National Highways Construction to Drop 7-10% in FY25: CareEdge Ratings
10 Feb 2025
2 Min Read
CW Team
The pace of National Highway construction in India is expected to slow by 7-10 per cent in FY25, with the estimated completion dropping from 12,350 km in FY24 to around 11,100-11,500 km in FY25, averaging nearly 31 km per day. This decline is primarily due to challenges in execution, increased competition, and significant delays in receiving appointed dates after project awards.
Approximately 55 per cent of the under-construction projects, valued at Rs 0.1 million with a combined bid project cost (BPC) of Rs 1 trillion, have been delayed by over six months. This is mainly attributed to escalating execution hurdles, a more competitive environment, and delays in project scheduling after award announcements.
CareEdge Ratings also conducted an extensive financial analysis of 17 sponsors and EPC contractors involved in Hybrid Annuity Model (HAM) projects. Despite a 14% compound annual growth rate (CAGR) in total operating income (TOI) between FY21 and FY24, reduced project awards in FY24 and H1FY25 have significantly decreased revenue prospects.
The order book-to-TOI ratio has dropped from 2.78x in FY22 to 2.15x in FY24, reflecting a much smaller executable order book, with many projects still awaiting appointed dates. Operating profitability is expected to decrease by 200 basis points in FY25, due to heightened competition and rising overhead costs.
Additionally, the discontinuation of the Atma Nirbhar Bharat scheme for monthly payments is likely to extend the working capital cycle by 15-20 days in FY25, placing further strain on developers. The Hybrid Annuity Model continues to dominate, accounting for nearly 55 per cent of the total projects awarded between FY21 and FY24, with a combined BPC of over Rs 4.03 trillion across 374 HAM projects.
News source: The Free Press Journal
The pace of National Highway construction in India is expected to slow by 7-10 per cent in FY25, with the estimated completion dropping from 12,350 km in FY24 to around 11,100-11,500 km in FY25, averaging nearly 31 km per day. This decline is primarily due to challenges in execution, increased competition, and significant delays in receiving appointed dates after project awards.
Approximately 55 per cent of the under-construction projects, valued at Rs 0.1 million with a combined bid project cost (BPC) of Rs 1 trillion, have been delayed by over six months. This is mainly attributed to escalating execution hurdles, a more competitive environment, and delays in project scheduling after award announcements.
CareEdge Ratings also conducted an extensive financial analysis of 17 sponsors and EPC contractors involved in Hybrid Annuity Model (HAM) projects. Despite a 14% compound annual growth rate (CAGR) in total operating income (TOI) between FY21 and FY24, reduced project awards in FY24 and H1FY25 have significantly decreased revenue prospects.
The order book-to-TOI ratio has dropped from 2.78x in FY22 to 2.15x in FY24, reflecting a much smaller executable order book, with many projects still awaiting appointed dates. Operating profitability is expected to decrease by 200 basis points in FY25, due to heightened competition and rising overhead costs.
Additionally, the discontinuation of the Atma Nirbhar Bharat scheme for monthly payments is likely to extend the working capital cycle by 15-20 days in FY25, placing further strain on developers. The Hybrid Annuity Model continues to dominate, accounting for nearly 55 per cent of the total projects awarded between FY21 and FY24, with a combined BPC of over Rs 4.03 trillion across 374 HAM projects.
News source: The Free Press Journal
Next Story
MoHUA Plans New Role for Smart City SPVs
In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..
Next Story
ADB Approves $110 Million Loan to Boost Skills in Gujarat
The Asian Development Bank (ADB) has approved a USD 109.97 million (Rs 9.27 billion) results-based loan to support Gujarat鈥檚 efforts to become a global industrial hub by developing a future-ready, skilled workforce.The funding will back the Gujarat skills development programme, led by the Department of Labour, Skill Development and Employment in collaboration with Kaushalya: The Skill University (KSU). The initiative aims to equip the workforce with advanced, industry-aligned skills to meet rising employment demand in high-growth sectors.According to ADB, the programme seeks to strengthen in..
Next Story
SDAL Tests Rudrastra UAV and Bhargavastra Defence System
Solar Defence and Aerospace Limited (SDAL) has successfully completed a key flight test of its indigenous Hybrid VTOL UAV Rudrastra at the Pokharan Firing Range, aligning with Indian Army performance benchmarks for mission adaptability, high endurance, precision engagement, and vertical take-off and landing (VTOL) capability.The trial marks a notable achievement in India鈥檚 Aatmanirbhar Bharat initiative, underscoring advancements in home-grown military technology. The Rudrastra UAV demonstrated a mission radius exceeding 50 km with uninterrupted video relay, a total operational range of over..