NCLAT Limits Insolvency to One Project
27 Nov 2024
2 Min Read
CW Team
In a significant ruling, the National Company Law Appellate Tribunal (NCLAT) has confined the insolvency proceedings against Raheja Developers to a single project, Raheja Shilas in Sector 109, Gurugram. The appellate tribunal's three-member bench, led by Justice Ashok Bhushan, directed that the Interim Resolution Professional (IRP) collate claims and submit a detailed status report on the project.
The decision came in response to a petition by Navin Raheja, Chairman of the suspended board, challenging an earlier National Company Law Tribunal (NCLT) order that initiated Corporate Insolvency Resolution Proceedings (CIRP) for the entire company. The NCLAT limited insolvency proceedings to Raheja Shilas following requests from flat buyers and the developer.
Raheja Developers assured the tribunal that an Occupancy Certificate (OC) for the project is expected within 4 to 8 weeks, addressing one of the primary concerns raised by the petitioners. The IRP has been instructed to assist in securing the OC and completing the necessary works to ensure the project鈥檚 handover to allottees.
The case stems from complaints by over 40 flat buyers who cited a payment default of ?112.90 crore due to delayed possession, which was initially promised between 2012 and 2014. The NCLT admitted their plea earlier this week and directed the CIRP's progress report submission by January 22, 2025.
This isn鈥檛 the first time Raheja Developers has faced insolvency proceedings. A similar case involving the Raheja Sampada project in 2019 was set aside in 2020, as delays were attributed to the absence of requisite clearances. However, the ongoing scrutiny highlights persistent challenges in the timely delivery of residential projects.
The latest NCLAT decision provides temporary relief to Raheja Developers but underscores the need for improved project management and transparency to restore buyer confidence.
In a significant ruling, the National Company Law Appellate Tribunal (NCLAT) has confined the insolvency proceedings against Raheja Developers to a single project, Raheja Shilas in Sector 109, Gurugram. The appellate tribunal's three-member bench, led by Justice Ashok Bhushan, directed that the Interim Resolution Professional (IRP) collate claims and submit a detailed status report on the project.
The decision came in response to a petition by Navin Raheja, Chairman of the suspended board, challenging an earlier National Company Law Tribunal (NCLT) order that initiated Corporate Insolvency Resolution Proceedings (CIRP) for the entire company. The NCLAT limited insolvency proceedings to Raheja Shilas following requests from flat buyers and the developer.
Raheja Developers assured the tribunal that an Occupancy Certificate (OC) for the project is expected within 4 to 8 weeks, addressing one of the primary concerns raised by the petitioners. The IRP has been instructed to assist in securing the OC and completing the necessary works to ensure the project鈥檚 handover to allottees.
The case stems from complaints by over 40 flat buyers who cited a payment default of ?112.90 crore due to delayed possession, which was initially promised between 2012 and 2014. The NCLT admitted their plea earlier this week and directed the CIRP's progress report submission by January 22, 2025.
This isn鈥檛 the first time Raheja Developers has faced insolvency proceedings. A similar case involving the Raheja Sampada project in 2019 was set aside in 2020, as delays were attributed to the absence of requisite clearances. However, the ongoing scrutiny highlights persistent challenges in the timely delivery of residential projects.
The latest NCLAT decision provides temporary relief to Raheja Developers but underscores the need for improved project management and transparency to restore buyer confidence.
Next Story
MoHUA Plans New Role for Smart City SPVs
In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..
Next Story
ADB Approves $110 Million Loan to Boost Skills in Gujarat
The Asian Development Bank (ADB) has approved a USD 109.97 million (Rs 9.27 billion) results-based loan to support Gujarat鈥檚 efforts to become a global industrial hub by developing a future-ready, skilled workforce.The funding will back the Gujarat skills development programme, led by the Department of Labour, Skill Development and Employment in collaboration with Kaushalya: The Skill University (KSU). The initiative aims to equip the workforce with advanced, industry-aligned skills to meet rising employment demand in high-growth sectors.According to ADB, the programme seeks to strengthen in..
Next Story
SDAL Tests Rudrastra UAV and Bhargavastra Defence System
Solar Defence and Aerospace Limited (SDAL) has successfully completed a key flight test of its indigenous Hybrid VTOL UAV Rudrastra at the Pokharan Firing Range, aligning with Indian Army performance benchmarks for mission adaptability, high endurance, precision engagement, and vertical take-off and landing (VTOL) capability.The trial marks a notable achievement in India鈥檚 Aatmanirbhar Bharat initiative, underscoring advancements in home-grown military technology. The Rudrastra UAV demonstrated a mission radius exceeding 50 km with uninterrupted video relay, a total operational range of over..