The special cooling needs of a data centre
01 Aug 2019
3 Min Read
CW Staff
One of the primary ways in which a data centre differs from a regular commercial building is in its cooling requirements. On average,
Prasanna Sarambale, CEO, Data Centre Business & Group Head, Business Development, Sterling and Wilson, estimates the cooling requirement of a data centre to be more than 10 times that of a conventional commercial space. 鈥淭ypically, 15-20 sq m of commercial office space needs 1 tr of cooling whereas for a similar footprint, a data centre could need more than 10 tr, though this will vary according to the type of data centre, peaking in the case of a Cloud data centre as against a colocation data centre,鈥� he explains. As a thumb rule, Sarambale estimates that for a colocation building, the capital expenditure for 1 tr of implementation could be around Rs 2-2.5 lakh whereas for a commercial building it could be Rs 0.5-0.75 lakh.
However, this comparison is overly simplistic because the data centre needs to be designed for operation 24脳365. Essentially, it isn鈥檛 only the HVAC load that needs to be factored into the building design鈥攖he HVAC system also needs to be made resilient against failure.
This involves incorporating fault tolerance into the infrastructure design depending on the class of the data centre, whether Tier-III/Level 3 or Tier-IV/Level 4, by adopting a dual distribution path and extra standby equipment (redundancy), says Sarambale. Provision is also required for maintenance such that the entire system isn鈥檛 required to be shut down at one time鈥攃onceptually this involves 鈥渃oncurrent maintainability,鈥� he adds. 鈥淎ll these requirements impact building design in terms of space, the number of shafts, the building design load.鈥� So, a high availability data centre for enterprise class, colocation and Cloud should ideally be 鈥減urpose-built鈥�.
鈥淎 Tier-III or Tier-IV data centre would need the building to be designed specifically for data centre operations,鈥� explains Sarambale. 鈥淚t is not possible to accommodate a high availability data centre in a readymade building because of the large area required. Also, the height of the space (floor to ceiling) should be a minimum of 5 m, which is higher than most commercial buildings. Even the floor loading requirement of a data centre is high, in the range of 1,500 kg/sq m whereas commercial buildings are designed for a maximum of 500 kg/sq m.鈥�
For the highest efficiency, Sarambale recommends employing the MEP consultant at the project inception stage and completing the MEP design even before the civil design starts. He also suggests making thermal storage a part of the design in case of high rack load, to maintain continuous cooling during grid failure and before emergency generators kick in.
CHARU BAHRI
One of the primary ways in which a data centre differs from a regular commercial building is in its cooling requirements. On average, Prasanna Sarambale, CEO, Data Centre Business & Group Head, Business Development, Sterling and Wilson, estimates the cooling requirement of a data centre to be more than 10 times that of a conventional commercial space. 鈥淭ypically, 15-20 sq m of commercial office space needs 1 tr of cooling whereas for a similar footprint, a data centre could need more than 10 tr, though this will vary according to the type of data centre, peaking in the case of a Cloud data centre as against a colocation data centre,鈥� he explains. As a thumb rule, Sarambale estimates that for a colocation building, the capital expenditure for 1 tr of implementation could be around Rs 2-2.5 lakh whereas for a commercial building it could be Rs 0.5-0.75 lakh.
However, this comparison is overly simplistic because the data centre needs to be designed for operation 24脳365. Essentially, it isn鈥檛 only the HVAC load that needs to be factored into the building design鈥攖he HVAC system also needs to be made resilient against failure.
This involves incorporating fault tolerance into the infrastructure design depending on the class of the data centre, whether Tier-III/Level 3 or Tier-IV/Level 4, by adopting a dual distribution path and extra standby equipment (redundancy), says Sarambale. Provision is also required for maintenance such that the entire system isn鈥檛 required to be shut down at one time鈥攃onceptually this involves 鈥渃oncurrent maintainability,鈥� he adds. 鈥淎ll these requirements impact building design in terms of space, the number of shafts, the building design load.鈥� So, a high availability data centre for enterprise class, colocation and Cloud should ideally be 鈥減urpose-built鈥�.
鈥淎 Tier-III or Tier-IV data centre would need the building to be designed specifically for data centre operations,鈥� explains Sarambale. 鈥淚t is not possible to accommodate a high availability data centre in a readymade building because of the large area required. Also, the height of the space (floor to ceiling) should be a minimum of 5 m, which is higher than most commercial buildings. Even the floor loading requirement of a data centre is high, in the range of 1,500 kg/sq m whereas commercial buildings are designed for a maximum of 500 kg/sq m.鈥�
For the highest efficiency, Sarambale recommends employing the MEP consultant at the project inception stage and completing the MEP design even before the civil design starts. He also suggests making thermal storage a part of the design in case of high rack load, to maintain continuous cooling during grid failure and before emergency generators kick in.
CHARU BAHRI
Next Story
Reliance, Diehl Advance Pact for Precision-Guided Munitions
Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..
Next Story
Modis Navnirman to Migrate to Main Board, Merge Subsidiary
Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..
Next Story
Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025
The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..