubic meters of earthwork has been completed out of the planned 0.685 million, with bridge building and casting ongoing. Land acquisition for a road overbridge at Pasighat Yard is being fast-tracked with local support.The project has continued steadily despite challenges like prolonged monsoon conditions and local disruptions. During a recent site visit, the NFR General Manager (Construction) directed officials to maintain progress and ensure high construction standards.Once operational, the new line is expected to spur economic development, promote tourism, and strengthen national integration by connecting remote border areas. The NFR reaffirmed its commitment to completing the project despite logistical and environmental challenges.

Next Story
Building Material

Adani Cement and CREDAI to Elevate Sustainable Urban Construction

Adani Cement and CREDAI (Confederation of Real Estate Developers鈥� Associations of India) have entered an exclusive preferred partnership to advance sustainable and high-quality construction in India. The signing took place in the presence of Hon鈥檅le Chief Minister of Goa, Pramod Sawant, during the CREDAI Governing Council Meeting held in Panjim, attended by industry body office bearers and leading developers from across the country.This strategic alliance brings together Adani Cement and the country鈥檚 apex body of private real estate developers, aiming to benefit both organisations and t..

Next Story
Infrastructure Urban

DCVMI Inaugurates New Manufacturing Plant in Cikarang

Daimler Truck marked a significant milestone in its regional expansion with the opening of Daimler Commercial Vehicles Manufacturing Indonesia (DCVMI)鈥攁 cutting-edge greenfield manufacturing facility located in the Cikarang Industrial Area, Indonesia. This strategic investment underscores Daimler Truck鈥檚 long-term commitment to Southeast Asia, tailored to meet the region鈥檚 dynamic and evolving mobility needs. The new DCVMI plant spans 15 hectares and has an annual production capacity of 5,000 Mercedes-Benz trucks and buses. With a total investment of IDR 500 billion, this facility e..

Next Story
Equipment

Govt Defers OTR-2024 Implementation to September 2026

In a significant development for the construction, mining, and heavy equipment industries, the Ministry of Heavy Industries (MHI) has officially deferred the implementation of the Machinery and Electrical Equipment Safety (Omnibus Technical Regulation) Order, 2024 (OTR-2024) by one year. The new compliance date is now set for September 1, 2026.The OTR-2024, originally notified on August 28, 2024, was to come into effect from August 28, 2025. It aimed to regulate the safety of machinery and electrical equipment, including earthmoving, construction, mining equipment, cranes, and their assemblies..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement