Construction challenges of Delhi Meerut Expressway Package 3
ROADS & HIGHWAYS

Construction challenges of Delhi Meerut Expressway Package 3

Union Minister for Road Transport & Highways and MSMEs Nitin Gadkari recently inaugurated Package 3 of the Delhi-Meerut Expressway, built at a civil cost of Rs 10.57 billion. The project is expected to help decongest the NCR, reduce travel time and heavy traffic jams in this section, and bring a significant reduction in the pollution level owing to lower fuel consumption.

The APCO Chetak Expressway JV executed work on this package. Innovative planning, design and construction methods marked the construction of the viaduct of this project for reducing construction time by the selection of materials, technology and sequence of operations, shares Sanjay Shrivastava, Vice President. He shares more on the challenges in the construction of the package and how were these overcome...

a. Restricted ROW
The concession agreement was to construct six lane elevated highway (25.65 m width) in 32 m wide restricted ROW width (Pilakua Habitation), with both side dense shopping habitation, in a length of 4.680 Km. It is worth to mention that the road width provided in CA as per Schedule A is 45 m, except Pilakua Habitation where existing ROW was 32 m.

The road section is connecting Delhi to Lucknow, via Moradabad, Bareli, Shajahanpur and is very important road of the area.

The Pilakua area and road network was studied and found that there were neither proper service roads nor alternative routes where traffic can be diverted. Since there was no option, the 25.65 m wide deck construction has to be undertaken up with traffic plying in market place for a length of 4680 m, with a restricted width (ROW) of 32 m. Construction operations inevitably require work forces to occupy the roadway. There is a need to provide for sufficient space to perform construction operations, while reducing the impact of these operations on the travelling public. The construction scheme was very difficult with present day in situ working.

b. Safety of commuters
The safe and efficient flow of traffic approaching and passing through work zones was the major concern to highway users and those involved in construction of roadways. More frequently, the travelling public is demanding increased mobility, while displaying less tolerance for delays, increased travel time, and inconvenience because of congestion, especially congestion caused by highway facility construction operations.

Construction operations inevitably require work forces to occupy the roadway. There is a need to provide for sufficient space to perform construction operations, while reducing the impact of these operations on the road users and local residents.

The construction in Pilkhuwa habitation area with safety for the commuters plying underneath, the construction zone requires a broader and more comprehensive approach to the problem than looking for marginal improvements in existing techniques. Re-conceptualization of the problem during the planning phase, lead to alternative designs which were innovative and used improvised approach to construction that could yield greater benefits in terms of reduced delay, disruption, and safety.

The scheme was discussed at large for possible structural solutions, with all stakeholders and the most optimal working solution was thus obtained. The segmental construction was ruled out, for huge setup and transportation and erection of wide and heavy segments in restricted carriage way of busy market road.

c. Environment challenges
The present road in question is Dasna Hapur Road Project, section of NH 24, which handles more than 3000 traveler per hour (Maximum in peak time) in one direction, through Pilkhuwa habitation area.

The local public in Pilkhuwa Habitation was facing the severe environment concerns of Noise and Air by way of moving traffic and probable threat due to proposed viaduct construction towards air, noise, vibration, solid and liquid pollution.

The development of an ambitious program regarding the nuisance-mitigating infrastructure through a prototype system of integrated technologies is to contribute and reduce nuisance (noise, vibration and air, solid and liquid pollution). This includes a particularly original work regarding mitigation of air pollution in road.

- SERAPHINA D鈥橲OUZA

Union Minister for Road Transport & Highways and MSMEs Nitin Gadkari recently inaugurated Package 3 of the Delhi-Meerut Expressway, built at a civil cost of Rs 10.57 billion. The project is expected to help decongest the NCR, reduce travel time and heavy traffic jams in this section, and bring a significant reduction in the pollution level owing to lower fuel consumption. The APCO Chetak Expressway JV executed work on this package. Innovative planning, design and construction methods marked the construction of the viaduct of this project for reducing construction time by the selection of materials, technology and sequence of operations, shares Sanjay Shrivastava, Vice President. He shares more on the challenges in the construction of the package and how were these overcome... a. Restricted ROW The concession agreement was to construct six lane elevated highway (25.65 m width) in 32 m wide restricted ROW width (Pilakua Habitation), with both side dense shopping habitation, in a length of 4.680 Km. It is worth to mention that the road width provided in CA as per Schedule A is 45 m, except Pilakua Habitation where existing ROW was 32 m. The road section is connecting Delhi to Lucknow, via Moradabad, Bareli, Shajahanpur and is very important road of the area. The Pilakua area and road network was studied and found that there were neither proper service roads nor alternative routes where traffic can be diverted. Since there was no option, the 25.65 m wide deck construction has to be undertaken up with traffic plying in market place for a length of 4680 m, with a restricted width (ROW) of 32 m. Construction operations inevitably require work forces to occupy the roadway. There is a need to provide for sufficient space to perform construction operations, while reducing the impact of these operations on the travelling public. The construction scheme was very difficult with present day in situ working. b. Safety of commuters The safe and efficient flow of traffic approaching and passing through work zones was the major concern to highway users and those involved in construction of roadways. More frequently, the travelling public is demanding increased mobility, while displaying less tolerance for delays, increased travel time, and inconvenience because of congestion, especially congestion caused by highway facility construction operations. Construction operations inevitably require work forces to occupy the roadway. There is a need to provide for sufficient space to perform construction operations, while reducing the impact of these operations on the road users and local residents. The construction in Pilkhuwa habitation area with safety for the commuters plying underneath, the construction zone requires a broader and more comprehensive approach to the problem than looking for marginal improvements in existing techniques. Re-conceptualization of the problem during the planning phase, lead to alternative designs which were innovative and used improvised approach to construction that could yield greater benefits in terms of reduced delay, disruption, and safety. The scheme was discussed at large for possible structural solutions, with all stakeholders and the most optimal working solution was thus obtained. The segmental construction was ruled out, for huge setup and transportation and erection of wide and heavy segments in restricted carriage way of busy market road. c. Environment challenges The present road in question is Dasna Hapur Road Project, section of NH 24, which handles more than 3000 traveler per hour (Maximum in peak time) in one direction, through Pilkhuwa habitation area. The local public in Pilkhuwa Habitation was facing the severe environment concerns of Noise and Air by way of moving traffic and probable threat due to proposed viaduct construction towards air, noise, vibration, solid and liquid pollution. The development of an ambitious program regarding the nuisance-mitigating infrastructure through a prototype system of integrated technologies is to contribute and reduce nuisance (noise, vibration and air, solid and liquid pollution). This includes a particularly original work regarding mitigation of air pollution in road. - SERAPHINA D鈥橲OUZA

Next Story
Infrastructure Urban

Reliance, Diehl Advance Pact for Precision-Guided Munitions

Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..

Next Story
Infrastructure Urban

Modis Navnirman to Migrate to Main Board, Merge Subsidiary

Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..

Next Story
Infrastructure Urban

Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025

The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement