A Construction and Demolition (C&D) waste processing plant in Bakkarwala village here has been fined Rs 5 lakh by the Delhi Pollution Control Committee (DPCC) for various deficiencies in dust pollution control measures.
Several deficiencies were discovered at the Rise Eleven Delhi Waste Management Company site during an inspection on July 2, according to DPCC officials, including the lack of a wheel washing facility and water sprinklers.
A 20-ft PVC sheet was installed as a wind barrier at the C&D waste site's boundary wall, but heaps of C&D waste and loose soil or earth that was to be processed and separated by the plant, as well as the DDA flats' boundary wall, were discovered in the open and outside the plant uncovered.
The DPCC stated in its notice that the wind-breaking PVC wall at the boundary was found to be insufficient.
Following the company's response to DPPC's show-cause notice issued on July 9, the decision to impose environmental compensation was made.
It has also ordered that within 15 days of service of this order, point-by-point compliance with terms and conditions of consent to operate under the Air and Water Acts issued by the DPCC on 27 February 2020, and authorisation under the C&D Waste Management Rules, 2016 issued by the DPCC on 18 March 2020, be submitted.
Notably, under the Air Prevention & Control of Pollution Act, 1981, no person shall establish or operate any industrial plant within the Union Territory of Delhi, which has been declared as an Air Pollution Control area, without the prior consent of the DPCC.
Also read: GWMC floats tender to set up waste plant at Bainguinim
A Construction and Demolition (C&D) waste processing plant in Bakkarwala village here has been fined Rs 5 lakh by the Delhi Pollution Control Committee (DPCC) for various deficiencies in dust pollution control measures.
Several deficiencies were discovered at the Rise Eleven Delhi Waste Management Company site during an inspection on July 2, according to DPCC officials, including the lack of a wheel washing facility and water sprinklers.
A 20-ft PVC sheet was installed as a wind barrier at the C&D waste site's boundary wall, but heaps of C&D waste and loose soil or earth that was to be processed and separated by the plant, as well as the DDA flats' boundary wall, were discovered in the open and outside the plant uncovered.
The DPCC stated in its notice that the wind-breaking PVC wall at the boundary was found to be insufficient.
Following the company's response to DPPC's show-cause notice issued on July 9, the decision to impose environmental compensation was made.
It has also ordered that within 15 days of service of this order, point-by-point compliance with terms and conditions of consent to operate under the Air and Water Acts issued by the DPCC on 27 February 2020, and authorisation under the C&D Waste Management Rules, 2016 issued by the DPCC on 18 March 2020, be submitted.
Notably, under the Air Prevention & Control of Pollution Act, 1981, no person shall establish or operate any industrial plant within the Union Territory of Delhi, which has been declared as an Air Pollution Control area, without the prior consent of the DPCC.
Image Source
Also read: GWMC floats tender to set up waste plant at Bainguinim
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..