MMRCL completes 96% tunneling work for Mumbai Metro Line-3
26 Jul 2021
2 Min Read
CW Team
Mumbai Metro Rail Corporation (MMRC) accomplished its 39th breakthrough at Mahalaxmi Metro Station out of the 42 breakthroughs planned for the Colaba-Bandra-Seepz underground line, 33.5 km long (line-3), of Mumbai Metro.
Tunnel Boring Machine (TBM), known as Tansa-2, built by the Robbins Company, operated by Do臒u艧 and Soma JV, finished 1,117.5 meters of upline drive of tunnelling from the Science Museum Metro Station to Mahalaxmi Metro Station.
To complete the work, TBM Tansa-2 took 257 days, utilising 745 concrete rings.
Package-3 (Mumbai Central鈥揥orli) consists of Acharya Atre Chowk, Science Museum, Mahalaxmi, Worli Metro stations, and Mumbai Central.It is the longest stretch of the corridor, and out of six breakthroughs planned under this package, it has seen three as of now.
The completed three packages completed are- Science Museum to Mahalaxmi 鈥� upline-1117.5m, Science Museum to Worli 鈥� upline-2072m, and downline-2057m
By this breakthrough, the total tunnelling finished on the project is 52.60 km out of the 54.50 km double line, around 96.5% of the entire project.
Under Package-3, three more breakthroughs are remaining. The completion of these breakthroughs would mark the end of the tunnelling work on the 33.5 km long fully underground line, including 27 stations on the route.
MMRC, a joint enterprise Indian Government and Maharashtra government, is the nodal firm responsible for implementing the Mumbai Metro Line-3 project.
Also read: Mumbai Metro-3 project faces cash crunch
Also read: Colaba-Bandra-SEEPZ Metro-3 corridor: MMRC achieves 38th breakthrough
Mumbai Metro Rail Corporation (MMRC) accomplished its 39th breakthrough at Mahalaxmi Metro Station out of the 42 breakthroughs planned for the Colaba-Bandra-Seepz underground line, 33.5 km long (line-3), of Mumbai Metro.
Tunnel Boring Machine (TBM), known as Tansa-2, built by the Robbins Company, operated by Do臒u艧 and Soma JV, finished 1,117.5 meters of upline drive of tunnelling from the Science Museum Metro Station to Mahalaxmi Metro Station.
To complete the work, TBM Tansa-2 took 257 days, utilising 745 concrete rings.
Package-3 (Mumbai Central鈥揥orli) consists of Acharya Atre Chowk, Science Museum, Mahalaxmi, Worli Metro stations, and Mumbai Central.It is the longest stretch of the corridor, and out of six breakthroughs planned under this package, it has seen three as of now.
The completed three packages completed are- Science Museum to Mahalaxmi 鈥� upline-1117.5m, Science Museum to Worli 鈥� upline-2072m, and downline-2057m
By this breakthrough, the total tunnelling finished on the project is 52.60 km out of the 54.50 km double line, around 96.5% of the entire project.
Under Package-3, three more breakthroughs are remaining. The completion of these breakthroughs would mark the end of the tunnelling work on the 33.5 km long fully underground line, including 27 stations on the route.
MMRC, a joint enterprise Indian Government and Maharashtra government, is the nodal firm responsible for implementing the Mumbai Metro Line-3 project.
Image Source
Also read: Mumbai Metro-3 project faces cash crunch
Also read: Colaba-Bandra-SEEPZ Metro-3 corridor: MMRC achieves 38th breakthrough
Next Story
RentenPe and Mygate Partner to Transform Rent Payments in India
Through a strategic partnership, RentenPe and Mygate aim to streamline rent payments and promote financial inclusion by enabling rent-based credit scores for Indian renters. RentenPe, India鈥檚 first Rent Credit Score鈩� platform and a pioneer in rental fintech innovation, has entered a significant alliance with Mygate, the leading community management app in the country. This partnership will transform rent transactions for millions of Indian households by embedding RentenPe鈥檚 payment and rent credit scoring technology directly within the Mygate app. With this integration, all ren..
Next Story
Supreme Unveils New Brand Identity to Elevate Lifestyle
Supreme, a respected name in Indian real estate with a four-decade legacy, has announced a complete rebranding. The move includes the launch of a new logo and a revamped website, both reflecting the group鈥檚 refreshed vision to 鈥楨levate Lifestyle鈥�. This brand transformation represents more than a visual refresh鈥攊t marks a strategic shift in the company鈥檚 mission, visual identity and market positioning. The update will be visible across all of Supreme鈥檚 digital, social and offline communication platforms. At the core of the initiative is a renewed focus on purposeful design..
Next Story
Capri Loans Launches #TarrakiKeHaath Campaign Honouring India鈥檚 Everyday Heroes
Capri Global Capital Ltd (Capri Loans), a leading non-banking financial company, has unveiled its latest brand campaign, #TarrakiKeHaath, a powerful tribute to the everyday hands that build India 鈥� from kirana store owners and taxi drivers to dhaba workers, tailors, and carpenters. Narrated by Capri Loans鈥� long-standing brand ambassador and acclaimed actor Pankaj Tripathi, the campaign celebrates the dignity, resilience, and aspirations of self-employed individuals and small business owners who form the backbone of Bharat鈥檚 economy. Conceptualized by Rediffusion Brand Solutions, the..