Ludhiana Smart City Mission Projects May Miss Additional Deadlines
13 Jan 2025
3 Min Read
CW Team
As the Smart City mission nears its conclusion, civic officials have expressed their desire to complete on-going projects by the end of March this year. However, given the slow pace of the projects, this goal may remain out of reach.
Despite the significant time already spent, several projects remain unfinished, including the 24x7 surface water supply initiative for selected areas, bioremediation of legacy waste (first phase), and the establishment of construction and demolition waste plants. Municipal Corporation (MC) officials stated that they would transfer funds from Ludhiana Smart City to the MC to avoid any complications in completing the projects at a later stage.
One of the first projects announced was the laying of water supply lines and arranging underground water tanks for the 24x7 water supply in selected areas under the Smart City Mission. However, nearly five years later, the work is still incomplete, and the deadline has been extended until the end of March. Additionally, the installation of smart UID number plates outside houses has faced delays. Sources revealed that since contractors withdrew from the project, authorities would need to float tenders again. The first phase of bioremediation of legacy waste is also pending, and officials expect it to be completed within one to two months.
Other on-going projects include the construction of basketball courts at Guru Nanak Stadium, the establishment of a construction and demolition waste plant, an all-weather swimming pool, and the construction of a bridge over Buddha Dariya near Chand Cinema.
A significant challenge for the MC will be completing works that were hurriedly inaugurated before the MC elections. These include the renovation of Rose Garden and the construction of bridges over Buddha Dariya and Sidhwan Canal. According to officials, these projects were recently handed over to contractors, and it will take them at least six months to complete, particularly with the bridges.
A senior MC official stated that they had instructed the contractors to complete the pending work within the given timeframe. However, delays occurred at some sites due to shortages of construction materials and the unavailability of skilled labour. He mentioned that funds had already been earmarked for these projects and once work commenced, no major issues were expected to arise.
MC Commissioner Aaditya Dachalwal assured that the projects would be completed on time, as they had urged contractors to meet the deadlines. He confirmed that some projects would be completed in January, while others would be finished by February. He also mentioned that they were consistently monitoring the remaining projects.
The MC had received Rs 9.59 billion under this mission, of which Rs 9.42 billion had already been utilised.
As the Smart City mission nears its conclusion, civic officials have expressed their desire to complete on-going projects by the end of March this year. However, given the slow pace of the projects, this goal may remain out of reach.
Despite the significant time already spent, several projects remain unfinished, including the 24x7 surface water supply initiative for selected areas, bioremediation of legacy waste (first phase), and the establishment of construction and demolition waste plants. Municipal Corporation (MC) officials stated that they would transfer funds from Ludhiana Smart City to the MC to avoid any complications in completing the projects at a later stage.
One of the first projects announced was the laying of water supply lines and arranging underground water tanks for the 24x7 water supply in selected areas under the Smart City Mission. However, nearly five years later, the work is still incomplete, and the deadline has been extended until the end of March. Additionally, the installation of smart UID number plates outside houses has faced delays. Sources revealed that since contractors withdrew from the project, authorities would need to float tenders again. The first phase of bioremediation of legacy waste is also pending, and officials expect it to be completed within one to two months.
Other on-going projects include the construction of basketball courts at Guru Nanak Stadium, the establishment of a construction and demolition waste plant, an all-weather swimming pool, and the construction of a bridge over Buddha Dariya near Chand Cinema.
A significant challenge for the MC will be completing works that were hurriedly inaugurated before the MC elections. These include the renovation of Rose Garden and the construction of bridges over Buddha Dariya and Sidhwan Canal. According to officials, these projects were recently handed over to contractors, and it will take them at least six months to complete, particularly with the bridges.
A senior MC official stated that they had instructed the contractors to complete the pending work within the given timeframe. However, delays occurred at some sites due to shortages of construction materials and the unavailability of skilled labour. He mentioned that funds had already been earmarked for these projects and once work commenced, no major issues were expected to arise.
MC Commissioner Aaditya Dachalwal assured that the projects would be completed on time, as they had urged contractors to meet the deadlines. He confirmed that some projects would be completed in January, while others would be finished by February. He also mentioned that they were consistently monitoring the remaining projects.
The MC had received Rs 9.59 billion under this mission, of which Rs 9.42 billion had already been utilised.
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..