Chenab Bridge: A Golden Joint
16 Nov 2022
2 Min Read
CW Team
The world鈥檚 highest single-arch railway bridge - the Chenab Bridge - witnessed the completion of its steel arch last year. What鈥檚 more, the overarch deck was also recently completed.
The overarch deck launching of the Chenab Railway Bridge was recently completed with a golden joint鈥� truly a global milestone for India at the world鈥檚 highest railway bridge.
So, what鈥檚 this achievement all about? Ninety-eight deck segments, each weighing about 85tonne, have been simultaneously launched from both ends of the valley over the mighty steel arch. Both ends finally met to complete the bridge overarch deck.The segments have been joined with the help of high strength friction grip (HSFG) bolts to mark the golden joint. This not only completes the bridge over the Chenab River valley, but creates a new chapter in the history of Jammu & Kashmir.
鈥淎fcons has been doing technologically complex projectsright from the early days,鈥� says S Paramasivan, Managing Director, Afcons. 鈥淚 must say Chenab Bridge will be on the top of the list, for the simple reason that this is a once-in-a-generation project. With all humility, I can say that India has not seen such a project so far...鈥�
Giridhar Rajagopalan, Deputy Managing Director, Afcons, adds, 鈥淭he overarch deck completion, 359m above the Chenab riverbed, will be an extraordinary achievement. I have my highest respect for every engineer and worker who has contributed to this engineering achievement. This golden joint will usher in a golden moment in the history of Indian Railways and will become a golden chapter in the history of Jammu &Kashmir. The construction engineering was completely done by Indian engineers, which makes the Chenab Railway Bridge a symbol of Atmanirbhar Bharat.鈥�
Indeed, the Chenab Railway Bridge is a construction mammoth. Around 30,350 mt of steel has been used in the 1,315-m bridge construction; 10,620 mtof steel has been consumed in the construction of the gigantic arch; and 14,504 mt of steel has gone into the construction of the bridge deck. The bridge, on the upstream of Salal Dam, is situated near Kauri village in the Reasi district of Jammu &Kashmir. Constructed by Mumbai-based infrastructure major Afcons, the execution plan has taken into consideration safety, quality and productivity as the driving parameters.
To read the full coverage of this project, CLICK HERE.
The world鈥檚 highest single-arch railway bridge - the Chenab Bridge - witnessed the completion of its steel arch last year. What鈥檚 more, the overarch deck was also recently completed.
The overarch deck launching of the Chenab Railway Bridge was recently completed with a golden joint鈥� truly a global milestone for India at the world鈥檚 highest railway bridge.
So, what鈥檚 this achievement all about? Ninety-eight deck segments, each weighing about 85tonne, have been simultaneously launched from both ends of the valley over the mighty steel arch. Both ends finally met to complete the bridge overarch deck.The segments have been joined with the help of high strength friction grip (HSFG) bolts to mark the golden joint. This not only completes the bridge over the Chenab River valley, but creates a new chapter in the history of Jammu & Kashmir.
鈥淎fcons has been doing technologically complex projectsright from the early days,鈥� says S Paramasivan, Managing Director, Afcons. 鈥淚 must say Chenab Bridge will be on the top of the list, for the simple reason that this is a once-in-a-generation project. With all humility, I can say that India has not seen such a project so far...鈥�
Giridhar Rajagopalan, Deputy Managing Director, Afcons, adds, 鈥淭he overarch deck completion, 359m above the Chenab riverbed, will be an extraordinary achievement. I have my highest respect for every engineer and worker who has contributed to this engineering achievement. This golden joint will usher in a golden moment in the history of Indian Railways and will become a golden chapter in the history of Jammu &Kashmir. The construction engineering was completely done by Indian engineers, which makes the Chenab Railway Bridge a symbol of Atmanirbhar Bharat.鈥�
Indeed, the Chenab Railway Bridge is a construction mammoth. Around 30,350 mt of steel has been used in the 1,315-m bridge construction; 10,620 mtof steel has been consumed in the construction of the gigantic arch; and 14,504 mt of steel has gone into the construction of the bridge deck. The bridge, on the upstream of Salal Dam, is situated near Kauri village in the Reasi district of Jammu &Kashmir. Constructed by Mumbai-based infrastructure major Afcons, the execution plan has taken into consideration safety, quality and productivity as the driving parameters.To read the full coverage of this project, CLICK HERE.
Next Story
MoHUA Plans New Role for Smart City SPVs
In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..
Next Story
ADB Approves $110 Million Loan to Boost Skills in Gujarat
The Asian Development Bank (ADB) has approved a USD 109.97 million (Rs 9.27 billion) results-based loan to support Gujarat鈥檚 efforts to become a global industrial hub by developing a future-ready, skilled workforce.The funding will back the Gujarat skills development programme, led by the Department of Labour, Skill Development and Employment in collaboration with Kaushalya: The Skill University (KSU). The initiative aims to equip the workforce with advanced, industry-aligned skills to meet rising employment demand in high-growth sectors.According to ADB, the programme seeks to strengthen in..
Next Story
SDAL Tests Rudrastra UAV and Bhargavastra Defence System
Solar Defence and Aerospace Limited (SDAL) has successfully completed a key flight test of its indigenous Hybrid VTOL UAV Rudrastra at the Pokharan Firing Range, aligning with Indian Army performance benchmarks for mission adaptability, high endurance, precision engagement, and vertical take-off and landing (VTOL) capability.The trial marks a notable achievement in India鈥檚 Aatmanirbhar Bharat initiative, underscoring advancements in home-grown military technology. The Rudrastra UAV demonstrated a mission radius exceeding 50 km with uninterrupted video relay, a total operational range of over..