PEDA tenders to set up transmission line for solar project in Punjab
21 Jul 2021
3 Min Read
CW Team
The Punjab Energy Development Agency (PEDA) has invited bids to design, supply, set up, commission, and test an 11 kW cross-linked polyethylene transmission line for a 1 MW solar project at Jogger's Park, Bathinda.
The deadline to submit the bids is 2nd August, and the bids will be opened on 3rd August.
Bidders have to pay Rs 5,000 as a non-refundable tender document fee. PEDA installed the 1 MW solar project under the State Net Metering Policy. This project will produce 415 V of electricity, which can be raised to 11 kV.
The winning bidders have to complete the overall project, including supply, erection, and testing, within 45 days from the date of the work issued.
The winning bidder has to submit a performance bank guarantee amount of 3% equal to the work order value for 15 months from the date of the issue of the notification of award. The performance bank guarantee should be submitted within ten days from the date of issue of the notification of award to approve the rates from the purchaser.
The Municipal Corporation of Bathinda has approved the setting up of the high tension transmission line work. It will release the payment to the winning bidder on the recommendation of PEDA according to the payment schedule.
According to the National Institute of Technology, the solar power generated can be used for captive application, and the grid can get the surplus power as per the State Net Metering Policy. The project site has the Alternating Current Distribution Box (ACBD) near the inverter, and its electricity will be 415 V.
The bidder should be a body incorporated in India under the Companies Act 1956, or 2013, a government-owned enterprise registered and incorporated in India in the power and infrastructure sector, or should be a limited liability partnership company under the LLP Act 2008.
Proprietorship and partnership firms with valid GST numbers can also participate in the bidding process. Also, engineering, procurement, construction companies, suppliers, manufacturers, and system integrators of solar photovoltaic power projects which have not been blacklisted by the government for design, manufacture, supply, install, and commission different solar capacity projects can participate in the bidding process. Consortiums cannot participate in the bidding.
The bidders should have a valid Class 1 Electrical Contractor Licence issued by the chief electrical inspector. The bidder must have completed laying transmission line work for a 1 MW grid-connected solar project in the last three years.
The bidder must have an annual turnover of Rs 5 million in any previous three financial years.
Also read: CERC awards transmission licence to PGCIL鈥檚 Rajasthan subsidiary
The Punjab Energy Development Agency (PEDA) has invited bids to design, supply, set up, commission, and test an 11 kW cross-linked polyethylene transmission line for a 1 MW solar project at Jogger's Park, Bathinda.
The deadline to submit the bids is 2nd August, and the bids will be opened on 3rd August.
Bidders have to pay Rs 5,000 as a non-refundable tender document fee. PEDA installed the 1 MW solar project under the State Net Metering Policy. This project will produce 415 V of electricity, which can be raised to 11 kV.
The winning bidders have to complete the overall project, including supply, erection, and testing, within 45 days from the date of the work issued.
The winning bidder has to submit a performance bank guarantee amount of 3% equal to the work order value for 15 months from the date of the issue of the notification of award. The performance bank guarantee should be submitted within ten days from the date of issue of the notification of award to approve the rates from the purchaser.
The Municipal Corporation of Bathinda has approved the setting up of the high tension transmission line work. It will release the payment to the winning bidder on the recommendation of PEDA according to the payment schedule.
According to the National Institute of Technology, the solar power generated can be used for captive application, and the grid can get the surplus power as per the State Net Metering Policy. The project site has the Alternating Current Distribution Box (ACBD) near the inverter, and its electricity will be 415 V.
The bidder should be a body incorporated in India under the Companies Act 1956, or 2013, a government-owned enterprise registered and incorporated in India in the power and infrastructure sector, or should be a limited liability partnership company under the LLP Act 2008.
Proprietorship and partnership firms with valid GST numbers can also participate in the bidding process. Also, engineering, procurement, construction companies, suppliers, manufacturers, and system integrators of solar photovoltaic power projects which have not been blacklisted by the government for design, manufacture, supply, install, and commission different solar capacity projects can participate in the bidding process. Consortiums cannot participate in the bidding.
The bidders should have a valid Class 1 Electrical Contractor Licence issued by the chief electrical inspector. The bidder must have completed laying transmission line work for a 1 MW grid-connected solar project in the last three years.
The bidder must have an annual turnover of Rs 5 million in any previous three financial years.
Image Source
Also read: CERC awards transmission licence to PGCIL鈥檚 Rajasthan subsidiary
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..