Renewable energy sector faces hurdles as PPA and PSA delays persist
19 Sep 2024
3 Min Read
CW Team
India’s renewable energy sector is experiencing delays in finalising Power Purchase Agreements (PPA) and Power Sale Agreements (PSA), hampering progress for developers amid rising demand for clean energy. The Ministry of New & Renewable Energy introduced an agency-wise bidding calendar in April 2023, targeting 50 GW of renewable energy projects annually through FY 2027-28. This initiative, involving agencies like the Solar Energy Corporation of India (SECI), NTPC, NHPC, and SJVN, aimed to accelerate India's clean energy transition.
This push led to a significant surge in solar tenders and auctions in early 2024, with tenders increasing by 122% year-over-year to over 30.7 GW and auctions witnessing a 2,957% year-over-year growth. Despite this growth, over 43 GW of projects are now stalled, waiting for PPA signings due to a lack of prequalified offtakers.
An official from a Renewable Energy Implementing Agency (REIA) explained that the new bidding trajectory requires the release of tenders even without secured offtakers, disrupting the previous process, where tenders were issued only upon securing a procurer. This has resulted in delays in PSA signings and created challenges in the industry.
Developers had anticipated some of these issues, expecting that stricter penalties for failing to meet Renewable Purchase Obligations (RPOs) would prompt faster PSA signings. The Electricity (Amendment) Bill 2022 introduced penalties for RPO non-compliance, ranging from Rs 0.25 /kWh to Rs 0.50/kWh, incentivizing power distribution companies (DISCOMs) to expedite PPA signings to avoid financial penalties.
However, the large volume of tenders without secured offtakers has frustrated developers. Many tenders face legal disputes or opposition from DISCOMs, particularly when bundled with thermal power. For example, DISCOMs like TANGEDCO in Tamil Nadu and West Bengal have objected to certain tenders, even after the Central Electricity Regulatory Commission (CERC) adopted the tariffs. These disputes have slowed PPA signings, particularly for projects viewed as unfavorable by DISCOMs.
Concerns also arise with hybrid power tenders involving solar, wind, and storage, where tariffs are slightly higher due to the added reliability of supply. Despite this, DISCOMs have hesitated to sign such PPAs, particularly due to concerns over transmission charges, with the inter-state transmission charge waiver applying only to projects commissioned by June 30, 2025.
While higher capacity utilization factors make wind-solar hybrid power and firm renewable energy projects attractive, uncertainties about transmission charges and the structure of tenders continue to pose challenges. Despite government mandates promoting renewable energy adoption, securing offtakers remains a significant issue for developers.
Raj Prabhu, CEO, Mercom Capital Group, emphasized that while setting an annual bidding trajectory was a step toward meeting India’s 2030 renewable energy goals, the entire process from bidding to procurement needs streamlining. He suggested that policy adjustments should ensure that bidding capacities count only if the auction is successful and power is procured, rather than merely announcing tenders.
(Mercom)
India’s renewable energy sector is experiencing delays in finalising Power Purchase Agreements (PPA) and Power Sale Agreements (PSA), hampering progress for developers amid rising demand for clean energy. The Ministry of New & Renewable Energy introduced an agency-wise bidding calendar in April 2023, targeting 50 GW of renewable energy projects annually through FY 2027-28. This initiative, involving agencies like the Solar Energy Corporation of India (SECI), NTPC, NHPC, and SJVN, aimed to accelerate India's clean energy transition.
This push led to a significant surge in solar tenders and auctions in early 2024, with tenders increasing by 122% year-over-year to over 30.7 GW and auctions witnessing a 2,957% year-over-year growth. Despite this growth, over 43 GW of projects are now stalled, waiting for PPA signings due to a lack of prequalified offtakers.
An official from a Renewable Energy Implementing Agency (REIA) explained that the new bidding trajectory requires the release of tenders even without secured offtakers, disrupting the previous process, where tenders were issued only upon securing a procurer. This has resulted in delays in PSA signings and created challenges in the industry.
Developers had anticipated some of these issues, expecting that stricter penalties for failing to meet Renewable Purchase Obligations (RPOs) would prompt faster PSA signings. The Electricity (Amendment) Bill 2022 introduced penalties for RPO non-compliance, ranging from Rs 0.25 /kWh to Rs 0.50/kWh, incentivizing power distribution companies (DISCOMs) to expedite PPA signings to avoid financial penalties.
However, the large volume of tenders without secured offtakers has frustrated developers. Many tenders face legal disputes or opposition from DISCOMs, particularly when bundled with thermal power. For example, DISCOMs like TANGEDCO in Tamil Nadu and West Bengal have objected to certain tenders, even after the Central Electricity Regulatory Commission (CERC) adopted the tariffs. These disputes have slowed PPA signings, particularly for projects viewed as unfavorable by DISCOMs.
Concerns also arise with hybrid power tenders involving solar, wind, and storage, where tariffs are slightly higher due to the added reliability of supply. Despite this, DISCOMs have hesitated to sign such PPAs, particularly due to concerns over transmission charges, with the inter-state transmission charge waiver applying only to projects commissioned by June 30, 2025.
While higher capacity utilization factors make wind-solar hybrid power and firm renewable energy projects attractive, uncertainties about transmission charges and the structure of tenders continue to pose challenges. Despite government mandates promoting renewable energy adoption, securing offtakers remains a significant issue for developers.
Raj Prabhu, CEO, Mercom Capital Group, emphasized that while setting an annual bidding trajectory was a step toward meeting India’s 2030 renewable energy goals, the entire process from bidding to procurement needs streamlining. He suggested that policy adjustments should ensure that bidding capacities count only if the auction is successful and power is procured, rather than merely announcing tenders.
(Mercom)
Next Story
Dassault To Build Falcon Jets In India With Reliance
Reliance Infrastructure Ltd’s subsidiary, Reliance Aerostructure, has signed an agreement with France’s Dassault Aviation to manufacture Falcon 2000 business jets in India, with the first batch expected to roll out from its Nagpur facility by 2028. This marks the first time a Falcon aircraft will be entirely built outside France.The announcement sent Reliance Infrastructure shares surging, hitting the 5 per cent upper circuit on the BSE. Anil Ambani, Chairman of Reliance Group, hailed the agreement as a “symbol of India’s technological and manufacturing strength�, adding that it aims..
Next Story
INDEA Lays Foundation for India’s First Auto Design School
The Indian School for Design of Automobiles (INDEA), the country’s first institute focused solely on automobile design and management, held its foundation stone ceremony at XLRI Delhi-NCR. The event was graced by Union Minister for Road Transport and Highways, Nitin Gadkari, who virtually unveiled the stone as Chief Guest.INDEA aims to become a premier talent hub, driving innovation in the Indian automotive sector. The school will focus on advanced design, mobility solutions, and sustainable practices, playing a vital role in shaping India’s transition from a cost-driven to a quality-led a..
Next Story
Karnataka Launches Global Innovation Hub at Airport City
The Government of Karnataka, in collaboration with Bengaluru Airport City Limited (BACL) and ANSR, has launched a global innovation hub named District I at Bengaluru Airport City's business park. The initiative aims to elevate India’s innovation ecosystem to a global scale by fostering collaboration among startups, academia, enterprises, and government bodies.District I will serve as a platform for deep-tech entrepreneurship, enterprise innovation, and commercialisation of academic research. It brings together Global Capability Centres (GCCs), IT firms, corporate labs, startups, venture capi..