Bengaluru metro rail network to be extended to 170 km: BMRCL
04 Jan 2022
2 Min Read
CW Team
Managing Director of Bengaluru Metro Rail Corporation Limited (BMRCL), Anjum Parwez told the media that the Bengaluru metro network would be increased from 56 km to 170 km, with 17 lakh daily ridership by 2024.
He said that the Challaghatta station would be completed by September this year, and the 3 km stretch Nagasandra-Bangalore International Exhibition Centre (BEIC) would be operational by October-November.
The completion date for both the corridor projects, Byappanahalli-Whitefield and RV Road-Bommasandra, is December 2022, while work for the Kalena Agrahara-Nagawara corridor is expected to be completed by 2024.
Parwez said that the Outer Ring Road (ORR) and KR Puram Kempegowda International Airport (KIA) are on track.
He added that after the completion of the Byappanahalli-Whitefield and ORR-Airport Metro projects, the daily ridership will increase to 17 lakh by 2024.
Last year in May, BMRCL awarded the construction work of Package-1 Central Silk board to Afcons Infrastructure and Package-2 of the Kodibeesanahalli-KR Puram to Shankaranarayana Constructions (SNC). In November, it awarded all the three civil construction contracts from KR Puram to KIA to Nagarjuna Construction Company.
BMRCL requires five years to complete metro corridor projects. However, due to the land acquisition issues, the work on the Nagasandra-BIEC section got delayed.
He said that the ORR-airport corridor would not witness delay due to land acquisition because most of the land is acquired and handed over to the contractors.
He added that U-girders would be used for the construction of a viaduct for the ORR-airport metro corridor.
Delays of other metro projects were also due to issues of land acquisition. SNC has completed 125 piles, and Afcons has completed piling at 118 locations on the ORR stretch, he said.
Managing Director of Bengaluru Metro Rail Corporation Limited (BMRCL), Anjum Parwez told the media that the Bengaluru metro network would be increased from 56 km to 170 km, with 17 lakh daily ridership by 2024.
He said that the Challaghatta station would be completed by September this year, and the 3 km stretch Nagasandra-Bangalore International Exhibition Centre (BEIC) would be operational by October-November.
The completion date for both the corridor projects, Byappanahalli-Whitefield and RV Road-Bommasandra, is December 2022, while work for the Kalena Agrahara-Nagawara corridor is expected to be completed by 2024.
Parwez said that the Outer Ring Road (ORR) and KR Puram Kempegowda International Airport (KIA) are on track.
He added that after the completion of the Byappanahalli-Whitefield and ORR-Airport Metro projects, the daily ridership will increase to 17 lakh by 2024.
Last year in May, BMRCL awarded the construction work of Package-1 Central Silk board to Afcons Infrastructure and Package-2 of the Kodibeesanahalli-KR Puram to Shankaranarayana Constructions (SNC). In November, it awarded all the three civil construction contracts from KR Puram to KIA to Nagarjuna Construction Company.
BMRCL requires five years to complete metro corridor projects. However, due to the land acquisition issues, the work on the Nagasandra-BIEC section got delayed.
He said that the ORR-airport corridor would not witness delay due to land acquisition because most of the land is acquired and handed over to the contractors.
He added that U-girders would be used for the construction of a viaduct for the ORR-airport metro corridor.
Delays of other metro projects were also due to issues of land acquisition. SNC has completed 125 piles, and Afcons has completed piling at 118 locations on the ORR stretch, he said.
Image Source
Next Story
RentenPe and Mygate Partner to Transform Rent Payments in India
Through a strategic partnership, RentenPe and Mygate aim to streamline rent payments and promote financial inclusion by enabling rent-based credit scores for Indian renters. RentenPe, India鈥檚 first Rent Credit Score鈩� platform and a pioneer in rental fintech innovation, has entered a significant alliance with Mygate, the leading community management app in the country. This partnership will transform rent transactions for millions of Indian households by embedding RentenPe鈥檚 payment and rent credit scoring technology directly within the Mygate app. With this integration, all ren..
Next Story
Supreme Unveils New Brand Identity to Elevate Lifestyle
Supreme, a respected name in Indian real estate with a four-decade legacy, has announced a complete rebranding. The move includes the launch of a new logo and a revamped website, both reflecting the group鈥檚 refreshed vision to 鈥楨levate Lifestyle鈥�. This brand transformation represents more than a visual refresh鈥攊t marks a strategic shift in the company鈥檚 mission, visual identity and market positioning. The update will be visible across all of Supreme鈥檚 digital, social and offline communication platforms. At the core of the initiative is a renewed focus on purposeful design..
Next Story
Capri Loans Launches #TarrakiKeHaath Campaign Honouring India鈥檚 Everyday Heroes
Capri Global Capital Ltd (Capri Loans), a leading non-banking financial company, has unveiled its latest brand campaign, #TarrakiKeHaath, a powerful tribute to the everyday hands that build India 鈥� from kirana store owners and taxi drivers to dhaba workers, tailors, and carpenters. Narrated by Capri Loans鈥� long-standing brand ambassador and acclaimed actor Pankaj Tripathi, the campaign celebrates the dignity, resilience, and aspirations of self-employed individuals and small business owners who form the backbone of Bharat鈥檚 economy. Conceptualized by Rediffusion Brand Solutions, the..