Only 46% projects under Smart Cities Mission completed in six years
06 Aug 2021
2 Min Read
CW Team
Six years post the launch of the Smart Cities Mission (SCM), under which 100 cities from across the country were shortlisted to be developed as smart cities by the centre, only 46% out of around 6,000 projects tendered, have been completed.
The 100 smart cities were supposed to be developed within the five years of the scheme's inception, which is between 2015 and 2020. The completed projects are not yet near the halfway mark one year after the deadline ended.
Out of the 6,017 projects tendered, only 2,781 have been completed until 9 July, 2021, as per the latest data provided by the Ministry of Housing and Urban Development. In other words, only 46% of projects have been completed, ever since the Centre launched the SCM on 25 June, 2015, out of the total tendered projects.
One hundred selected cities under the Smart City Mission were provided with assured electricity supply, adequate water supply, sanitation, including efficient urban mobility and public transport, solid waste management, and affordable housing, especially for the poor and robust IT connectivity and digitalisation.
The selection of 100 "Smart Cities" was completed from January 2016 to June 2018 through four selection rounds. According to the guidelines of Smart Cities Mission, the Centre must provide financial support to the Mission to the extent of Rs 48,000 crore over five years, which is Rs 100 crore on an average per city per year and an equal amount should be provided by the states or urban local bodies.
The government of India has released Rs 23,925.83 crore as the central share to the states, out of which these Smart Cities have utilised Rs 20,410.14 crore, which is around 85%.
Also read: Smart Cities Mission: Projects in Visakhapatnam nears completion
Also read: Smart City Mission: Nine projects in Jaipur completed at Rs 142 cr
Also read: Thiruvananthapuram Smart City projects near completion
Six years post the launch of the Smart Cities Mission (SCM), under which 100 cities from across the country were shortlisted to be developed as smart cities by the centre, only 46% out of around 6,000 projects tendered, have been completed.
The 100 smart cities were supposed to be developed within the five years of the scheme's inception, which is between 2015 and 2020. The completed projects are not yet near the halfway mark one year after the deadline ended.
Out of the 6,017 projects tendered, only 2,781 have been completed until 9 July, 2021, as per the latest data provided by the Ministry of Housing and Urban Development. In other words, only 46% of projects have been completed, ever since the Centre launched the SCM on 25 June, 2015, out of the total tendered projects.
One hundred selected cities under the Smart City Mission were provided with assured electricity supply, adequate water supply, sanitation, including efficient urban mobility and public transport, solid waste management, and affordable housing, especially for the poor and robust IT connectivity and digitalisation.
The selection of 100 Smart Cities was completed from January 2016 to June 2018 through four selection rounds. According to the guidelines of Smart Cities Mission, the Centre must provide financial support to the Mission to the extent of Rs 48,000 crore over five years, which is Rs 100 crore on an average per city per year and an equal amount should be provided by the states or urban local bodies.
The government of India has released Rs 23,925.83 crore as the central share to the states, out of which these Smart Cities have utilised Rs 20,410.14 crore, which is around 85%.
Image Source
Also read: Smart Cities Mission: Projects in Visakhapatnam nears completion
Also read: Smart City Mission: Nine projects in Jaipur completed at Rs 142 cr
Also read: Thiruvananthapuram Smart City projects near completion
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..