Centre yet to fully fund Dharamshala smart city project
06 Aug 2021
2 Min Read
CW Team
The central government has failed to fully fund the Dharamshala smart city project, which is likely to hamper the development works of the project.
As per data from data, the central government had provided Rs 245 crore to the smart city project while the government has contributed only Rs 47 crore.
According to the agreement of the project, the central and the state government must provide equal funds for the projects. Sources told the media that the Ministry of Housing and Urban Development asked the state government to contribute its share of funds to the project prior to the release of more money by the centre, which is around Rs 200 crore now.
The sources also said that the project received Rs 292 crore, in which the central government contributed Rs 245 crore and the State government contributed Rs 47 crore. Around Rs 51.82 crore was left with the project authorities, and around Rs 241 crore was spent under the project till July 31. The sources said that the development under the project might come to a halt until the State or Central government provides more funds.
The state government has requested the central government for 90% of the funds while Himachal Pradesh should be allowed to contribute just 10% to the project being a special category state.
The central government turned down the request stating that the other states which have been sanctioned smart city projects also might begin to make similar requests if Himachal is given the benefit of a special category state.
Some of the works that have already been implemented in the Dharamshala under the Smart City project include website, underground dustbins, smart classrooms, root zone treatment, DC complex parking, LED lights in streets, GIS Web Portal, e-Nagarpalika, inclusive streets, solar power plant, all ability park and Bhagsunag project area development.
Also read: Govt allots Rs 181 cr to Dharamshala, Shimla under smart city goal
The central government has failed to fully fund the Dharamshala smart city project, which is likely to hamper the development works of the project.
As per data from data, the central government had provided Rs 245 crore to the smart city project while the government has contributed only Rs 47 crore.
According to the agreement of the project, the central and the state government must provide equal funds for the projects. Sources told the media that the Ministry of Housing and Urban Development asked the state government to contribute its share of funds to the project prior to the release of more money by the centre, which is around Rs 200 crore now.
The sources also said that the project received Rs 292 crore, in which the central government contributed Rs 245 crore and the State government contributed Rs 47 crore. Around Rs 51.82 crore was left with the project authorities, and around Rs 241 crore was spent under the project till July 31. The sources said that the development under the project might come to a halt until the State or Central government provides more funds.
The state government has requested the central government for 90% of the funds while Himachal Pradesh should be allowed to contribute just 10% to the project being a special category state.
The central government turned down the request stating that the other states which have been sanctioned smart city projects also might begin to make similar requests if Himachal is given the benefit of a special category state.
Some of the works that have already been implemented in the Dharamshala under the Smart City project include website, underground dustbins, smart classrooms, root zone treatment, DC complex parking, LED lights in streets, GIS Web Portal, e-Nagarpalika, inclusive streets, solar power plant, all ability park and Bhagsunag project area development.
Image Source
Also read: Govt allots Rs 181 cr to Dharamshala, Shimla under smart city goal
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..