How India is losing Rs 3 trillion in infrastructure projects!
02 Jan 2019
2 Min Read
CW Team
Over the past few decades, India has witnessed the launch of several big-ticket infrastructure projects, pumping billions into the country’s aviation, industrial development, smart cities, railways, roads and energy sectors.
However, the scale of the projects have also led to delays in some of them. The most recent available Flash Report (September 2018), published by the Ministry of Statistics and Planning, is testament to this.
According to the report, out of 1,420 central-sector infrastructure projects worth Rs 1.50 billion and above, 385 are on schedule, 366 projects are delayed, 358 projects reported cost overruns, and 136 projects reported both time and cost overruns with respect to their original schedules. That said, around 32 projects have reported additional delays vis-à-vis their date of completion. Of these 32 projects, 14 are mega projects costing Rs 10 billion and above.
The total original cost of implementation of the 1,420 projects when sanctioned was Rs 18.05 trillion but this was subsequently revised to Rs 21.63 trillion, implying a cost overrun of Rs 3.38 trillion (20 per cent of the original cost). The expenditure incurred on these projects till September 2018 is Rs 7.83 trillion, which is 36.21 per cent of the anticipated cost of the projects.
However, the number of delayed projects decreases to 300 if delay is calculated on the basis of latest schedule of completion. Further, for 651 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 366 delayed projects, 100 (27.32 per cent) projects have an overall delay in the range of one to twelve months, 69 (18.85 per cent) projects have a delay in the range of 13 to 24 months, 91 (24.86 per cent) projects have a delay in the range of 25 to 60 months and 106 (28.96 per cent) projects have a delay of 61 months and above.
The average time overrun in these 366 delayed projects is 45.95 months.
SHRIYAL SETHUMADHAVAN and RAHUL KAMAT
Over the past few decades, India has witnessed the launch of several big-ticket infrastructure projects, pumping billions into the country’s aviation, industrial development, smart cities, railways, roads and energy sectors.
However, the scale of the projects have also led to delays in some of them. The most recent available Flash Report (September 2018), published by the Ministry of Statistics and Planning, is testament to this.
According to the report, out of 1,420 central-sector infrastructure projects worth Rs 1.50 billion and above, 385 are on schedule, 366 projects are delayed, 358 projects reported cost overruns, and 136 projects reported both time and cost overruns with respect to their original schedules. That said, around 32 projects have reported additional delays vis-à-vis their date of completion. Of these 32 projects, 14 are mega projects costing Rs 10 billion and above.
The total original cost of implementation of the 1,420 projects when sanctioned was Rs 18.05 trillion but this was subsequently revised to Rs 21.63 trillion, implying a cost overrun of Rs 3.38 trillion (20 per cent of the original cost). The expenditure incurred on these projects till September 2018 is Rs 7.83 trillion, which is 36.21 per cent of the anticipated cost of the projects.
However, the number of delayed projects decreases to 300 if delay is calculated on the basis of latest schedule of completion. Further, for 651 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 366 delayed projects, 100 (27.32 per cent) projects have an overall delay in the range of one to twelve months, 69 (18.85 per cent) projects have a delay in the range of 13 to 24 months, 91 (24.86 per cent) projects have a delay in the range of 25 to 60 months and 106 (28.96 per cent) projects have a delay of 61 months and above.
The average time overrun in these 366 delayed projects is 45.95 months.
SHRIYAL SETHUMADHAVAN and RAHUL KAMAT
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group’s Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence’s long-term commitment to the Indian market and its support for the Indian Government’s Make in India initiative. The partnership’s current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the “Vulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company’s growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association’s industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States� share of global activity below 15 per cent. Meanwhile, in..