CERC approves compensation for GST rate hike to RE developer
08 Jan 2024
3 Min Read
CW Team
The Central Electricity Regulatory Commission (CERC) has granted approval to a renewable energy developer for seeking compensation to counteract the financial and commercial repercussions arising from changes in law events due to an escalation in the rates of goods and service tax (GST).
The developer is entitled to claim carrying costs, calculated at the minimum of the actual interest rate, the rate specified in the renewable energy tariff regulations, or the late payment surcharge rate stipulated in the power purchase agreement (PPA).
Ostro Energy, a subsidiary of ReNew Power Services, specialises in the development, operation, and maintenance of large-scale grid-connected solar power projects for wind power generation.
The power purchase agreement (PPA) for the 50 MW wind energy project was executed with the Solar Energy Corporation of India (SECI) on October 25, 2019. The Scheduled Commercial Operation Date was set for April 18, 2021. The alteration in GST rates occurred on October 1, 2021.
On June 12, 2022, the company filed a petition seeking compensation to alleviate the financial impact resulting from changes in law events related to the GST rate increase from 5% to 12%.
The petitioner urged the respondent to provide compensation, either as a one-time lump sum payment or through tariff adjustments, in response to the GST tax rate hike. Additionally, it sought interest or carrying costs from the date of incurring the expense until the Commission's order. The respondents in this matter are SECI and Uttar Pradesh Power Corporation (UPPCL).
The Commission noted that Article 12 of the PPAs stipulates that any statutory change in the tax structure affecting the wind power project constitutes a change in law. Recognising that the GST rates changed post the scheduled commercial operation date and considering the principle that change in law compensation should not result in profit, the Commission determined that the discount rate and annuity period would be the appropriate methodology for calculating change in law compensation.
The Commission decided that the liability of the respondents for monthly annuity payments commences from the 60th day from the date of the order or the date of claim submission by the petitioner, whichever is later. In case of delayed monthly annuity payments beyond the 60th day, a late payment surcharge is applicable.
Furthermore, the Commission ruled that Ostro Energy is eligible for carrying costs at the lowest of the actual interest rate paid, the rate of interest on working capital as per applicable renewable energy tariff regulations, or the late payment surcharge rate as per the PPA. Recently, CERC determined that the delay in adopting the tariff order by the Uttar Pradesh Power Corporation is a valid reason to claim an extension in the commissioning date for a wind energy project.
The Central Electricity Regulatory Commission (CERC) has granted approval to a renewable energy developer for seeking compensation to counteract the financial and commercial repercussions arising from changes in law events due to an escalation in the rates of goods and service tax (GST).
The developer is entitled to claim carrying costs, calculated at the minimum of the actual interest rate, the rate specified in the renewable energy tariff regulations, or the late payment surcharge rate stipulated in the power purchase agreement (PPA).
Ostro Energy, a subsidiary of ReNew Power Services, specialises in the development, operation, and maintenance of large-scale grid-connected solar power projects for wind power generation.
The power purchase agreement (PPA) for the 50 MW wind energy project was executed with the Solar Energy Corporation of India (SECI) on October 25, 2019. The Scheduled Commercial Operation Date was set for April 18, 2021. The alteration in GST rates occurred on October 1, 2021.
On June 12, 2022, the company filed a petition seeking compensation to alleviate the financial impact resulting from changes in law events related to the GST rate increase from 5% to 12%.
The petitioner urged the respondent to provide compensation, either as a one-time lump sum payment or through tariff adjustments, in response to the GST tax rate hike. Additionally, it sought interest or carrying costs from the date of incurring the expense until the Commission's order. The respondents in this matter are SECI and Uttar Pradesh Power Corporation (UPPCL).
The Commission noted that Article 12 of the PPAs stipulates that any statutory change in the tax structure affecting the wind power project constitutes a change in law. Recognising that the GST rates changed post the scheduled commercial operation date and considering the principle that change in law compensation should not result in profit, the Commission determined that the discount rate and annuity period would be the appropriate methodology for calculating change in law compensation.
The Commission decided that the liability of the respondents for monthly annuity payments commences from the 60th day from the date of the order or the date of claim submission by the petitioner, whichever is later. In case of delayed monthly annuity payments beyond the 60th day, a late payment surcharge is applicable.
Furthermore, the Commission ruled that Ostro Energy is eligible for carrying costs at the lowest of the actual interest rate paid, the rate of interest on working capital as per applicable renewable energy tariff regulations, or the late payment surcharge rate as per the PPA. Recently, CERC determined that the delay in adopting the tariff order by the Uttar Pradesh Power Corporation is a valid reason to claim an extension in the commissioning date for a wind energy project.
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..