Ken-Betwa interlinking dam to wait longer
07 Dec 2020
3 Min Read
CW Staff
The clearance for the Lower Orr Dam, which is a part of the Ken-Betwa river interlinking project, has been delayed by an expert panel that was set up in the Indian Ministry of Environment. New data is being sought by the ministry to decide whether there will be a new public hearing or not.
The assessed cost of the project is about Rs 30.65 billion and requires around 3,750 hectares of land. The dam was to be built across the Orr river near Didauni, a village in Madhya Pradesh.
The project would have provided an irrigation facility to 90,000 hectares of area, but is expected to submerge about 2,723 hectares of land, including seven fully affected villages and five villages partially.
Previously, the project sought clearance from the Expert Appraisal Committee (EAC) for hydroelectric ventures and for the river valley. The project had also received environmental clearance from the EAC in 2016. But since the project encompassed 968.24 hectares of forest land, the Ministry of Environment was asked to get the necessary authorisation from the National Water Development Agency and the Madhya Pradesh government.
The Forest Advisory Committee (FAC) of the MoEFC gave the clearance in February 2019. But the rules governing green clearance of the project dictated that if the proponents of the project were not submitted within the prescribed time of 18 months, the project would be referred to the EAC for reconsideration.
The rules also stated that EAC might collect fresh data and use it to prepare the Environmental Impact Assessment (EIA) if the project is more than three years old. Since the forest clearance was received almost after 31 months, the EAC ruled that they need to look at the new primary data. Considering all the facts and the regulatory provisions, EAC decided to defer the project.
Fresh baseline data was to be collected for all the environmental attributes. The ecological effects will then be contemplated using those data as a benchmark, the EAC recommended.
Since the inception of the Ken-Betwa it has been somewhat contentious. The viability of this project has been questioned by wildlife conservationists, experts, activists, and even by the Supreme Court.
Last year, the Supreme Court had questioned the monetary feasibility of this project and also scrutinised the basis on which the wildlife clearance was provided.
As the undertaking of this project would prompt the submergence of the chief forest area, which is home to many endangered species like the vulture and the tiger, it had also faced stiff opposition from the activists and the conservationists.
Ajay Dubey, Madhya Pradesh based wildlife activist, criticised the project stating that there was no need to build the massive project on top of dense forest areas as it would endanger the wildlife. He added that the government could opt for smaller water irrigation projects rather than building huge dams.
Meanwhile, the EAC has sought details about national parks, wildlife sanctuaries, and other eco-sensitive areas which could be used to protect the endangered species. As stated in the minutes of the meeting, the EAC is working out the kinks of the conservation plan for the Schedule-I species. The plan would then be submitted for approval.
The project has been an ambitious plan for the government for more than a decade and a half.
Source:
Also read: Implementation of river interlinking will raise the ultimate irrigation potential
The clearance for the Lower Orr Dam, which is a part of the Ken-Betwa river interlinking project, has been delayed by an expert panel that was set up in the Indian Ministry of Environment. New data is being sought by the ministry to decide whether there will be a new public hearing or not.The assessed cost of the project is about Rs 30.65 billion and requires around 3,750 hectares of land. The dam was to be built across the Orr river near Didauni, a village in Madhya Pradesh.
The project would have provided an irrigation facility to 90,000 hectares of area, but is expected to submerge about 2,723 hectares of land, including seven fully affected villages and five villages partially.
Previously, the project sought clearance from the Expert Appraisal Committee (EAC) for hydroelectric ventures and for the river valley. The project had also received environmental clearance from the EAC in 2016. But since the project encompassed 968.24 hectares of forest land, the Ministry of Environment was asked to get the necessary authorisation from the National Water Development Agency and the Madhya Pradesh government.
The Forest Advisory Committee (FAC) of the MoEFC gave the clearance in February 2019. But the rules governing green clearance of the project dictated that if the proponents of the project were not submitted within the prescribed time of 18 months, the project would be referred to the EAC for reconsideration.
The rules also stated that EAC might collect fresh data and use it to prepare the Environmental Impact Assessment (EIA) if the project is more than three years old. Since the forest clearance was received almost after 31 months, the EAC ruled that they need to look at the new primary data. Considering all the facts and the regulatory provisions, EAC decided to defer the project.
Fresh baseline data was to be collected for all the environmental attributes. The ecological effects will then be contemplated using those data as a benchmark, the EAC recommended.
Since the inception of the Ken-Betwa river interlinking project, it has been somewhat contentious. The viability of this project has been questioned by wildlife conservationists, experts, activists, and even by the Supreme Court.
Last year, the Supreme Court had questioned the monetary feasibility of this project and also scrutinised the basis on which the wildlife clearance was provided.
As the undertaking of this project would prompt the submergence of the chief forest area, which is home to many endangered species like the vulture and the tiger, it had also faced stiff opposition from the activists and the conservationists.
Ajay Dubey, Madhya Pradesh based wildlife activist, criticised the project stating that there was no need to build the massive project on top of dense forest areas as it would endanger the wildlife. He added that the government could opt for smaller water irrigation projects rather than building huge dams.
Meanwhile, the EAC has sought details about national parks, wildlife sanctuaries, and other eco-sensitive areas which could be used to protect the endangered species. As stated in the minutes of the meeting, the EAC is working out the kinks of the conservation plan for the Schedule-I species. The plan would then be submitted for approval.
The interlinking of rivers project has been an ambitious plan for the government for more than a decade and a half.
Source: The Wire
Also read: Implementation of river interlinking will raise the ultimate irrigation potential
Next Story
Concorde Acquires 3 Acre in Hennur for Premium High-Rise Project
In a strategic expansion move, Concorde has acquired a 3-acre land parcel in Hennur, North Bengaluru, for a premium high-rise residential development. The upcoming project will feature a saleable built-up area of approximately 4.25 lakh sq. ft., with an estimated Gross Development Value (GDV) of Rs 5 billion. Scheduled for launch in FY 2026鈥�27, the development will offer 2 and 3 BHK premium residences designed to appeal to discerning urban homebuyers seeking elevated, community-centric living in one of the city's fastest-growing corridors. 鈥淭his investment underlines our commitme..
Next Story
JP Infra Launches Monsoon Fest 2025 for 亚博体育官网首页buyers
JP Infra, one of Mumbai鈥檚 most trusted real estate developers, has announced the launch of 鈥楳onsoon Fest 2025鈥�, a limited-period campaign offering exclusive privileges across its residential projects in Mira Road, Thane, and other key locations. Running from 16th June to 31st July 2025, the Monsoon Fest presents a curated package of benefits for homebuyers. Every booking comes with an assured premium White Goods voucher from leading brands. Buyers can also choose one of three value-added offers: 50 per cent waiver on stamp duty Modular kitchen Fully furnished home&nbs..
Next Story
LANXESS Resin Removes Short-Chain PFAS From Water
Speciality chemicals company LANXESS has launched Lewatit MDS TP 108, a new ion exchange resin designed for the efficient removal of short-chain per- and polyfluoroalkyl substances (PFAS) from water. These PFAS compounds鈥攃haracterised by having three or fewer carbon atoms鈥攁re among the smallest and most challenging to eliminate through conventional water purification methods.Lewatit MDS TP 108 marks a significant advancement in the treatment of contaminated water, particularly where traditional technologies such as activated carbon adsorption fall short. The new resin offers a service life..