Mumbai-Ahmedabad Bullet Train Adds 8th Steel Bridge in Gujarat
23 Jun 2025
2 Min Read
CW Team
The Mumbai-Ahmedabad Bullet Train project has reached another major construction milestone in Gujarat with the successful launch of its eighth steel bridge. This marks nearly 50 per cent progress on the 17 steel structures planned for the state as part of the high-speed rail corridor.
The latest installation is a 100-metre-long steel span positioned over the Dedicated Freight Corridor (DFC) tracks near Bharuch. It is one of 28 steel bridges planned along the entire corridor, of which 17 are located in Gujarat.
Weighing approximately 1,400 metric tons, the bridge stands 14.6 metres tall and spans 14.3 metres in width. It was fabricated at a facility in Trichy and transported to the site using specialised trailers. A launching nose, measuring 84 metres and weighing 600 metric tons, was used to position the bridge into place.
The structure was assembled 18 metres above ground level on temporary trestles using 55,300 high-strength Tor-Shear bolts. It also includes elastomeric bearings and C5-grade protective paint, ensuring a projected lifespan of 100 years. The bridge was launched using two semi-automatic jacks with a capacity of 250 tons each, operated through mac-alloy bars.
To avoid disruption to freight operations on the DFC tracks, the launch was carefully coordinated through phased traffic blocks.
With this latest development, eight steel bridges have now been completed across Gujarat at locations including Surat, Vadodara, Nadiad, Silvassa, and Bharuch. Among the most notable is a 230-metre-long span over the Delhi-Mumbai Expressway near Vadodara, the heaviest structure to date, weighing 4,397 metric tons.
The project is being executed by the National High Speed Rail Corporation Limited (NHSRCL) and forms part of India's first high-speed rail corridor, designed to significantly reduce travel time between Mumbai and Ahmedabad.
The Mumbai-Ahmedabad Bullet Train project has reached another major construction milestone in Gujarat with the successful launch of its eighth steel bridge. This marks nearly 50 per cent progress on the 17 steel structures planned for the state as part of the high-speed rail corridor.The latest installation is a 100-metre-long steel span positioned over the Dedicated Freight Corridor (DFC) tracks near Bharuch. It is one of 28 steel bridges planned along the entire corridor, of which 17 are located in Gujarat.Weighing approximately 1,400 metric tons, the bridge stands 14.6 metres tall and spans 14.3 metres in width. It was fabricated at a facility in Trichy and transported to the site using specialised trailers. A launching nose, measuring 84 metres and weighing 600 metric tons, was used to position the bridge into place.The structure was assembled 18 metres above ground level on temporary trestles using 55,300 high-strength Tor-Shear bolts. It also includes elastomeric bearings and C5-grade protective paint, ensuring a projected lifespan of 100 years. The bridge was launched using two semi-automatic jacks with a capacity of 250 tons each, operated through mac-alloy bars.To avoid disruption to freight operations on the DFC tracks, the launch was carefully coordinated through phased traffic blocks.With this latest development, eight steel bridges have now been completed across Gujarat at locations including Surat, Vadodara, Nadiad, Silvassa, and Bharuch. Among the most notable is a 230-metre-long span over the Delhi-Mumbai Expressway near Vadodara, the heaviest structure to date, weighing 4,397 metric tons.The project is being executed by the National High Speed Rail Corporation Limited (NHSRCL) and forms part of India's first high-speed rail corridor, designed to significantly reduce travel time between Mumbai and Ahmedabad.
Next Story
Lodha Buys Rs 5.67 Billion Transit Units in Mankhurd
Mumbai-based listed real estate developer Lodha Developers Limited has acquired 945 permanent transit camp (PTC) units measuring 339,000 square feet from Arihant Construction Company for Rs 5.67 billion. The transaction, registered on 3 June 2025, is part of Lodha鈥檚 obligations under the Slum Rehabilitation Authority (SRA) scheme related to its ongoing township project in Vikhroli.The acquired units in Mankhurd will be handed over to the SRA to secure development rights for free-sale construction under the Vikhroli project. The deal includes a stamp duty payment of Rs 340.2 million and regis..
Next Story
Prestige Group Plans Rs 500 Billion Launches in FY25
Bengaluru-based listed real estate developer Prestige Group is targeting residential project launches worth over Rs 500 billion in gross development value (GDV) across major Indian markets including Bengaluru, Delhi-NCR, Mumbai, Hyderabad, Chennai, and Goa in the current financial year.According to Praveer Srivastava, Senior Vice President at Prestige Group, the company also aims to launch residential projects worth Rs 140鈥�150 billion by the end of the first quarter of FY26.A major highlight this year is Prestige鈥檚 entry into the Delhi-NCR market, marked by the launch of a Rs 120 billion r..