Chennai Metro Rail to Launch Trial Run of Driverless Train
24 Oct 2024
2 Min Read
CW Team
Chennai is on the verge of a major improvement in its public transport system as the first trial run of the three-coach driverless train for the Phase II project of the Chennai Metro Rail is set to begin. This project, part of a larger Rs 632.46 billion investment in urban infrastructure, represents a key move towards modernising the city's metro services and enhancing connectivity.
It has been reported that the trial run is expected to take place on October 26, with high-profile figures such as Chief Minister M.K. Stalin and Union Minister of Housing and Urban Affairs Manohar Lal Khattar anticipated to flag off the event. Sources have indicated that final confirmation of the date is expected in the coming days, reflecting the excitement surrounding this development for Chennai鈥檚 transport system.
The driverless train coaches, which were transported from Sri City, arrived at the Poonamallee depot facility on October 17. This marks a significant step in the city's metro expansion. The Chennai Metro Rail Limited (CMRL) has incorporated several new features in these trains to improve passenger comfort, including digital route displays and charging points for electronic devices, catering to the needs of tech-savvy commuters.
At the core of this project is the Rs 1.87 billion depot located at Poonamallee, which spans 40.5 acres and houses 17 buildings. The depot is essential for the maintenance and repair of the trains that will operate within the Phase II network, ensuring the system runs efficiently.
Currently, the train is positioned on the Inspection Bay Line, where checks on key systems such as circuits, brakes, ventilation, and air-conditioning are being carried out. CMRL officials are meticulously testing all components ahead of the trial run. The train will first undergo slow-speed tests of 10-15 kmph on the inspection track before transitioning to the 820-metre ballasted test track for its official trial run.
The Phase II project includes a crucial corridor between Poonamallee and Porur, part of the metro's corridor 4, which runs from Light House to Poonamallee. To support the full operation of this service, CMRL plans to prepare a total of 36 trains, with the next set of coaches expected to arrive from November onwards for further testing.
Chennai is on the verge of a major improvement in its public transport system as the first trial run of the three-coach driverless train for the Phase II project of the Chennai Metro Rail is set to begin. This project, part of a larger Rs 632.46 billion investment in urban infrastructure, represents a key move towards modernising the city's metro services and enhancing connectivity.
It has been reported that the trial run is expected to take place on October 26, with high-profile figures such as Chief Minister M.K. Stalin and Union Minister of Housing and Urban Affairs Manohar Lal Khattar anticipated to flag off the event. Sources have indicated that final confirmation of the date is expected in the coming days, reflecting the excitement surrounding this development for Chennai鈥檚 transport system.
The driverless train coaches, which were transported from Sri City, arrived at the Poonamallee depot facility on October 17. This marks a significant step in the city's metro expansion. The Chennai Metro Rail Limited (CMRL) has incorporated several new features in these trains to improve passenger comfort, including digital route displays and charging points for electronic devices, catering to the needs of tech-savvy commuters.
At the core of this project is the Rs 1.87 billion depot located at Poonamallee, which spans 40.5 acres and houses 17 buildings. The depot is essential for the maintenance and repair of the trains that will operate within the Phase II network, ensuring the system runs efficiently.
Currently, the train is positioned on the Inspection Bay Line, where checks on key systems such as circuits, brakes, ventilation, and air-conditioning are being carried out. CMRL officials are meticulously testing all components ahead of the trial run. The train will first undergo slow-speed tests of 10-15 kmph on the inspection track before transitioning to the 820-metre ballasted test track for its official trial run.
The Phase II project includes a crucial corridor between Poonamallee and Porur, part of the metro's corridor 4, which runs from Light House to Poonamallee. To support the full operation of this service, CMRL plans to prepare a total of 36 trains, with the next set of coaches expected to arrive from November onwards for further testing.
Next Story
MoHUA Plans New Role for Smart City SPVs
In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..
Next Story
ADB Approves $110 Million Loan to Boost Skills in Gujarat
The Asian Development Bank (ADB) has approved a USD 109.97 million (Rs 9.27 billion) results-based loan to support Gujarat鈥檚 efforts to become a global industrial hub by developing a future-ready, skilled workforce.The funding will back the Gujarat skills development programme, led by the Department of Labour, Skill Development and Employment in collaboration with Kaushalya: The Skill University (KSU). The initiative aims to equip the workforce with advanced, industry-aligned skills to meet rising employment demand in high-growth sectors.According to ADB, the programme seeks to strengthen in..
Next Story
SDAL Tests Rudrastra UAV and Bhargavastra Defence System
Solar Defence and Aerospace Limited (SDAL) has successfully completed a key flight test of its indigenous Hybrid VTOL UAV Rudrastra at the Pokharan Firing Range, aligning with Indian Army performance benchmarks for mission adaptability, high endurance, precision engagement, and vertical take-off and landing (VTOL) capability.The trial marks a notable achievement in India鈥檚 Aatmanirbhar Bharat initiative, underscoring advancements in home-grown military technology. The Rudrastra UAV demonstrated a mission radius exceeding 50 km with uninterrupted video relay, a total operational range of over..