NHAI scraps 27 km elevated corridor, considers flyovers on GST Road
04 Jun 2024
2 Min Read
CW Team
The National Highways Authority of India (NHAI) is considering altering its plans to reduce the project cost and mitigate the financial burden imposed on road users. Instead of constructing a 27-km long elevated corridor from Tambaram to Chengalpattu on the GST Road, NHAI is contemplating the construction of multiple elevated stretches or flyovers to ensure smooth traffic flow.
Initially, the elevated corridor project, estimated at Rs 35.23 billion, was supposed to commence at Perungalathur and terminate beyond Paranur Toll Plaza, traversing 15 major and minor intersections on the GST Road, as outlined in the draft DPR. The projected cost per kilometer for the elevated project stands at Rs 1.47 billion.
Sources have revealed that this reconsideration stemmed from the realization that the extensive elevated road would incur exorbitant project costs, resulting in substantially high toll charges, thus posing an additional burden on road users. Accordingly, the revised plan aims to erect multiple flyovers instead of a singular elevated corridor to alleviate the toll burden.
Existing grade separators or flyovers already exist at all major junctions between Perungalathur and Vandalur. NHAI is contemplating the construction of a seven-kilometer long elevated corridor from Iyencheri junction to Potheri to facilitate the unimpeded entry and exit of buses to the Kilambakkam terminus, thus bypassing Urapakkam, Guduvancheri, and Kattankulathur junctions, according to sources.
We have tasked the consultant with pinpointing the specific locations where the elevated stretches or flyovers should be erected. Following the submission of the DPR, we will reach a final decision, stated the sources. It is anticipated that the elevated stretches will be developed at Maraimalai Nagar, Ford Factory, Singaperumal Koil, and Mahindra City junctions.
The proposed elevated roads or flyovers will be six-lane structures along the GST Road, with provisions for local traffic to utilise lanes beneath them.
NHAI has already completed the eight-laning of the Tambaram-Chettipuniyam stretch by narrowing the median width on the GST Road. Subsequently, the completion of road widening efforts has significantly alleviated traffic congestion. The GST Road witnesses approximately 1.5 lakh vehicles daily. Once the construction of the ROB-cum-grade separator at Perungalathur concludes, traffic movement between Tambaram and Urapakkam junctions is expected to be unimpeded.
The National Highways Authority of India (NHAI) is considering altering its plans to reduce the project cost and mitigate the financial burden imposed on road users. Instead of constructing a 27-km long elevated corridor from Tambaram to Chengalpattu on the GST Road, NHAI is contemplating the construction of multiple elevated stretches or flyovers to ensure smooth traffic flow.
Initially, the elevated corridor project, estimated at Rs 35.23 billion, was supposed to commence at Perungalathur and terminate beyond Paranur Toll Plaza, traversing 15 major and minor intersections on the GST Road, as outlined in the draft DPR. The projected cost per kilometer for the elevated project stands at Rs 1.47 billion.
Sources have revealed that this reconsideration stemmed from the realization that the extensive elevated road would incur exorbitant project costs, resulting in substantially high toll charges, thus posing an additional burden on road users. Accordingly, the revised plan aims to erect multiple flyovers instead of a singular elevated corridor to alleviate the toll burden.
Existing grade separators or flyovers already exist at all major junctions between Perungalathur and Vandalur. NHAI is contemplating the construction of a seven-kilometer long elevated corridor from Iyencheri junction to Potheri to facilitate the unimpeded entry and exit of buses to the Kilambakkam terminus, thus bypassing Urapakkam, Guduvancheri, and Kattankulathur junctions, according to sources.
We have tasked the consultant with pinpointing the specific locations where the elevated stretches or flyovers should be erected. Following the submission of the DPR, we will reach a final decision, stated the sources. It is anticipated that the elevated stretches will be developed at Maraimalai Nagar, Ford Factory, Singaperumal Koil, and Mahindra City junctions.
The proposed elevated roads or flyovers will be six-lane structures along the GST Road, with provisions for local traffic to utilise lanes beneath them.
NHAI has already completed the eight-laning of the Tambaram-Chettipuniyam stretch by narrowing the median width on the GST Road. Subsequently, the completion of road widening efforts has significantly alleviated traffic congestion. The GST Road witnesses approximately 1.5 lakh vehicles daily. Once the construction of the ROB-cum-grade separator at Perungalathur concludes, traffic movement between Tambaram and Urapakkam junctions is expected to be unimpeded.
Next Story
Swamiraj Rebrands as House of Swamiraj, Announces Rs 210 Cr Project
In a strategic shift marking its evolution from a reputed builder to a lifestyle-focused brand, Swamiraj Constructions has rebranded as House of Swamiraj. With a two-decade legacy and over 1,700 homes delivered across the Mumbai Metropolitan Region (MMR), the company is embracing a new phase centred on community-driven, wellness-oriented living. The rebranding was unveiled via a digital campaign titled #BeyondDimensions, executed in three phases—teaser, engagement, and launch. The campaign spotlighted the brand’s renewed commitment to designing homes that go beyond function to foster ..
Next Story
Morpho Dimensions Set to Cross Rs 1 billion Revenue in FY 25�26
Morpho Dimensions, a venture of acclaimed architecture and design firm Morphogenesis, is transforming India’s office interiors landscape with a technology-first, design-led approach. With a secured orderbook of Rs 700 million and additional projects in the pipeline, the firm is confidently on track to cross Rs 1 billion in revenue in FY 2025�26. By combining Artificial Intelligence (AI), Building Information Modelling (BIM), and Virtual Reality (VR), Morpho Dimensions enables clients to visualise and step into immersive, ready-to-operate workspaces within 90 days—ushering in a new bench..
Next Story
TOTO’s NEOREST Surpasses 4 Million Global Shipments
TOTO has announced that its flagship smart toilet, NEOREST, has surpassed 4 million global shipments as of March 2025, marking a major milestone in the evolution of luxury sanitation and setting a new global benchmark in design-led hygiene innovation. Launched in 1993 with the aim to redefine conventional toilets, NEOREST has consistently merged cutting-edge technology with minimalist design. Over three decades, it has become a category-defining product, earning global acclaim with prestigious honours including the iF Design Award, Red Dot, and Green Good Design Awards. The integrate..