Mopa airport witnesses completion of over 75% airport project
03 May 2022
2 Min Read
CW Team
Director of Goa Civil Aviation, Sunil Shanbhogue, told the media that more than 75% of the work on the international greenfield airport at Mopa has been completed, including the completion of runways.
He said that the work on connectivity from the runway to the passenger terminal is underway.
He added that the technical building has already been handed over to the Airports Authority of India (AAI) and will hand over the air traffic control (ATC) building next week. The installation of equipment at the technical building will begin soon.
GMR Airports Limited, through its subsidiary, Goa International Airport Limited (GGIAL), is recruiting airport rescues, firefighting and baggage screening to Uttar Pradesh and Hyderabad for training.
The state government has targeted inaugurating the airport at the hands of PM Narendra Modi on 15 August.
The total project cost has increased to Rs 2,615 crore because of delays due to judicial proceedings and the Covid-19 pandemic.
Under the concession agreement, GGIAL can operate the business for 40 years, extendable by another 20 years. The airport project will be carried out in four phases. The construction of the second phase will commence only after 80% of the passenger traffic is handled.
The government had given in-principle approval for constructing an 8 km highway from Dhargalim to Varconda.
The project had been stalled by court proceedings, including judicial stay orders, due to environmental issues. In 2020, the Supreme Court (SC) upheld the project鈥檚 environmental clearance (EC) and allowed construction to resume.
According to an official, after the infrastructure is ready, it takes around six months to ensure all the necessary permissions and clearances from authorities to begin operations.
Also read: Action against illegal buildings around Goa airport stalled
Director of Goa Civil Aviation, Sunil Shanbhogue, told the media that more than 75% of the work on the international greenfield airport at Mopa has been completed, including the completion of runways.
He said that the work on connectivity from the runway to the passenger terminal is underway.
He added that the technical building has already been handed over to the Airports Authority of India (AAI) and will hand over the air traffic control (ATC) building next week. The installation of equipment at the technical building will begin soon.
GMR Airports Limited, through its subsidiary, Goa International Airport Limited (GGIAL), is recruiting airport rescues, firefighting and baggage screening to Uttar Pradesh and Hyderabad for training.
The state government has targeted inaugurating the airport at the hands of PM Narendra Modi on 15 August.
The total project cost has increased to Rs 2,615 crore because of delays due to judicial proceedings and the Covid-19 pandemic.
Under the concession agreement, GGIAL can operate the business for 40 years, extendable by another 20 years. The airport project will be carried out in four phases. The construction of the second phase will commence only after 80% of the passenger traffic is handled.
The government had given in-principle approval for constructing an 8 km highway from Dhargalim to Varconda.
The project had been stalled by court proceedings, including judicial stay orders, due to environmental issues. In 2020, the Supreme Court (SC) upheld the project鈥檚 environmental clearance (EC) and allowed construction to resume.
According to an official, after the infrastructure is ready, it takes around six months to ensure all the necessary permissions and clearances from authorities to begin operations.
Image Source
Also read: Action against illegal buildings around Goa airport stalled
Next Story
MoHUA Plans New Role for Smart City SPVs
In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..
Next Story
ADB Approves $110 Million Loan to Boost Skills in Gujarat
The Asian Development Bank (ADB) has approved a USD 109.97 million (Rs 9.27 billion) results-based loan to support Gujarat鈥檚 efforts to become a global industrial hub by developing a future-ready, skilled workforce.The funding will back the Gujarat skills development programme, led by the Department of Labour, Skill Development and Employment in collaboration with Kaushalya: The Skill University (KSU). The initiative aims to equip the workforce with advanced, industry-aligned skills to meet rising employment demand in high-growth sectors.According to ADB, the programme seeks to strengthen in..
Next Story
SDAL Tests Rudrastra UAV and Bhargavastra Defence System
Solar Defence and Aerospace Limited (SDAL) has successfully completed a key flight test of its indigenous Hybrid VTOL UAV Rudrastra at the Pokharan Firing Range, aligning with Indian Army performance benchmarks for mission adaptability, high endurance, precision engagement, and vertical take-off and landing (VTOL) capability.The trial marks a notable achievement in India鈥檚 Aatmanirbhar Bharat initiative, underscoring advancements in home-grown military technology. The Rudrastra UAV demonstrated a mission radius exceeding 50 km with uninterrupted video relay, a total operational range of over..