亚博体育官网首页

Porvorim elevated corridor cost rises by Rs 700 Mn
ROADS & HIGHWAYS

Porvorim elevated corridor cost rises by Rs 700 Mn

The cost of the 5.15-km elevated corridor under construction in Porvorim along National Highway 66 has escalated by Rs 700 million due to unforeseen piling work requirements. According to officials, the additional cost arises from a significant increase in the required depth of the piling work.

鈥淓arlier, consultants had recommended piling work of up to 16 m below ground. However, during construction, it was found that the piles need to extend to 45-47 m to ensure structural stability. For this difference, the contractor has submitted a claim of Rs 700 million,鈥� said Jude Carvalho, Executive Engineer of the Public Works Department (PWD), National Highways division.

The contractor鈥檚 claim for the increased cost has been submitted to the Union Ministry of Road Transport and Highways (MoRTH) for approval. Carvalho acknowledged that the escalation in costs might seem excessive but stressed that the final decision rests with the central government. 鈥淭he variation in the cost escalation is under scrutiny. It is now up to MoRTH to determine if the claim is justified. As of now, no additional funds have been approved,鈥� Carvalho added.

Despite the cost overrun, the PWD has assured that construction timelines will remain unaffected. The elevated corridor, which commenced construction in April, is progressing at a swift pace and is expected to be completed by 2026. 鈥淭he additional burden will not impact the pace or schedule of the work. In fact, the contractor is moving at a very fast pace and is likely to complete the project well within the deadline, even with the variation in piling work,鈥� Carvalho said.

The construction contract for the elevated corridor has been awarded to Rajendra Singh Bamboo Infra Pvt Ltd (RSBIPL), a Rajasthan-based infrastructure company. The six-lane elevated corridor aims to alleviate the notorious traffic congestion along the bustling Porvorim stretch of NH-66, which serves as a critical artery connecting Goa鈥檚 northern and southern regions.

The corridor is expected to enhance travel experiences by providing a smoother, safer, and more efficient route for commuters. Once completed, the project is anticipated to be a game-changer for the region鈥檚 infrastructure, addressing years of traffic bottlenecks and significantly reducing travel time for thousands of daily commuters.

The cost of the 5.15-km elevated corridor under construction in Porvorim along National Highway 66 has escalated by Rs 700 million due to unforeseen piling work requirements. According to officials, the additional cost arises from a significant increase in the required depth of the piling work. 鈥淓arlier, consultants had recommended piling work of up to 16 m below ground. However, during construction, it was found that the piles need to extend to 45-47 m to ensure structural stability. For this difference, the contractor has submitted a claim of Rs 700 million,鈥� said Jude Carvalho, Executive Engineer of the Public Works Department (PWD), National Highways division. The contractor鈥檚 claim for the increased cost has been submitted to the Union Ministry of Road Transport and Highways (MoRTH) for approval. Carvalho acknowledged that the escalation in costs might seem excessive but stressed that the final decision rests with the central government. 鈥淭he variation in the cost escalation is under scrutiny. It is now up to MoRTH to determine if the claim is justified. As of now, no additional funds have been approved,鈥� Carvalho added. Despite the cost overrun, the PWD has assured that construction timelines will remain unaffected. The elevated corridor, which commenced construction in April, is progressing at a swift pace and is expected to be completed by 2026. 鈥淭he additional burden will not impact the pace or schedule of the work. In fact, the contractor is moving at a very fast pace and is likely to complete the project well within the deadline, even with the variation in piling work,鈥� Carvalho said. The construction contract for the elevated corridor has been awarded to Rajendra Singh Bamboo Infra Pvt Ltd (RSBIPL), a Rajasthan-based infrastructure company. The six-lane elevated corridor aims to alleviate the notorious traffic congestion along the bustling Porvorim stretch of NH-66, which serves as a critical artery connecting Goa鈥檚 northern and southern regions. The corridor is expected to enhance travel experiences by providing a smoother, safer, and more efficient route for commuters. Once completed, the project is anticipated to be a game-changer for the region鈥檚 infrastructure, addressing years of traffic bottlenecks and significantly reducing travel time for thousands of daily commuters.

Next Story
Infrastructure Energy

ACME Solar Adds 19.8 MW Wind Power in Gujarat

ACME Solar Holdings Ltd has announced the commissioning of an additional 19.8 MW of wind power capacity at its Shapur project in Gujarat, bringing its total operational renewable energy portfolio to 2,826.2 MW.In May, the company had commissioned 26.4 MW of the planned 50 MW wind project. With the current phase contributing another 19.8 MW, the total installed capacity at Shapur now stands at 46.2 MW.The project is nearing full completion and is expected to be entirely commissioned in the coming days, the company stated.With this addition, ACME Solar continues to strengthen its presence in the..

Next Story
Real Estate

WeWork India Expands With New Centres in Pune, Chennai

Workspace solutions provider WeWork India has announced the leasing of two new centres: WeWork EON Free Zone in Pune and WeWork Ramanujan Intellion Park in Chennai. Together, the new locations will add 200,000 square feet of flexible workspace to its portfolio and are scheduled to open in the second half of FY25.This move marks WeWork India鈥檚 third centre in Chennai, situated at the beginning of Old Mahabalipuram Road within the Littlewood Tower at Ramanujan Intellion Park. Spanning 150,000 square feet across three floors, the fully customised centre will offer 2,400 desks to accommodate ent..

Next Story
Infrastructure Transport

VOC Port鈥檚 Rs 70 Billion Plan Fails to Attract Bidders Again

The VOC Port Authority鈥檚 ambitious Rs 70.56 billion outer harbour project has encountered another significant setback, with its second tender cancelled due to the absence of qualified bidders. Sources confirmed that the tender has been withdrawn from the active bid list, and the authority may now consider restructuring the project.This marks the second failed attempt to initiate the large-scale development at Thoothukudi port. The Request for Proposal (RFP) was reissued in December 2024, following the cancellation of the initial round, which attracted just two applications鈥攆rom Vedanta and..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement