Dilip Buildcon Completes Navnera Barrage Project in Rajasthan
04 Feb 2025
2 Min Read
CW Team
Dilip Buildcon has successfully completed the construction of the Navnera Barrage (dam) across the Kalisindh River in Rajasthan. The project, part of the Eastern Rajasthan Canal Project (ERCP) Phase-I/(A), was undertaken on an EPC single responsibility turnkey basis.
The project, which involved survey, planning, design, and construction work, was physically completed on September 30, 2024. A completion certificate for the project was issued by the relevant authorities on January 17, 2025, and received by Dilip Buildcon on February 1, 2025.
Details of the project include a revised cost of Rs 6.61 billion and a construction period of 48 months. The original scheduled completion date, including an extension of time (EOT), was set for October 13, 2024. However, the company managed to complete the work ahead of schedule, with the project finished by September 30, 2024.
As a result of the early completion, Dilip Buildcon is entitled to a bonus of Rs 2.53 crore.
In compliance with the Securities and Exchange Board of India (SEBI) regulations, the company has announced the closure of the trading window for all insiders, designated persons, and their immediate relatives. This closure will remain in effect until 48 hours after the declaration of the company鈥檚 financial results for the quarter ending December 31, 2024.
The successful completion of the Navnera Barrage is a significant milestone for Dilip Buildcon and contributes to the ongoing development of critical infrastructure in Rajasthan under the ERCP.
Dilip Buildcon has successfully completed the construction of the Navnera Barrage (dam) across the Kalisindh River in Rajasthan. The project, part of the Eastern Rajasthan Canal Project (ERCP) Phase-I/(A), was undertaken on an EPC single responsibility turnkey basis.The project, which involved survey, planning, design, and construction work, was physically completed on September 30, 2024. A completion certificate for the project was issued by the relevant authorities on January 17, 2025, and received by Dilip Buildcon on February 1, 2025.Details of the project include a revised cost of Rs 6.61 billion and a construction period of 48 months. The original scheduled completion date, including an extension of time (EOT), was set for October 13, 2024. However, the company managed to complete the work ahead of schedule, with the project finished by September 30, 2024.As a result of the early completion, Dilip Buildcon is entitled to a bonus of Rs 2.53 crore.In compliance with the Securities and Exchange Board of India (SEBI) regulations, the company has announced the closure of the trading window for all insiders, designated persons, and their immediate relatives. This closure will remain in effect until 48 hours after the declaration of the company鈥檚 financial results for the quarter ending December 31, 2024.The successful completion of the Navnera Barrage is a significant milestone for Dilip Buildcon and contributes to the ongoing development of critical infrastructure in Rajasthan under the ERCP.
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..