BHEL seeks bids for 5 MW Solar Project in Haridwar
19 Jan 2024
3 Min Read
CW Team
Bharat Heavy Electricals (BHEL) is seeking proposals from project developers for the establishment of a 5 MW ground-mounted solar power project at its Ranipur facility in Haridwar. The project will follow a build, own, operate, and maintain framework.
Responsibilities encompass the entire project life cycle, from development and construction to synchronisation, commissioning, operation, and maintenance. Additionally, the bidder must establish the evacuation network up to the BHEL substation.
The chosen contractor is required to enter into a 25-year power purchase agreement (PPA) with BHEL. Interested parties must submit their bids by February 6, 2024, with bid openings scheduled for the same day.
Prospective bidders are obligated to furnish an earnest money deposit of Rs 3 million (~$36,087). Upon successful bidding, the selected party must provide a performance bank guarantee (PBG) of Rs 12.85 million (~$154,569) before PPA signing or within 21 days of receiving the letter of intent, whichever comes first.
Project commissioning must occur within six months of the effective PPA date, with no provision for partial commissioning. A delay of up to one month will trigger the encashment of a partial PBG of Rs 3 million (~$36,087), calculated on a per-day basis. Delays beyond one month and up to three months will result in the remaining PBG of Rs 9.85 million (~$118,482) being encashed.
The declared annual Capacity Utilisation Factor (CUF) must not fall below the specified CUF for each year according to BHEL's tender.
Excess power generated by the project will be directly sold to BHEL, which retains the right to sell or use surplus power at its discretion.
Bidders must have a track record of establishing ground-mounted solar power projects with capacities not less than 2.5 MW, including individual projects of at least 1 MW. Operational and maintenance experience of solar projects with a minimum capacity of 2.5 MW over the past seven financial years is mandatory, and these projects must have been commissioned and operational for at least one year.
Applicants are required to have a net worth equal to or greater than Rs 51.4 million (~$618,268) as of the last date of the financial year 2022-23.
Financial stability must be demonstrated through either a minimum annual average turnover of Rs 102.8 million (~$1.24 million) over the last three financial years or an in-principle sanction letter from lending institutions committing a line of credit of at least Rs 64.3 million (~$773,448) to meet the project's working capital requirements.
In a separate initiative in September 2023, BHEL invited bids to secure 90 million units (MUs) of round-the-clock renewable power annually on a long-term basis. The procured power is intended for supply to the ex-bus periphery at company units in Haridwar (54 MUs), Bhopal (12 MUs), Trichy (12 MUs), and Hyderabad (12 MUs) on a long-term basis.
Bharat Heavy Electricals (BHEL) is seeking proposals from project developers for the establishment of a 5 MW ground-mounted solar power project at its Ranipur facility in Haridwar. The project will follow a build, own, operate, and maintain framework.
Responsibilities encompass the entire project life cycle, from development and construction to synchronisation, commissioning, operation, and maintenance. Additionally, the bidder must establish the evacuation network up to the BHEL substation.
The chosen contractor is required to enter into a 25-year power purchase agreement (PPA) with BHEL. Interested parties must submit their bids by February 6, 2024, with bid openings scheduled for the same day.
Prospective bidders are obligated to furnish an earnest money deposit of Rs 3 million (~$36,087). Upon successful bidding, the selected party must provide a performance bank guarantee (PBG) of Rs 12.85 million (~$154,569) before PPA signing or within 21 days of receiving the letter of intent, whichever comes first.
Project commissioning must occur within six months of the effective PPA date, with no provision for partial commissioning. A delay of up to one month will trigger the encashment of a partial PBG of Rs 3 million (~$36,087), calculated on a per-day basis. Delays beyond one month and up to three months will result in the remaining PBG of Rs 9.85 million (~$118,482) being encashed.
The declared annual Capacity Utilisation Factor (CUF) must not fall below the specified CUF for each year according to BHEL's tender.
Excess power generated by the project will be directly sold to BHEL, which retains the right to sell or use surplus power at its discretion.
Bidders must have a track record of establishing ground-mounted solar power projects with capacities not less than 2.5 MW, including individual projects of at least 1 MW. Operational and maintenance experience of solar projects with a minimum capacity of 2.5 MW over the past seven financial years is mandatory, and these projects must have been commissioned and operational for at least one year.
Applicants are required to have a net worth equal to or greater than Rs 51.4 million (~$618,268) as of the last date of the financial year 2022-23.
Financial stability must be demonstrated through either a minimum annual average turnover of Rs 102.8 million (~$1.24 million) over the last three financial years or an in-principle sanction letter from lending institutions committing a line of credit of at least Rs 64.3 million (~$773,448) to meet the project's working capital requirements.
In a separate initiative in September 2023, BHEL invited bids to secure 90 million units (MUs) of round-the-clock renewable power annually on a long-term basis. The procured power is intended for supply to the ex-bus periphery at company units in Haridwar (54 MUs), Bhopal (12 MUs), Trichy (12 MUs), and Hyderabad (12 MUs) on a long-term basis.
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..