亚博体育官网首页

As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr
ROADS & HIGHWAYS

As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr

As per a report, 428 infrastructure projects, each entailing an investment of Rs 150 crore or above, have been hit by cost overruns of more than Rs 4.98 lakh crore.

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,559 projects, 428 projects declared cost overruns, and around 647 projects were delayed.

The ministry's latest report for April 2022 said the total original cost of execution of the 1559 projects was Rs 21,73,907.11 crore, and their expected completion cost is likely to be Rs 26,72,201.26 crore, which reflects overall cost overruns of Rs 4,98,294.15 crore.

The expenditure incurred on these infrastructure projects till April 2022 was Rs 13,50,610.98 crore, which was 50.54% of their expected cost, according to the report.

However, the number of delayed projects drops to 525 if the delay is calculated based on the latest plan of completion.

Further, for 619 projects neither the commissioning year nor the tentative gestation period has been declared.

Out of the 647 delayed projects, 103 have overall delays in the range of 1-12 months, 111 have been stalled for 13-24 months, 314 projects for 25-60 months, and 119 projects have been stalled for 61 months and more.

The average time overrun in these 647 stalled projects was 42.83 months.

Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, delay in acquiring forest and environment approvals, delay in finalisation of detailed engineering, lack of infrastructure support and linkages, ordering and equipment supply, delay in tie-up for project financing, change in scope, delay in tendering, and law and order problems.

The report also mentioned state-wise lockdowns due to Covid-19 as a cause for the delay in execution of these projects.

It has also been observed that project companies are not informing revised cost estimates and commissioning plans for many projects, which indicates that time and cost overrun figures are under-reported.


Also read: Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

As per a report, 428 infrastructure projects, each entailing an investment of Rs 150 crore or above, have been hit by cost overruns of more than Rs 4.98 lakh crore. According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,559 projects, 428 projects declared cost overruns, and around 647 projects were delayed. The ministry's latest report for April 2022 said the total original cost of execution of the 1559 projects was Rs 21,73,907.11 crore, and their expected completion cost is likely to be Rs 26,72,201.26 crore, which reflects overall cost overruns of Rs 4,98,294.15 crore. The expenditure incurred on these infrastructure projects till April 2022 was Rs 13,50,610.98 crore, which was 50.54% of their expected cost, according to the report. However, the number of delayed projects drops to 525 if the delay is calculated based on the latest plan of completion. Further, for 619 projects neither the commissioning year nor the tentative gestation period has been declared. Out of the 647 delayed projects, 103 have overall delays in the range of 1-12 months, 111 have been stalled for 13-24 months, 314 projects for 25-60 months, and 119 projects have been stalled for 61 months and more. The average time overrun in these 647 stalled projects was 42.83 months. Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, delay in acquiring forest and environment approvals, delay in finalisation of detailed engineering, lack of infrastructure support and linkages, ordering and equipment supply, delay in tie-up for project financing, change in scope, delay in tendering, and law and order problems. The report also mentioned state-wise lockdowns due to Covid-19 as a cause for the delay in execution of these projects. It has also been observed that project companies are not informing revised cost estimates and commissioning plans for many projects, which indicates that time and cost overrun figures are under-reported. Image Source Also read: Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

Next Story
Resources

RentenPe and Mygate Partner to Transform Rent Payments in India

Through a strategic partnership, RentenPe and Mygate aim to streamline rent payments and promote financial inclusion by enabling rent-based credit scores for Indian renters. RentenPe, India鈥檚 first Rent Credit Score鈩� platform and a pioneer in rental fintech innovation, has entered a significant alliance with Mygate, the leading community management app in the country. This partnership will transform rent transactions for millions of Indian households by embedding RentenPe鈥檚 payment and rent credit scoring technology directly within the Mygate app. With this integration, all ren..

Next Story
Real Estate

Supreme Unveils New Brand Identity to Elevate Lifestyle

Supreme, a respected name in Indian real estate with a four-decade legacy, has announced a complete rebranding. The move includes the launch of a new logo and a revamped website, both reflecting the group鈥檚 refreshed vision to 鈥楨levate Lifestyle鈥�. This brand transformation represents more than a visual refresh鈥攊t marks a strategic shift in the company鈥檚 mission, visual identity and market positioning. The update will be visible across all of Supreme鈥檚 digital, social and offline communication platforms. At the core of the initiative is a renewed focus on purposeful design..

Next Story
Infrastructure Urban

Capri Loans Launches #TarrakiKeHaath Campaign Honouring India鈥檚 Everyday Heroes

Capri Global Capital Ltd (Capri Loans), a leading non-banking financial company, has unveiled its latest brand campaign, #TarrakiKeHaath, a powerful tribute to the everyday hands that build India 鈥� from kirana store owners and taxi drivers to dhaba workers, tailors, and carpenters. Narrated by Capri Loans鈥� long-standing brand ambassador and acclaimed actor Pankaj Tripathi, the campaign celebrates the dignity, resilience, and aspirations of self-employed individuals and small business owners who form the backbone of Bharat鈥檚 economy. Conceptualized by Rediffusion Brand Solutions, the..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement